Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Hikal Limited
(b)Name of the Company / Organisation HIKAL LIMITED
(c)Registered Address Plot no. 629,630-B GIDC Estate Panoli, Ta - Ankleshwar , Bharuch.,,Bharuch,Gujarat-394116
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Dharmesh Panchal
(b)Designation (Owner/ Partner/ CEO) Unithead
(c)Address Plot no. 629,630-B GIDC Estate Panoli, Ta- Ankleshwar, Bharuch.,,Anklesvar,Bharuch,Gujarat-394116
(d)Pin code 394116
(e)E-mail hikallimited123@gmail.com
(f)STD Code. 2646(f)Telephone No. 302100
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(b) Pesticides industry and pesticide specific intermediates (excluding formulations)
5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Minor Activity
(b)Category A
(c)Proposal Number IA/GJ/IND2/77372/2008
(d)Master Proposal Number(Single Window) SW/77367/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot No: 629 and 630B
(b)Pincode 394116
(c)Bounded Latitudes (North)
From
Degree 21.5879
Minutes
Second
From
Degree 72.9930
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 21.5879
Minutes
Second
From
Degree 72.9930
Minutes
Second
(e)Survey of India Topo Sheet No. 45C/14,15, 46G/2, 46G/3
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 3838
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 11
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/98/2008-IA II (I)
(c)Date of Issue of TOR 13 Feb 2008
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 24 Dec 2018
(c)Date of Issue of EC 09 May 2019
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Project Site is located in Notified Industriual Ar
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bhopal
(iii)Letter No. File No: 5-26/2008(ENV)/603
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Apr 29 2018 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)12.1337102319526905Tons per Annum(TPA)Road
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Pharma and cropPhrama and cropPharma and croppharma and crop
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 04 Mar 2016
(iv)Valid Upto 24 Apr 2018
(v)File No. GPCB/ANK/CCA-231(10)/ID-15177/347611
(vi)Application No. 100338
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 600
(b) Funds Allocated for Environment Management (Capital) (in Crores) 203.2
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 3
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 1.24
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 24821.05
(b)Existing quantity of raw material/fuel 6000
(c)Total quantity of raw material/fuel 30821.05
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)NG30821Kilo Litre per DayGujarat GasPipe Conveyor0.5 Fuel Supply AgreementCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2018 To 31 May 2018
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube40.2419.0939.6760
(2.)PM10Micro Gram per Meter Cube84.2258.5183.99100
(3.)SO2Micro Gram per Meter Cube12.34.9412.2180
(4.)NOxMicro Gram per Meter Cube22.229.3322.2280
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Fluoridemg/l0.00.011.5
(2.)Chloridesmg/l1062501000
(3.)TSSmg/l1004080150
(4.)TDSmg/l25055355002000
(5.)Heavy MetalsIronmg/l0.00.00.30.3
(6.)pHNA8.27.36.58.5
(7.)Total Hardnessmg/l290203200600
    14.3.     No. of Surface Water monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.617.1A
(2.)CODmg/l157.5A
(3.)DOmg/l6.03.8A
(4.)BODmg/l5.30.0A
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))73.539.375
(2.)Leq(Night)A-weighted decibels(dB(A))6833.670
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pHOthersNA8.17.2
(2.)K(Potassium)Milligram per Kilogram5.875.02
(3.)N(Nitrogen)Milligram per Kilogram18575
(4.)P(Phosphorus)Milligram per Kilogram8.94.2
(5.)Electric ConductivityMillisiemens per Centimetre390137
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 2 To 5
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.5 To 4
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersGIDC89364 Not Appliacble PipelineOthersGIDC PipelineNA30 Jan 2018760
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Industrial + Domestic38573857ETP+MEE+ATFD+ROOthersFETP+Reuse within Plant Premises3412445
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 3857
(b)Total Discharged Water (Kilolitre per Day) 445
(c)Total Reused Water (Kilolitre per Day) 3412
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Pesticide ResidueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)280Tons6RoadCo-Processing
(2.)ETP SludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)4015Tons7RoadTreatment, Storage and Disposal Facility(TSDF)
(3.)Chemical Intermediate ResidueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)8062.4Tons313RoadOthersIncineration
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube12.350014.326.6580
(2.)NOxMicrogram per Meter Cube22.225007.6429.8680
(3.)PM2.5Microgram per Meter Cube40.245001454.1460
(4.)PM10Microgram per Meter Cube84.225008.1492.36100
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)BoilerNG300.63PM105.8
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 22000
(b)Source DGVCL
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 500 X 4
(e)Stack Height (in m) 11
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 12.135
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 12.135
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0.0
(b)Waste/Barren Land (ha.) 0.0
(c)Grazing/ Community Land (ha.) 0.0
(d)Surface Water Bodies (ha.) 0.0
(e)Settlements (ha.) 0.0
(f)Industrial (ha.) 12.135
(g)Forest (ha.) 0.0
(h)Mangroves (ha.) 0.0
(i)Marine Area (ha.) 0.0
(j)Others (ha.) : NA 0.0
    Total (ha.) 12.135
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant0.98
(2.)OthersOther area + Open Land7.369
(3.)Area for Solid Waste Management0.023
(4.)Green belt3.763
Total (ha.) 12.135
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaAnkleshwer5.15Presently it is not in CEPI
(2.)ESAsArebian Sea40Sea
(3.)ESZsShoolpaneshwer40Wildlife Sanctury
(4.)CorridorsNH 80.5National Highway
(5.)Wildlife Corridorsnone0.0none
(6.)NPANarmada water body11River
(7.)WLSShoolpaneshwer38Wildlife Sanctury
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNone0.0None
(2.)Forestnone0.0None
(3.)Defence Installationsnone0.0None
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 12.135
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 40
(b)Permanent Employment-During Operation 212
(c)Temporary Employment- During Construction 202
(d)Temporary Employment- During Operation 247
(e)No. of working days 365
(f)Total Manpower 701
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt37634037634
(2.)Percentage of Total Project Area33033
(3.)No. of Plants200055507550
(4.)Funds Allocated10.027.7537
    33.       Project Benefits
S. No. Type of Project BenefitsDetails of Project Benefits
NIL
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. High court stay order
(ii)Name of the EIA Consultant Shree Green Consultants
(iii)Address 505, SNS Platina, Nr. Reliance Market, Vesu Surat
(iv)Mobile No. 9712916775
(v)Landline No. 8140086466
(vi)Email Id info@shreegreen.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 30 Jan 2021
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAThe project involves expansion from 3710 TPA to 26905 TPA (both Pharma and crop products), which is wrongly reflected at para 9(b) of Form-2. Please inform about the EC for the present capacity of 3710 TPM (supported with the consent to operate), and the compliance status thereof. 08 Sep 2018
2.NAThe correction have been made as per the instruction received 17 Sep 2018
3.NAPlease see our earlier observations vide query dated 8/9/2018 for the needful. 21 Sep 2018
4.NAThe correction have been made as per the instruction received 02 Nov 2018
5.NAPlease see our earlier observations vide queries dated 8/9/2018, reiterated on 21/9/2018. Please submit copy of the EC dated 24/9/2008 and the CCR dated 1/11/2018 from RO Bhopal for further consideration of the proposal. 11 Nov 2018
6.NAThe correction have been made as per the instruction received 13 Nov 2018
7.NAPlease inform/clarify the following:- - As per the EC dated 24/9/2008, existing production capacity of the unit is 5030 TPA (for 17 products). Whereas, the same is mentioned as 3710 TPA in item 9(b) of Form-2, which includes Pharma-2910 TPA (10 products) & Crop-800 TPA (8 products). - The EC dated 24/9/2008 mentions the project covered under category B of item 5(f). But now, the existing proposed are mentioned under item 5(b) also. - Whether the proposed products under 'crop' are technical grade pesticides. 23 Nov 2018
8.NAThe correction have been made as per the instruction received 03 Dec 2018
9.NAYour reply in response to our observations dated 23/11/2018, is still not clarifying the discrepancies regarding the existing production capacity (as per the EC dated 24/9/2008) and the present proposal for expansion (from 3710 to 26905 TPA). Also, no details are provided in Annexure-3 in respect of products identified as Crops (800 TPA). In case of clarifications, if any, the matter may be discussed with us in the Ministry. 12 Dec 2018
10.NAThe correction have been made as per the instruction received 24 Dec 2018
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantDharmesh Panchal
DesignationUnithead
Name of Company (Applicant Name should not be given here)HIKAL LIMITED