EC Report
1.
Project Details
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? :
No
1.
Project Details
i. Proposal No. :
IA/GJ/IND2/74435/2017
ii. MoEFCC File No. :
J-11011/74/2017-IA.II (I)
iii.Short narrative of the project:
M/s SNF Flopam India Pvt Ltd.
iv. Project Sector :
Industrial Projects-2
v. Company/Proponent :
SNF FLOPAM INDIA PVT. LTD.
vi.Details of State of the project
Details of State of the project
S.no.
State Name
District Name
Tehsil Name
1.
Gujarat
kutch
Anjar
vii.Date of TOR Granted
07 Jul 2017
viii.TOR letter issued by Ministry:
Annexure-TOR letter
ix.Date of Submission for EC:
21 May 2018
x.Project Type:
New
2.
Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP:
Annexure-EIA/EMP
ii.Risk Assessment:
Annexure-Risk Assessment
iii.Public Hearing:
Annexure-Public Hearing
iv. Date of Public Hearing:
06 Feb 2018
v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC:
None
vi. Uploaded Cover Letter:
Annexure-Cover Letter
vii.Remarks:
We have attached here with all documents for application. Forwarding letter is signed by MD of the company. the registered email ID is also belonging to MD of the company. The consultancy organisation has obtained stay against the QCI/NABET scheme from honourable High Court of Gujarat; and the copy of stay is attached on page number A-2 to A-9 of a report further regarding purpose of land usage we need to clarify that the existing plot was already belonging to existing industrial unit named Ever
Additional Attachments, if any
S.no.
Attached File
Date of Submission
1.
CCA Copy of EKC
28 Apr 2018
2.
SNF EDS Answer
28 Apr 2018
3.
SNF EDS REPLY 26.04.2018
06 May 2018
4.
Query Reply 20.05.2018
21 May 2018
3.
Additional Detail Sought
Additional Detail Sought
Sno.
ADS Letter
Remarks
Date of ADS
1.
NA
The EAC, after deliberations, desired for inputs, clarifications and necessary actions in respect of the following: • Discrepancy in the survey no and plot area vis-a-vis the Form-1 submitted and the ToR dated 7th July, 2017. • As per the ToR dated 7th July, 2017 and accordingly the public hearing conducted by the SPCB, was for Survey No.141/1/2 & 142/1 covering an area of 42 acres. Whereas, the present proposal involves more survey nos.139/1, 141/1/2, 142/1 & 147/1 having total area of 70 acres. As such, the said public hearing not in conformity with the EIA Notification, 2006, may not be acceptable. • Firm commitment from the concerned regulatory authority to meet the surface water requirement of 2945 cum/day.
04 Jul 2018
2.
ADS Letter
In our TOR application and all correspondence and the copy of layout, we have mentioned total area as 70 Acre (42 Acre Already utilized as industrial land and 28 Acre Additional proposed). However, as the correspondence address, we have mentioned S. no. 141/1/2 and 142/1 only The other survey numbers 139/1, & 147/1 are part of land parcel and shall be considered in our EC application. We have already given details of Land breakup area in PFR report, section no. 3.8 during our application for TOR. EC Application dated 04/02/2017 (subsequent TOR meeting dated 17/04/2017), we have also given details and mentioned about Land Break-up area during Public Hearing Presentation held on 06/02/2018. The same was mentioned in EIA report submitted for Public hearing in Chapter 1 and Chapter 2
30 Aug 2018
3.
NA
Deferred
03 Oct 2018
4.
ADS Letter
We have uploaded New land documents and other clarifications asked in EAC meeting. A kind request to EAC to consider the case for Appraisal
30 Apr 2019
4.
Accredited Consultant Details
i. Accreditation status :
Yes
ii. Accreditation No. :
Stay order of Hon. High court
iii. Name of Consultant:
Eco Care Soiutions
iv. Address :
306-307, Dwarkesh Complex, Sun Pharma Arcade, Vadodara- 390020
v. Mobile No.:
9427506362
vi. Landline No.:
02652683368
vii. Email Id:
skhot@snf-group.com
5.
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
i. Name of Applicant :
Shital
ii. Designation :
ManagingDirector
iii. Name of Company(Applicant Name should not be given here) :
SNF FLOPAM INDIA PVT. LTD.
iv. Address :
Survey No. 141-1-2-N-142-1, National Highway 8A, East Varsana PO Gopalpuri, Gandhidham
v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
Annexure-Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
Print