1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Expansion of DAP and Proposal of Coal Handling Plant, Ammonia, Ammonium Nitrate, Urea, GSSP, Ammonium Fluoride, Nitric Acid. By M/s Paradeep Phosphate Limited | (b)Name of the Company / Organisation | EXPANSION OF DAP AND PROPOSAL OF COAL HANDLING PLANT, AMMONIA, AMMONIUM NITRATE, UREA, GSSP, AMMONIUM FLUORIDE, NITRIC ACID. BY M/S PARADEEP PHOSPHATE LIMITED | (c)Registered Address | Sarpanch gram panchayat kopra.
Tah.-Rajim,
Dist.-Gariaband ,,Gariaband,Chhattisgarh-493887 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Ambikesh Kumar Mishra | (b)Designation (Owner/ Partner/ CEO) | Dy General Manager | (c)Address | Paradeep Phosphates Limited,PPL township,,Jagatsinghapur,Orissa-754145 | (d)Pin code | 754145 | (e)E-mail | yashwantbordia@gmail.com | (f)STD Code. | 672(f)Telephone No. | 259600 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 5(a) Chemical fertilizers
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/OR/IND2/77891/2018 | (d)Master Proposal Number(Single Window) | SW/77777/2018 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 2 | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | 9,10,14,16,19,21,24,25,46,52,71 | (b)Pincode | 754145 | (c)Bounded Latitudes (North) | | From | | Degree | 20.268101 | Minutes | | Second | | From | | Degree | 20.280022 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 86.608243 | Minutes | | Second | | From | | Degree | 86.649256 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 73 L/11, 73 L/12 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 10 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 1 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Orissa | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Orissa | Jagatsinghapur | Jagatsinghapur | PPL township | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | J-11011/370/2009-IA-II(I) | (b)Date of Apply of TOR | 19 Apr 2018 | (c)Date of Issue of TOR / Standard ToR | 19 Jun 2018 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 19 May 2017 | Distance of Public Hearing Venue from the Proposed Project : | 0.500 |
| D A V School PPL premises | State : | Orissa | District : | Jagatsinghapur | Tehsil : | Jagatsinghapur | Village : | PPL Township |
| 150 | Employment , Pollution | District Collector | | |
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | SAP | 0.792 MMTPA | Exisitng capcacity | (2.) | coal handling plant | 7mmtpa | proposed capacity | (3.) | Urea | 1.3 MMTPA | Proposed Capacity | (4.) | Ammonium Nitrate | 0.35 MTPD | Proposed Capacity | (5.) | GSSP | 0.5 MTPD | Proposed capacity | (6.) | PAP | 0.42 MMTPA | Existing Capacity | (7.) | DAP | 1.5 MMTPA (existing) + 0.4 MMTPA (Proposed) | 1.9 MMTPA (Total capacity after expansion) | (8.) | Aluminium Fluoride | 9500 MTPA | Proposed capacity | (9.) | Ammonia | 2.178 MMTPA | Proposed capacity | (10.) | Nitric Acid | 0.33 MTPA (0.05 MMTPA Con. Nit. Acid) | Proposed Capacity | (11.) | Urea | 1.3 MMTPA | Proposed Capacity | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | SAP | 0.792 | Others | MMTPA | Others | Sea | (2.) | Urea | 1.3 | Others | MMTPA | Road,Rail | | (3.) | Ammonium Nitrate | 0.35 | Others | MTPD | Road,Rail | | (4.) | Coal Handling Plant | 7 | Others | MMTPA | Conveyor Belt | | (5.) | PAP | 0.42 | Others | MMTPA | Road,Rail | | (6.) | DAP | 1.9 | Others | MMTPA | Road,Rail | | (7.) | Aluminium Fluoride | 9500 | Tons per Annum | | Road | | (8.) | Nitric Acid | 0.33 | Others | MMTPA | Road | | (9.) | Ammonia | 2.178 | Others | MMTPA | Road | | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 31 Mar 2017 | (iv)Valid Upto | 31 Mar 2022 | (v)File No. | 4898/IND-I-CON-779 | (vi)Application No. | 1453865 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 9459 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 473 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 47 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 100 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 379500 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 379500 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | ammonia | 379500 | Tons per Annum | | IMPORT | Road | | 0.500 | Linkage | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Mar 2018 To 31 May 2018 | (b)Season | Summer | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 105 | 54 | 88 | 100 | (2.) | PM2.5 | | Micro Gram per Meter Cube | 49 | 22 | 42.3 | 60 | (3.) | NOx | | Micro Gram per Meter Cube | 38 | 9.5 | 28.1 | 80 | (4.) | Others | CO | Mili Gram per Meter Cube | 1.05 | 0.35 | 0.86 | 400 | (5.) | SO2 | | Micro Gram per Meter Cube | 20.2 | 4.8 | 17.0 | 80 | |
14.2. No. of Ground Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | Total Hardness | | | mg/l | | 344 | 160 | 200 | 600 | (2.) | pH | | | NA | | 7.99 | 6.48 | 6.5 | 8.5 | (3.) | Chlorides | | | mg/l | | 415 | 66 | 250 | 1000 | (4.) | Fluoride | | | mg/l | | 0.52 | 0.28 | 1 | 1.5 | (5.) | Heavy Metals | | Iron | mg/l | | 0.36 | 0.22 | 0.3 | 00 | (6.) | TSS | | | mg/l | | 1.8 | 1.0 | 0 | 0 | (7.) | TDS | | | mg/l | | 992 | 366 | 500 | 2000 | |
14.3. No. of Surface Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | pH | | mg/l | | 7.84 | 6.85 | C | (2.) | DO | | mg/l | | 7.0 | 4.6 | C | (3.) | COD | | mg/l | | 578 | 10 | C | (4.) | BOD | | mg/l | | 172 | 2.8 | C | (5.) | Others | iron | mg/l | | 0.56 | 0.26 | C | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Night) | A-weighted decibels(dB(A)) | 63.2 | 43.2 | 55 | (2.) | Leq(Day) | A-weighted decibels(dB(A)) | 70.6 | 53.8 | 65 | |
14.5. No. of Soil Sample Monitored locations : 8 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | N(Nitrogen) | Kilogram per hectare | | 376.5 | 275.6 | (2.) | Electric Conductivity | Others | µmhos/cm | 415 | 358 | (3.) | pH | Others | na | 7.88 | 7.18 | (4.) | P(Phosphorus) | Kilogram per hectare | | 24.5 | 16.2 | (5.) | K(Potassium) | Kilogram per hectare | | 175.4 | 87.6 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 2.0 To 5.0 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 2.0 To 4.0 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Surface | | 22730 | 0.760 | Copy of Permission Letter | Pipeline | | Others | PIPE IINE WITH PUMPING STATION | 2462 | 27 Mar 2018 | 18927 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | FROM PLANT | 842 | 2400 | ETP | Reuse within the Plant & Recycling | | 842 | | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 842 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 842 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | SPENT CATALYST | Industrial Waste | | 600 | Tons | 1000 | Road | | Authorized Recyclers | | (2.) | ETP Sludge | Industrial Waste | | 1320 | Tons | 0.0 | Others | Use in DAP/PAP | Others | Use as a Filler | (3.) | Sulpher Muck | Industrial Waste | | 3000 | Tons | 0.0 | Others | Use in DAP Plant | Others | Used as a filler | (4.) | STP Sludge | Industrial Waste | | 660 | Tons | 0.0 | Others | Use in Greenbelt development | Others | Use as Manure | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM2.5 | | Microgram per Meter Cube | 47.00 | 0.0 | 12.18 | 59.18 | 60.00 | (2.) | SO2 | | Microgram per Meter Cube | 24.46 | 0.0 | 10.96 | 48.96 | 80 | (3.) | NOx | | Microgram per Meter Cube | 31.22 | 0.0 | 8.94 | 29.14 | 80 | (4.) | Others(Specify) | NH3 | Microgram per Meter Cube | 24.00 | 0.0 | 58.49 | 82.49 | 400 | (5.) | PM10 | | Microgram per Meter Cube | 74.76 | 0.0 | 30.35 | 126.35 | 100 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | WHRU/Auxiliary boiler | FO | 30 | 5.5 | NOx | | 64.7 kg/hr | (2.) | GSSP BALL MILL | POWER | 40 | 0.8 | Others | SPM | 3.6 | (3.) | GSSP HOT AIR GENERATOR | FO | 30 | 0.5 | Others | SPM | 2.06 | (4.) | DAP A,B,C,D(Each) | POWER | 50 | 2.8 | Others | SPM | 100 mg/Nm3 | (5.) | Sulphur Recovery | Power | 30 | 0.6 | SO2 | | 0.8 | (6.) | DAP- A,B,C,D | POWER | 50 | 2.8 | Others | SPM, NH3, F | 100 MG/NH3, 150 MG/NM3,LESS THAN 10 MG/NM3 | (7.) | DAP - A,B,C.D (EACH) | POWER | 50 | 2.8 | Others | SPM,NH3,F | 100MG/NM3, 150 MG/NM3, <10 MG//NM3 | (8.) | NITRIC ACID | POWER | 50 | 1.25 | NOx | | 100 | (9.) | GSSP SCRUBBER | POWER | 40 | 1.0 | Others | FLUORINE | 0.68 | (10.) | ALUMINIUM FLUORIDE | FO | 2.8 | 0.25 | Others | FLUORIDE | 0.0I36 | (11.) | AMMONIUM NITRATE | POWER | 40 | 1.8 | Others | SPM | 20.25 | (12.) | DAP- A, B, C, D | power | 50 | 2.8 | Others | SPM, NH3, F | 100 mg/nm3, 150 mg/nm3, 10mg/nm3 | (13.) | UREA PT | POWER | 130 | 30 | Others | SPM | 75 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 238584 | (b)Source | GRID | (c)Uploaded Copy of Agreement | Copy of Agreement | (d)Standby Arrangement (Details of DG Sets) | 5mva DG SETS,2 NO 1KVA DG SETS | (e)Stack Height (in m) | 12 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0.0 | (b)Private Land (ha.) | 950 | (c)Government Land (ha.) | 0.0 | (d)Revenue Land (ha.) | 0.0 | (e)Other Land (ha.) | 0.0 | Total Land (ha.) | 950 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 0.0 | (b)Waste/Barren Land (ha.) | 0.0 | (c)Grazing/ Community Land (ha.) | 0.0 | (d)Surface Water Bodies (ha.) | 84.58 | (e)Settlements (ha.) | 121.41 | (f)Industrial (ha.) | 372.08 | (g)Forest (ha.) | 0.0 | (h)Mangroves (ha.) | 0.0 | (i)Marine Area (ha.) | 0.0 | (j)Others (ha.) : Green Belt Area | 347.61 | Total (ha.) | 925.68 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Main Plant | | 70.5 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Critically Polluted Area | None | 00 | Not Applicable | (2.) | NPA | None | 00 | Not Applicable | (3.) | ESZs | None | 00 | Not Applicable | (4.) | Wildlife Corridors | None | 00 | Not Applicable | (5.) | ESAs | None | 00 | Not Applicable | (6.) | WLS | None | 00 | Not Applicable | (7.) | Corridors | None | 00 | Not Applicable | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Defence Installations | | None | 00 | Not Applicable | (2.) | Archaeological Sites | | None | 00 | Not Applicable | (3.) | Forest | | None | 00 | Not Applicable | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 00 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 00 | (b)Land yet to be acquired(Ha) | 00 | (c)Status of Land acquisition if not acquired | Not Applicable as land is already acquired and is | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 00 | (b)No. of Households | 00 | (c)No. of PDFs (Project Displaced Families) | 00 | (d)No. of PAFs (Project Affected Families) | 00 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 00 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | Yes | (i)Details of Water Bodies in Core Area | There are 17 no of ponds in the township as core zone | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Mahanadi River and Atharbanki Creek in along the boundary wall of the site | (ii)Direction of Water Bodies in Buffer Area | North East | (iii)Distance of Water Bodies in Buffer Area | 5.0 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 50 | (b)Permanent Employment-During Operation | 150 | (c)Temporary Employment- During Construction | 617 | (d)Temporary Employment- During Operation | 200 | (e)No. of working days | 365 | (f)Total Manpower | 1017 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 345.61 | (b)Percentage of Total Project Area | 36.38 | (c)No. of Plants to be Planted | 675647 | (d)Funds Allocated for Plantation | 7000000 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | Help to get fertilizers easily | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 2 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1619/SA 070; July 17, 2018 | (ii)Name of the EIA Consultant | M/s EQMS India Pvt. Ltd. | (iii)Address | 304-305, 3rd Floor, Plot No. 16, Rishabh Corporate Tower, Community Centre, Karkardooma, Delhi-110092 | (iv)Mobile No. | 8890836012 | (v)Landline No. | 0113000320 | (vi)Email Id | eqms@eqmsindia.org | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 2 | (ix)Validity of Accreditation | 23 May 2019 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | Please clarify/inform the following:-
- Statutory clearances required/obtained for the existing capacities of SAP, PAP, DAP.
- Applicability of the EIA Notification, 2006 for coal handling plant, Nitric Acid, Aluminium Fluoride, etc, and their categorization.
- Water withdrawal permission only for one year the period from 1/12/2017 to 30/11/2018.
- Baseline and the predicted air quality for PM10 are higher than the prescribed standards. | 21 Sep 2018 | 2. | NA | The correction have been made as per the instruction received | 01 Oct 2018 | 3. | NA | Our earlier observations regarding applicability of EIA Notification, 2006 to certain products/activities (coal handling plant) and the higher PM10 values, are yet to be resolved. Further, in case of the proposal for expansion, certified compliance reports for the earlier ECs dated 23/7/1990, 2/12/2004 & 5/10/2010 need to be necessarily submitted. | 04 Oct 2018 | 4. | NA | The correction have been made as per the instruction received | 11 Oct 2018 | 5. | NA | - Product list needs to be revised vis-a-vis the applicability of the EIA Notification, 2006.
- Being the expansion project, please submit CCR for the ECs dated 2/12/2004 also. | 16 Oct 2018 | 6. | NA | The correction have been made as per the instruction received | 13 Nov 2018 | 7. | NA | As per the norms, proposals for expansion projects are to be considered with the compliance status of the CCRs. Needful may please be done accordingly for consideration of the proposal. | 23 Nov 2018 | 8. | NA | The correction have been made as per the instruction received | 05 Dec 2018 | |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | Reply to ADS as per 4th EAC meeting. | 12 Jun 2020 | 2. | NA | NA | 20 Mar 2019 | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Ambikesh Kumar Mishra | Designation | Dy General Manager | Name of Company (Applicant Name should not be given here) | EXPANSION OF DAP AND PROPOSAL OF COAL HANDLING PLANT, AMMONIA, AMMONIUM NITRATE, UREA, GSSP, AMMONIUM FLUORIDE, NITRIC ACID. BY M/S PARADEEP PHOSPHATE LIMITED | Address | PPL Township , Jagatsinghpur |
|