   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/MH/CMIN/72758/2018    ii. MoEFCC File No. : J-11015/151/2014-IA-II(M)    iii.Short narrative of the project: EXPANSION OF BHATADI OC EXPANSION    iv. Project Sector : Coal Mining    v. Company/Proponent : Western Coalfields Limited
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.MaharashtraChandrapurChandrapur
 
   vii.Date of TOR Granted N/A viii.TOR letter issued by Ministry: N/A ix.Date of Submission for EC: 01 Mar 2018 x.Project Type: Expansion under para 7(ii)
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i. Uploaded EC Compliance report by rigional office of MoEFCC: Annexure-Uploaded EC Compliance report ii. Certified Monitoring report by RoMoEF: Annexure-Uploaded Monitoring report iii. Uploaded Form I: Annexure-Uploaded Form I   iv. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: Annexure-Additional Report/Study/Document   v. Uploaded Cover Letter: Annexure-Cover Letter   vi.Remarks: NIL
Additional Attachments, if any
S.no. Attached File Date of Submission
1. Reply to EDS raised by MS01 Mar 2018
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NADeferred 01 May 2018
2. ADS LetterSubsequent to the MoM of 28th EAC meeting held on 17-04-2018, it is to submit for reconsideration of observation of EAC regarding conduction of fresh Public Hearing (PH). Now, as PH already conducted as per EIA, 1994 on 20-07-2004 and based on attached document, EC is solicited under EIA Notification 2006 with exemption of fresh PH for Expansion of Bhatadi OC Project for Expansion in Capacity by 40 % from 0.9750 MTPA to 1.365 MTPA with in the already sanctioned EC land Area. 02 Jul 2018
3.NAThe Committee, after detailed deliberations, observed that their recommendation during the meeting held on 17-18 April, 2018 in respect of conducting fresh public hearing is yet to be complied with. The Committee insisted for the same for further consideration of the proposal. The proposal was therefore deferred for the needful on the above lines. 12 Sep 2018
4. ADS LetterThe details of information sought has been sent by e-mail to MoEF&CC on 28.09.2018. The same has been uploaded for kind perusal and grant of EC. 08 Oct 2018
5. ADS LetterThe details of information sought has been sent by e-mail to MoEF&CC on 28.09.2018. The same has been uploaded for kind perusal and grant of EC. 08 Oct 2018
6.NANA 08 Feb 2019
7. ADS LetterSubsequent to the observation of EAC during its 42nd meeting held on 24th January, 2019, the additional information has been compiled and attached herewith for kind consideration please. It is most earnestly solicited that the subject application may kindly be re- considered for grant of Environmental Clearance for 40% enhancement in production capacity for Expansion of Bhatadi OC (from 0.975 MTPA to 1.365 MTPA) within existing land area of 847.37 ha with exemption of fresh Public Hearing as per the O.M. Dated 15.09.2017 for a period of one year only i.e. up to 31st March, 2020. 25 Feb 2019
8.NAkindly comply with recommendation of EAC regarding Public Hearing 17 Jun 2019
9. ADS LetterPlease find attached herewith the detailed complaince report regarding Public Hearing as per directives of EAC. SUbmitted for your kind perusal. 11 Oct 2019
10.NAThe EAC, after deliberations observed that although earlier observation of EAC was complied by Project proponent for conducting public hearing. However, presence of schedule 1 species requires conservation plan duly approved by concerned statutory authority as the buffer zone area falls under buffer zone of Tadoba Andhari Tiger Reserve. "The proposal was deferred for want of submission of wild life conservation plan, duly approved by concerned statuary authority and details of pollution mitigation measures for villages(if any) to be affected by mining operations." Further, EAC desired that no OB dump or mining activity shall be dumped/carried out in and around 150 m of distance from bank of river. 03 Dec 2019
11. ADS LetterPlease find attached herewith the detailed complaince report as per directives of EAC (50th EAC meeting). Submitted for your kind perusal. 30 Dec 2019
12. ADS LetterPlease find attached herewith the detailed compliance report as per directives of EAC (50th EAC meeting). Submitted for your kind perusal. 30 Dec 2019
4. Accredited Consultant Details
   i. Accreditation status : Yes    ii. Accreditation No. : QCI/NABET/ENV/AOC/16/05/0166    iii. Name of Consultant: CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED   iv. Address : Jaripatka, Nagpur Maharashtra   v. Mobile No.: 8275970074   vi. Landline No.: 0712 2807209   vii. Email Id: wclenv@yahoo.in
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : KAUSHIK    ii. Designation : G.M (MINING)/ ENVIRONMENT.    iii. Name of Company(Applicant Name should not be given here) : Western Coalfields Limited    iv. Address : Coal Estate Civil lines, Nagpur-440001 v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: Annexure-Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency