EC Report
1. Project Details
   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/GJ/IND2/60354/2016    ii. MoEFCC File No. : IA-J-11011/19/2017-IA-II(I)    iii.Short narrative of the project: PROPOSED EXPANSION OF SPECIALTY CHEMICALS IN EXISTING UNIT    iv. Project Sector : Industrial Projects-2    v. Company/Proponent : PAUSHAK LTD
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.GujaratPanchmahalHalol
2.GujaratPanchmahalHalol
 
vii. Uploaded EC Compliance report by rigional office of MoEFCC: Annexure-Uploaded EC Compliance report viii. Certified Monitoring report by RoMoEF: Annexure-Uploaded Monitoring report    ix.Date of TOR Granted 26 May 2017 x.TOR letter issued by Ministry: Annexure-TOR letter ix.Date of Submission for EC: 03 Apr 2018 x.Project Type: Expansion
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 16 Feb 2018   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: Annexure-Additional Report/Study/Document   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: NIL
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NAThe EAC, after deliberations, insisted for more inputs and clarifications in respect of the following:- • Categorization of project under the EIA Notification, 2006, item 5(b) and/or 5(f), • Revised layout plan for proper demarcation of green belt 10 m width, • Revised water balance for the unit conforming to Zero Liquid Discharge after the proposed expansion, • Revised product list to ensure uniformity/consistency with the ToRs issued vide letter dated 26th May, 2017, • Justification for several expansions during the period 2006 and 2013 as observed by the Regional Office of the Ministry vide their monitoring report dated 9th November, 2017, • Proper explanation to be provided for the accident happened in 2015-2016 and necessary action/precautions taken by the project proponent. 08 Jun 2018
2. ADS LetterPlease find herewith the attached Query Reply for your reference. 18 Jun 2018
4. Accredited Consultant Details
   i. Accreditation status : Yes    ii. Accreditation No. : Stay Order    iii. Name of Consultant: Aqua-Air Environmental Engineers Pvt. Ltd.   iv. Address : 403 Centre Point Nr. Kadiwala School Ring Road Surat - 395 002 Gujarat   v. Mobile No.: 9904433995   vi. Landline No.: 02612460854   vii. Email Id: nikunj.bhatt@alembic.co.in
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : Debangshu    ii. Designation : AVP - Operation    iii. Name of Company(Applicant Name should not be given here) : PAUSHAK LTD    iv. Address : Plot No. 135,136,145,146,147,229,230, Vill: Panelav, PO. Tajpura, Tal. Halol, Dist. Panchmahal - 389350, Gujarat v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: Annexure-Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
Print