   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/RJ/NCP/73561/2018    ii. MoEFCC File No. : 21-16/2018-IA-III    iii.Short narrative of the project: Capital Highstreet (Bikaner)    iv. Project Sector : INFRA-1    v. Company/Proponent : ARHAM REALTY LLP.
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.RajasthanBikanerBikaner
 
   vii.Date of TOR Granted N/A viii.TOR letter issued by Ministry: N/A ix.Date of Submission for EC: 19 Mar 2018 x.Project Type: New
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 19 Mar 2018   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: Annexure-Additional Report/Study/Document   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: NIL
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NAKindly see the final minutes of 30th meeting of EAC Infra-2 03 May 2018
2. ADS LetterRegarding Environmental Clearance of proposed Commercial Project “Capital Highstreet (Bikaner), coming up at Khasra no. 43/19/3 & 44/19/4, village -Ridmalsar Purohitan, Bikaner Rajasthan, promoted by Arham Realty LLP. 26 Jun 2018
3.NAAs per final minutes of 30th meeting of EAC Infra-2, kindly upload concerned required information please. 16 Jul 2018
4. ADS LetterNA 27 Jul 2018
5.NAThe Committee discussed the project in details and noted the information provided by the project proponent is not adequate. After deliberation on the proposal, the EAC sought following documents/certificates: (i) Submit status of application of availability of water from PHED/CGWA. (ii) Submit detailed traffic impact study duly endorsed by the concerned authority. (iii) Submit details of tree cutting and plan for green belt development. (iv) Submit Revised ECBC details as discussed. (v) Submit revised Plan for Corporate Environment Responsibility (CER) as specified under Ministry’s Office Memorandum vide F.No. 22-65/2017-IA.III dated 1st May 2018 shall be prepared and submitted. 03 Oct 2018
6. ADS LetterNA 13 Oct 2018
4. Accredited Consultant Details
   i. Accreditation status : Yes    ii. Accreditation No. : S.No.68    iii. Name of Consultant: Gaurang Environmental Solutions Pvt Ltd   iv. Address : 501 Soni's Paris Point near Collectorate Circle, Bani Park Jaipur   v. Mobile No.: 9782074776   vi. Landline No.: 01414029115   vii. Email Id: gaurangenviro@gmail.com
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : Kuldeep    ii. Designation : AVP    iii. Name of Company(Applicant Name should not be given here) : ARHAM REALTY LLP.    iv. Address : S 33/34, JDA shopping centre,Amarpali circle, Jaipur,Rajasthan v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: Annexure-Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency