EC Report
1. Project Details
   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/MH/CMIN/73035/2018    ii. MoEFCC File No. : J-11015/537/2008-IA-II(M)    iii.Short narrative of the project: Dinesh (Makardhokra - III) OC    iv. Project Sector : Coal Mining    v. Company/Proponent : Western Coalfields Limited
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.MaharashtraNagpurUmred
 
   vii.Date of TOR Granted N/A viii.TOR letter issued by Ministry: N/A ix.Date of Submission for EC: 16 Feb 2018 x.Project Type: Expansion under para 7(ii)
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i. Uploaded EC Compliance report by rigional office of MoEFCC: Annexure-Uploaded EC Compliance report ii. Certified Monitoring report by RoMoEF: Annexure-Uploaded Monitoring report iii. Uploaded Form I: Annexure-Uploaded Form I   iv. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: None   v. Uploaded Cover Letter: Annexure-Cover Letter   vi.Remarks: NIL
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NADeferred 01 May 2018
2. ADS LetterSubsequent to the MoM of 28th EAC meeting held on 17-4-18, it is to submit for reconsideration of observation of EAC regarding conduction of fresh Public Hearing (PH). Now, as PH already conducted as per EIA, 2006 on 22-10-2010 and based on attached document, EC is solicited under EIA Notification 2006 with exemption of fresh PH for Dinesh (Makardhokra - III) OC Expansion Project for Expansion in Capacity by 40 % from 3.0 MTPA to 4.2 MTPA with in the already sanctioned EC land Area. 11 May 2018
3.NADeferred 31 Jul 2018
4. ADS LetterAs directed by EAC in its meeting held on 24.07.2018, since the Stage I FC for the quantum of forest land involved is yet to be secured, a mining plan (including mine closure plan) for operating within the non-forest land only as PHASE-I in a land area of 919.63 ha has been prepared and the approval of the WCL Board based on the decision taken during the meeting held on 24/08/2018 has been communicated vide letter no. WCL/BD/SECTT/BM-303/2018/409 dated 28.08.2018. Accordingly, the necessary modification in the Form-1 & Addendum EIA/EMP has been done and the copy of each of the Mining Plan (PHASE- I), Board Approval & Addendum EIA/EMP along with Form 1 of PHASE - I is enclosed for your kind consideration for grant of EC to Dinesh (Makardhokra-III) Opencast Coal Mine Expansion Project from 3.00 MTPA to 4.20 MTPA as Phase–I. 29 Aug 2018
4. Accredited Consultant Details
   i. Accreditation status : Yes    ii. Accreditation No. : QCI/NABET/ENV/AOC/16/05/0166 Dated 24.05.2016, Re-    iii. Name of Consultant: CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED   iv. Address : Kanke Road, Ranchi   v. Mobile No.: 8275970074   vi. Landline No.: 0651 2231506   vii. Email Id: wclenv@yahoo.in
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : KAUSHIK    ii. Designation : G.M (MINING)/ ENVIRONMENT.    iii. Name of Company(Applicant Name should not be given here) : Western Coalfields Limited    iv. Address : Coal Estate Civil lines, Nagpur-440001 v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: Annexure-Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency