EC Report
1. Project Details
   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/GA/MIS/75629/2018    ii. MoEFCC File No. : 11-20/2018-IA.III    iii.Short narrative of the project: Post Facto CRZ Clearance for “Repair & Renovation of Existing Hotel Structures at Survey No. 242/1 of Saunta Vaddo, Village Calangute, Taluka Bardez, District North Goa, Goa”    iv. Project Sector : INFRA-2    v. Company/Proponent : NALINI DA ROSA FERNANDES
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.GoaNorth GoaBardez
 
vii. Uploaded EC Compliance report by rigional office of MoEFCC: Annexure-Uploaded EC Compliance report viii. Certified Monitoring report by RoMoEF: Annexure-Uploaded Monitoring report    ix.Date of TOR Granted N/A ix.Date of Submission for EC: 26 Jul 2018 x.Project Type: Expansion
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 30 Jun 2018   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: Annexure-Additional Report/Study/Document   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: NIL
Additional Attachments, if any
S.no. Attached File Date of Submission
1. GCZMA Recommendation Letter30 Jun 2018
2. CRZ Form I with Annexures30 Jun 2018
3. Application letters submitted to GCZMA dated 23 march 8 june and 12 june 201830 Jun 2018
4. EDS Reply Letter26 Jul 2018
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1. ADS LetterPLEASE FIND ENCLOSED HEREWITH THE LETTER DATED 11-20-2018-IA III DATED 05-09-2018 In this regard, you are requested ti inform why full facts of the case including demolition orders from the agencies in the State Government and the legal position thereof as contained in the order dated 26.02.2018 of the Honble High Court of Goa was not provided to this Ministry or the /Expert Appraisal Committee. It is further informed that your request has been examined and the competent authority has declined your request for regularization/Post Facto Clearance of the Beach Resort at Survey No.242/1C in Calagunte-Baga in Goa pursuant to the Order dated 10.08.2018 of the Honble Supreme Court in the mnatter of SLP Nos 12032-12035 of 2018 It has been further directed to inform that the aforesaid order dated 10.08.2018 of the Honble Supreme Court shall be strictly implemented and a compliance report shall be submitted to the Goa Coastal Zone Management Authority 06 Sep 2018
2. ADS LetterPLEASE FIND ENCLOSED HEREWITH THE LETTER DATED 11-20-2018-IA III DATED 05-09-2018 In this regard, you are requested ti inform why full facts of the case including demolition orders from the agencies in the State Government and the legal position thereof as contained in the order dated 26.02.2018 of the Honble High Court of Goa was not provided to this Ministry or the /Expert Appraisal Committee. It is further informed that your request has been examined and the competent authority has declined your request for regularization/Post Facto Clearance of the Beach Resort at Survey No.242/1C in Calagunte-Baga in Goa pursuant to the Order dated 10.08.2018 of the Honble Supreme Court in the mnatter of SLP Nos 12032-12035 of 2018 It has been further directed to inform that the aforesaid order dated 10.08.2018 of the Honble Supreme Court shall be strictly implemented and a compliance report shall be submitted to the Goa Coastal Zone Management Authority 06 Sep 2018
3. ADS LetterPLEASE FIND ENCLOSED HEREWITH THE LETTER DATED 11-20-2018-IA III DATED 05-09-2018 In this regard, you are requested ti inform why full facts of the case including demolition orders from the agencies in the State Government and the legal position thereof as contained in the order dated 26.02.2018 of the Honble High Court of Goa was not provided to this Ministry or the /Expert Appraisal Committee. It is further informed that your request has been examined and the competent authority has declined your request for regularization/Post Facto Clearance of the Beach Resort at Survey No.242/1C in Calagunte-Baga in Goa pursuant to the Order dated 10.08.2018 of the Honble Supreme Court in the mnatter of SLP Nos 12032-12035 of 2018 It has been further directed to inform that the aforesaid order dated 10.08.2018 of the Honble Supreme Court shall be strictly implemented and a compliance report shall be submitted to the Goa Coastal Zone Management Authority 06 Sep 2018
4. ADS LetterPLEASE FIND ENCLOSED HEREWITH THE LETTER DATED 11-20-2018-IA III DATED 05-09-2018 In this regard, you are requested ti inform why full facts of the case including demolition orders from the agencies in the State Government and the legal position thereof as contained in the order dated 26.02.2018 of the Honble High Court of Goa was not provided to this Ministry or the /Expert Appraisal Committee. It is further informed that your request has been examined and the competent authority has declined your request for regularization/Post Facto Clearance of the Beach Resort at Survey No.242/1C in Calagunte-Baga in Goa pursuant to the Order dated 10.08.2018 of the Honble Supreme Court in the mnatter of SLP Nos 12032-12035 of 2018 It has been further directed to inform that the aforesaid order dated 10.08.2018 of the Honble Supreme Court shall be strictly implemented and a compliance report shall be submitted to the Goa Coastal Zone Management Authority 06 Sep 2018
5. ADS LetterPLEASE FIND ENCLOSED HEREWITH THE LETTER DATED 11-20-2018-IA III DATED 05-09-2018 In this regard, you are requested ti inform why full facts of the case including demolition orders from the agencies in the State Government and the legal position thereof as contained in the order dated 26.02.2018 of the Honble High Court of Goa was not provided to this Ministry or the /Expert Appraisal Committee. It is further informed that your request has been examined and the competent authority has declined your request for regularization/Post Facto Clearance of the Beach Resort at Survey No.242/1C in Calagunte-Baga in Goa pursuant to the Order dated 10.08.2018 of the Honble Supreme Court in the matter of SLP Nos 12032-12035 of 2018 It has been further directed to inform that the aforesaid order dated 10.08.2018 of the Honble Supreme Court shall be strictly implemented and a compliance report shall be submitted to the Goa Coastal Zone Management Authority 06 Sep 2018
6. ADS LetterPLEASE FIND ENCLOSED HEREWITH THE LETTER DATED 11-20-2018-IA III DATED 05-09-2018 In this regard, you are requested to inform why full facts of the case including demolition orders from the agencies in the State Government and the legal position thereof as contained in the order dated 26.02.2018 of the Honble High Court of Goa was not provided to this Ministry or the /Expert Appraisal Committee. It is further informed that your request has been examined and the competent authority has declined your request for regularization/Post Facto Clearance of the Beach Resort at Survey No.242/1C in Calagunte-Baga in Goa pursuant to the Order dated 10.08.2018 of the Honble Supreme Court in the matter of SLP Nos 12032-12035 of 2018 It has been further directed to inform that the aforesaid order dated 10.08.2018 of the Honble Supreme Court shall be strictly implemented and a compliance report shall be submitted to the Goa Coastal Zone Management Authority 06 Sep 2018
7. ADS LetterPLEASE FIND ATTACH HEREWITH THE LETTER DATED 11-20-2018-IA III DATED 05-09-2018 AND COMPLIANCE THE ORDER 06 Sep 2018
4. Accredited Consultant Details
   i. Accreditation status : Yes    ii. Accreditation No. : 5    iii. Name of Consultant: Aditya Environmental services pvt. ltd.   iv. Address : Aditya Environmental Services Pvt. Ltd. P1, Commercial Complex,   v. Mobile No.: 9821513367   vi. Landline No.: 02242127500   vii. Email Id: naliniff@gmail.com
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : Nalini    ii. Designation : Proprietor    iii. Name of Company(Applicant Name should not be given here) : NALINI DA ROSA FERNANDES    iv. Address : House no. 7/2F, Sauntavaddo, Calangute-Baga, Bardez, Goa 403 516 v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: Annexure-Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
Print