Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Dhenkanal Steel Plant
(b)Name of the Company / Organisation RUNGTA MINES LTD
(c)Registered Address Rungta Office, Main Road, At/PO: Barbil, Odisha,Keonjhar,Orissa-758035
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Ajaya Kumar Mallick
(b)Designation (Owner/ Partner/ CEO) CGM (Elect)
(c)Address RUNGTA MINES LIMITED,MAIN ROAD,BARBIL ,KEONDHAR ,ODISHA,,Barbil,Keonjhar,Orissa-758035
(d)Pin code 758035
(e)E-mail rml.forest@gmail.com
(f)STD Code. 676(f)Telephone No. 275481
(g)Fax No. 06767276161
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Project/Activity3(a) Metallurgical industries (ferrous & non ferrous)
3(b) Cement plants
4(b) Coke oven plants
(b)Category A
(c)Proposal Number IA/OR/IND/80884/2018
(d)Master Proposal Number(Single Window) SW/99625/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 1
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Refer Annexure III of Form I
(b)Pincode 759121
(c)Bounded Latitudes (North) FROM 20.7538 To 20.7733
(d)Bounded Longitudes (East) FROM 85.2866 To 85.3125
(e)Survey of India Topo Sheet No. F45T5
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 95
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 1
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Orissa
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)OrissaDhenkanalHindolJharbandh, Galpada and Tarkabeda
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11011/309/2018-IA-II(I)
(b)Date of Apply of TOR 30 Sep 2018
(c)Date of Issue of TOR / Standard ToR 10 Dec 2018
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :03 Feb 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :07 Mar 2019
Distance of Public Hearing Venue from the Proposed Project :20
Tehsil office of Hindol
State :Orissa
District :Dhenkanal
Tehsil :Hindol
Village :Hindol
300Employment opportunities, education, drinking water facilities, development of village roads, cleaning of village ponds, pollution control, medical facilities, pension for senior citizensOthersAdditional District Magistrate
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Beneficiation Plant2 X2.69 MTPAEach phase: 1X 2.69 MTPA
(2.)Pelletisation Plant2X1.2 MTPA+10%Each phase : 1 X1.2 MTPA +10%,
(3.)Coal Washery1X400 TPH + 1X235 TPHPh-1: 1X400 TPH, Ph-2: 1X235 TPH
(4.)Coke Oven Plant16 batteries X 70000 TPAPh 1-6 batt. Ph2- 10 batt.
(5.)RM(TMT/Flat/Round/Wire Rod/Structural/others)4X0.2 MTPAPh-1 1X0.2 + 2X0.3MTPA, Ph-2 5X0.2+ 2X0.3MTPA
(6.)Strip Mill/Sheet/Coil/ Wire&Bar Mill/Wire Rope1X0.45 MTPAPh-1:1X0.4MTPA, Ph-2:1X0.45+ 1X0.4 MTPA
(7.)Producer Gas Plant20X3000 Nm3/hPh-1: 10X3000 Nm3/h, Ph-2: 10X3000 Nm3/h
(8.)Oxygen Plant1 X 100 + 1 X 180 TPDPh-1:1 X 100 TPD, Ph-2: 1 X 180 TPD
(9.)Lime Plant1 X 100 + 1 X 180 TPDPh-1: 1 X 300 TPD, Ph-2: 1 X 180 TPD
(10.)Captive Power Plant385 MWPh-1: 217 MW, Ph-2: 168 MW
(11.)WHRB based CPP135 MWPh-1: 67 MW, Ph-2: 68 MW
(12.)DRI Kiln exit gas based boiler1 X 60 + 1 X 90 TPHPh-1: 1 X 50 TPH, Ph-2:1 X 90 TPH
(13.)Coke Oven Gas based CPP1 X 60 + 1 X 100 TPHPh-1: 1 X 60 TPH, Ph-2:1 X 100 TPH
(14.)DRI Plant2X500 + 4X600 TPD +20% extraPh-1 : 2X500 + 2X600 TPD Ph-2 : 2 X 600 TPD
(15.)Mini Blast Furnace1X600 + 1X1050 CUMPh-1: 1X600 CUM Ph-2: 1X1050 CUM
(16.)Steel Melting via IF Route7X 20 T IF + 4X20 T LRFPh-1: 7X 20 T IF + 4X20 T LRF, Ph-2: Nil
(17.)Steel Melting via EAF -VGD-AOD Route1X90 + 1X160 T EAF, LRF, VGDPh-1: 1X90 T EAF & VGD, Ph-2: 1X160 T EAF & VGD
(18.)CCM (Billets/ Bloom Caster/ Slab)1 nos. X 3 strandsPh-1: 2 nos. X 3 strands. Ph-2: 4 nos. X 3 strands
(19.)Ductile Pipe Plant2X0.2 MTPAPh-1: 1X0.2 MTPA, Ph-2: 1X0.2 MTPA
(20.)Cement Plant1 X 2600 + 1 X 2300 TPDPh-1: 1 X 2600 TPD, Ph-2: 1 X 2300 TPD
(21.)AFBC/CFBC based CPP2X125 + 4X250 TPHPh-1: 2X125 + 2X250 TPH, Ph-2: 2X250 TPH
(22.)Sinter Plant1X64 + 1X110 sq.mPh-1: 1X64 sq.m. Ph-2: 1X110 sq.m.
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Beneficiation Plant5.4OthersMTPARoad,Rail
(2.)Pelletisation Plant2.948OthersMTPARoad,Rail,OthersInhouse
(3.)Coal Washery4.141OthersMTPARoad,Rail
(4.)MBF1.559OthersMTPAOthersIn house
(5.)Sinter1.663OthersMTPAOthersIn house
(6.)SMS via EAF1.925OthersMTPAOthersIn house
(7.)Oxygen Plant0.098OthersMTPAOthersIn house
(8.)Lime Plant0.3045OthersMTPAOthersInhouse
(9.)CPP-AFBC/CFBC250Mega Watt(MW)OthersCaptive use
(10.)DRI1.547OthersMTPAOthersIn house
(11.)Rolling Mill1.6OthersMTPARoad,Rail
(12.)Ductile Pipe0.4OthersMTPARoad,Rail
(13.)CPP-WHRB135Mega Watt(MW)OthersCaptive use
(14.)MBF Gas Power Plant31Mega Watt(MW)OthersCaptive use
(15.)Coke oven Based Power Plant36Mega Watt(MW)OthersCaptive use
(16.)SMS via IF Route0.539OthersMTPAOthersIn house
(17.)Strip Mill/Sheet/Coil/Wire/others0.85OthersMTPARoad,Rail
(18.)PGP480OthersMillion NM cube/AnnumOthersIn house
(19.)Billets2.415OthersMTPAOthersIn house
(20.)Cement Plant1.686OthersMTPARoad,Rail
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 7863.9
(b) Funds Allocated for Environment Management (Capital) (in Crores) 98.67
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 19.59
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 23.75
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 17.02
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 17.02
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)coke Breeze216373Tons per AnnumSouth AfricaRoad,Rail126 LOACopy of Linkage
(2.)Dolomite537581Tons per AnnumRourkelaRoad300 Open MarketCopy of Linkage
(3.)Iron Ore fines6996368Tons per AnnumOwn Mines/OMC/other private MinesRoad,Rail300 OthersEC letterCopy of Linkage
(4.)Silica Component31098Tons per AnnumRaigarhRoad,Rail500 Open MarketCopy of Linkage
(5.)Scrap29293Tons per AnnumRourkelaRoad300 Open MarketCopy of Linkage
(6.)Iron ore lump (BF grade)657195Tons per AnnumOwn Mine/OMC/other private MinesRoad,Rail300 OthersEC letterCopy of Linkage
(7.)Coal5936621Tons per AnnumSouth Africa/Talcher CoalfieldRoad,Rail126 Open MarketCopy of Linkage
(8.)Coking coal1691200Tons per AnnumSouth Africa/Talcher CoalfieldRoad,Rail126 Open MarketCopy of Linkage
(9.)Pig Iron78222Tons per AnnumKamanada Steel PlantRoad350 OthersEC letterCopy of Linkage
(10.)Flocculant270Tons per AnnumRourkelaRoad300 Open MarketCopy of Linkage
(11.)Quartz81081Tons per AnnumRaigarhRoad500 Open MarketCopy of Linkage
(12.)Bentonite67543Tons per AnnumRourkelaRoad300 Open MarketCopy of Linkage
(13.)GYPSUM33412Tons per AnnumAndhra PradeshRoad500 Open MarketCopy of Linkage
(14.)Limestone1934689Tons per AnnumRajgangpurRoad350 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2018 To 31 May 2018
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube7139.671100
(2.)NOxMicro Gram per Meter Cube21.7921.680
(3.)SO2Micro Gram per Meter Cube16.16.315.980
(4.)PM2.5Micro Gram per Meter Cube42.722.842.260
    14.2.     No. of Ground Water monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSmg/l1610..
(2.)Total Hardnessmg/l546249200600
(3.)Chloridesmg/l245272501000
(4.)TDSmg/l14164565002000
(5.)Fluoridemg/l0.730.211.5
(6.)pHNA7.56.66.58.5
    14.3.     No. of Surface Water monitoring locations : 11
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.97.4A
(2.)BODmg/l255E
(3.)CODmg/l3914E
(4.)DOmg/l6.96.7A
    14.4.     No. of Ambient Noise monitoring locations : 10
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))42.5139.1245
(2.)Leq(Day)A-weighted decibels(dB(A))52.1648.1255
    14.5.     No. of Soil Sample Monitored locations : 2
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)Electric ConductivityMillisiemens per Centimetre0.1670.111
(2.)K(Potassium)Kilogram per hectare33261
(3.)pH7.86.2
(4.)P(Phosphorus)Kilogram per hectare81.932.76
(5.)N(Nitrogen)Kilogram per hectare9.525.32
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 6.34 To 8.82
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.37 To 4.52
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface708007 Not Appliacble PipelineIntake WellNA26 Aug 20132950
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Coal Washery1454.41454.4RecycleReuse within the Plant & Recycling1454.4
(2.)MBF3847.923847.92Common Monitoring BasinReuse within the Plant & Recycling3847.92
(3.)SMS101.52101.52Common Monitoring BasinReuse within the Plant & Recycling101.52
(4.)Pellet Plant217.92217.92Common Monitoring BasinReuse within the Plant & Recycling217.92
(5.)Drinking Water & Sanitary450450Soak Pit SystemOthersSoak Pit0450
(6.)Strip Mill109.20109.20Common Monitoring BasinReuse within the Plant & Recycling109.20
(7.)PGP295.44295.44Common Monitoring BasinReuse within the Plant & Recycling295.44
(8.)Sinter Plant707.04707.04Common Monitoring BasinReuse within the Plant & Recycling707.04
(9.)Rolling Mill205.44205.44Common Monitoring BasinReuse within the Plant & Recycling205.44
(10.)Power Plant1360.81360.8Common Monitoring BasinReuse within the Plant & Recycling1360.8
(11.)Benefication4339.94339.9Tailing PondReuse within the Plant & Recycling4339.9
16.1.
(a)Total Waste Water Generation 13089.58
(b)Total Discharged Water 450
(c)Total Reused Water 12639.58
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Reject from rolling millIndustrial Waste14694Tons0RoadOthersreused in steel making within project
(2.)TailingIndustrial Waste2156240Tons0OthersPipelineOthersTailing Pond
(3.)MiddlingIndustrial Waste1759908Tons0Conveyor BeltOthersreused in FBB within project
(4.)Bag filter dust from DRIIndustrial Waste27822Tons0RoadOthersreused in sinter making
(5.)Reject from strip millIndustrial Waste7806Tons0RoadOthersreused in steel making
(6.)Baf filter dust from IFIndustrial Waste13123Tons0RoadOthersReused in sinter making
(7.)Reject from WasheryIndustrial Waste310572Tons0RoadOthersDisposed in project area
(8.)Dust from pelletIndustrial Waste240772Tons0RoadOthersReused in sinter making
(9.)BF SlagIndustrial Waste467775Tons0RoadOthersreutilized in making PBS Cement
(10.)Mill Scale from SMSIndustrial Waste38500Tons0RoadOthersReused in cement making
(11.)Dust from MBFIndustrial Waste219713Tons0RoadOthersreused in sinter making
(12.)Slag from IFIndustrial Waste104050Tons0RoadOthersMetal Recovery
(13.)Mill Scale from IFIndustrial Waste10780Tons0RoadOthersReused in Sinter making
(14.)Coal ash from PGPIndustrial Waste55661Tons0RoadOthersSold to brick manufacturers
(15.)Bag filter dust from coke ovenIndustrial Waste50736Tons0RoadOthersReused in sinter making
(16.)Kiln AccretionIndustrial Waste27822Tons0RoadOthersDisposed in solid waste disposal area
(17.)Bag filter dust from EAFIndustrial Waste42989Tons0RoadOthersreused in sinter making
(18.)CharIndustrial Waste285248Tons0RoadOthersReused in FBB
(19.)ESP DustIndustrial Waste69554Tons0RoadOthersReused in sinter making
(20.)Mill Scale from Strip millIndustrial Waste9541Tons0RoadOthersSold to cement manufacturers
(21.)Sinter return finesIndustrial Waste581900Tons0RoadOthersReused in sinter making
(22.)Slag from EAFIndustrial Waste208589Tons0RoadOthersMetal Recovery
(23.)Sludge from GCPIndustrial Waste33311Tons0RoadOthersReused in sinter making
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube42.74.75.2747.97160
(2.)NOxMicrogram per Meter Cube21.74.78.4530.15180
(3.)PM10Microgram per Meter Cube714.79.1880.181100
(4.)SO2Microgram per Meter Cube16.14.718.6534.75180
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DRI-2x600 TPD, WHRB K3 & K4Coal803SO235.75
(2.)Pellet plant ph-1Producer Gas Plant704OthersPM2.51.41
(3.)DRI K1 & K2, CDHCoal301.5OthersPM 2.50.19
(4.)Washery (2.616 MTPA)Coal351.7PM100.47
(5.)DRI K3 & K4, RMHSCoal351.8PM100.76
(6.)Washery (2.616 MTPA)Coal351.7OthersP 2.50.27
(7.)Sinter Plant (0.611 MTPA)Coke breeze452OthersPM 2.50.48
(8.)SMS-IF (06)-352PM100.61
(9.)Rolling Mill (0.8 MTPA RH2)LHHS603NOx3.89
(10.)Rolling Mill (0.8 MTPA RH3)LSHS603PM100.48
(11.)Rolling Mill (0.8 MTPA RH 4)LSHS603NOx3.89
(12.)Cement Plant (2600 TPD- Crushing)-302PM100.82
(13.)Cement Plant (2600 TPD-RM/Kiln)Coal804SO20.82
(14.)Cement Plant (2600 TPD-Plant Mill)-604PM104.95
(15.)Cement Plant (2600 TPD-Packing)-351OthersPM 2.50.09
(16.)Power Plant (2x125 TPH-FBB1)Coal, Middling, Coal Fine, Char906PM101.94
(17.)BF gas power plant (11 MW)BF Gas302.5OthersPM 2.50.24
(18.)DRI k5&K6- RMHSCoal351.8PM100.76
(19.)DRI K5&K6-CDHCoal301.5PM100.42
(20.)DRI K&&K6-PSBCoal351.8OthersPM 2.50.43
(21.)Pellet plant Phase II (1x1434 MTPA) RMHSProducer gas301.5PM100.34
(22.)Blast Furnace (0.992 MTPA) StoveCoke352.2SO27.78
(23.)Sinter Plant (1.051 MTPA) - MainCoke Breeze806.5NOx0.04
(24.)Coke Oven (0.7 MTPA)Coke1003.2PM101.52
(25.)Rolling Mill RHF (0.3 MTPA) - 1LSHS603.6PM100.72
(26.)Rolling Mill RHF (0.3 MTPA) - 1LSHS603.6SO26.58
(27.)Rolling Mill RHF (0.2 MTPA) - 3LSHS603PM100.48
(28.)Rolling Mill RHF (0.2 MTPA) - 3LSHS603NOx3.89
(29.)Strip Mill (0.4 MTPA)LSHS804PM100.97
(30.)Powe Plant (2x250 TPH FBB)-2Coal, Middling, coal fines, char1107SO234.56
(31.)Power plant (dedusting 1)Coal , char455OthersPM2.51.13
(32.)Rolling Mill RHF (0.3 MTPA) - 2LSHS603.6SO26.58
(33.)Strip Mill (0.4 MTPA)LSHS804SO210.58
(34.)DRI 2X500 TPD WHRB - K1&K2Coal802.75PM102.604
(35.)Pellet Plant RMHS - PEP02Producer Gas301.5PM100.34
(36.)Sinter (0.611 MTPA) ESP-MSCoke Breeze555PM109.01
(37.)Rolling Mill (0.8 MTPA) RH-4LSHS603PM100.48
(38.)PGP 10X3000 NM3/hCoal302OthersPM2.50.16
(39.)Producer Gas Plant 10X3000 NM3/hCoal302PM100.27
(40.)PGP 10X3000 NM3/hCoal302OthersPM2.50.16
(41.)Cement Plant (2300 TPD) Crushing-302OthersPM2.50.4
(42.)Cement Plant (2300 TPD) - RM/KilnCoal804SO20.49
(43.)Power Plant 2X250 TPH FBBCoal, Midling, Coal Fine, Char1107PM103.89
(44.)Power Plant 2X250TPH FBBCoal, Midling, Coal Fine, Char1104SO234.56
(45.)BF gas based power plantBF gas303NOx1.31
(46.)Coke Over Gas based PPCoke Over Gas303SO23.5
(47.)Coke Oven gas based PPCoke Oven Gas303OthersPM2.50.49
(48.)SMS IF-07-351.8PM100.31
(49.)Cement Plant (2600 TPD) RM/ KilnCoal804OthersPM2.52.11
(50.)SMS (EAF - 160T)-705PM105.81
(51.)Cement Plant (2300 TPD) Pa-cking-351OthersPM2.50.08
(52.)DP Mill (1x0.2 MTPA)LSHS603NOx2.78
(53.)Coke oven (0.7 MTPA)Coke1003.2OthersPM2.50.87
(54.)BF (0.992 MTPA) StoveCoke352.2OthersPM2.50.25
(55.)BF (0.992 MTPA) DedustingCoke472.2OthersPM2.50.49
(56.)Sinter Plant (1.051 MTPA) - MainCoke Breeze806.5PM1015.46
(57.)Rolling Mill RHF (0.3 MTPA) - 02LSHS603.6PM100.72
(58.)Rolling Mill RHF (0.2 MTPA) - 03LSHS603OthersPM2.50.28
(59.)Strip Mill (0.4 MTPA)LSHS804OthersPM2.50.56
(60.)DP Mill (0.2 MTPA)LSHS603OthersPM2.50.28
(61.)Cement Plant (2300 TPD) RM/KilnCoal804PM103.12
(62.)Power Plant 2X250 TPH FBBCoal, Middling, Coal Fines, Char1107OthersPM2.52.23
(63.)BF Gas based power plantBF Gas303PM100.77
(64.)DRI K1&K2 PSBCoal351.7PM100.63
(65.)Pellet Plant PEP - 01Producer Gas704PM102.45
(66.)Pellet Plant PEP - 01Producer Gas704NOx0.08
(67.)Pellet Plant RMHS PEP - 02Producer Gas301.5OthersPM2.50.19
(68.)Pellet Plant RMHS PEP - 03Producer Gas301.5PM100.17
(69.)DRI K3&K4 RMHSCoal351.8OthersPM2.50.43
(70.)DRI K3&K4 PSBCoal351.8OthersPM2.50.43
(71.)BF Stove (0.567 MTPA) BF - 01Coke351.8SO24.44
(72.)BF SH (0.567 MTPA) BF - 02Coke471.8PM100.48
(73.)SMS - IF 04-352PM100.61
(74.)SMS IF 04-352OthersPM2.50.35
(75.)SMS IF 05-352OthersPM2.50.35
(76.)SMS IF 06-352OthersPM2.50.35
(77.)SMS IF 07-351.8OthersPM2.50.18
(78.)SMS (90T) EAF - EAF01-604PM103.27
(79.)Rolling Mill (0.8 MTPA) RH-03LSHS603SO26.58
(80.)Rolling Mill (0.8 MTPA) RH - 03LSHS603NOx3.89
(81.)DRI-K1&K2 CDSCoal301.5PM100.34
(82.)DRI(2x600 TPD K5&K6)Coal803SO235.75
(83.)Pellet Plant (1X1.143 MTPA) PHSProducer Gas301.5PM100.34
(84.)Rolling Mill RHF (0.3 MTPA) - 2LSHS603.6OthersPM2.50.42
(85.)SMS EAF - 160T-705OthersPM2.53.34
(86.)Power Plant 2X250 TPH FBBCoal, Middling, Coal Fines, Char1107NOx34.56
(87.)Rolling Mill RHF (0.3 MTPA) - 02LSHS603.6NOx3.89
(88.)DRI K3&K4 CDHCoal301.5PM100.42
(89.)Rolling Mill (0.8 MTPA) RH1LSHS603SO26.58
(90.)Rolling Mill (0.8 MTPA) RH-03LSHS603OthersPM2.50.28
(91.)Strip Mill (1X0.45 MTPA)LSHS804NOx6.25
(92.)DP Mill (1X0.2 MTPA)LSHS603SO24.27
(93.)DRI (2X500 TPD) WHRB K1&K2Coal802.75NOx0.089
(94.)DRI (2X600 TPD) WHRB K3&K4Coal803NOx0.107
(95.)DRI (2X600 TPD) WHRB K3&K4Coal803OthersPM2.51.74
(96.)Pellet Plant PEP 01Producer Gas704SO25.45
(97.)Coke Oven SP-MSCoke852.5PM100.91
(98.)Rolling Mill (0.8 MTPA) RH-01LSHS603NOx3.89
(99.)PGP (10X3000 NM3/h)Coal302PM100.27
(100.)Cement Plant (2600 TPD) RM/KilnCoal804PM103.67
(101.)Cement Plant (2600 TPD) Packing-351PM100.16
(102.)Power Plant (2X125 TPH) FBB-01Coal, Middling, Coal fines, char906SO217.28
(103.)Power Plant (2X250 TPH) FBB-02Coal, middling, coal fines, char1107NOx34.56
(104.)Power Plant dedusting-1Coal/Char455PM101.96
(105.)BF Gas PP (11MW)BF Gas302.5PM100.42
(106.)Coke Oven Gas based PP (14 MW)Coke Oven Gas302.5NOx1.08
(107.)DRI (2X600 TPD) K5&K6Coal803NOx0.11
(108.)DRI (2X600 TPD) K5&K6Coal803OthersPM2.51.74
(109.)Pellet Plant (1X1.434 MTPA) ESPPRoducer Gas704PM102.45
(110.)Pellet Plant (1X1.434 MTPA) ESPProducer Gas704OthersPM2.51.41
(111.)Pellet Plant (1X1.434 MTPA) RMHSProducer Gas301.5OthersPM2.50.19
(112.)Coal Washery (1.524 MTPA)Coal351.7OthersPM2.50.16
(113.)BF (0.992 MTPA) StoveCoke352.2PM100.44
(114.)Sinter Plant (1.051 MTPA) Dedustingcoke breeze552.5PM101.42
(115.)Sinter (0.611)Coke breeze555OthersPM 2.55.18
(116.)Rolling Mill (0.8 MTPA-RH-1)LSHS603PM100.48
(117.)Rolling Mill (01 MTPA-RH 1)LSHS603OthersPM 2.50.28
(118.)Rolling Mill (08 MTPA-RH02)LHSH603SO26.58
(119.)Rolling Mill (0.8 MTPA RH2)LSHS603OthersPM 2.50.28
(120.)D P Mill (1x0.2 MTPA)LSHS603PM100.48
(121.)Cement Plant (2600 TPD-Crushing)-302OthersPM 2.50.47
(122.)Coke Oven Gas based power plant (14 MW)Coke oven gas302.5SO22.1
(123.)DRI K5&K6- RMHSCoal351.8OthersPM 2.50.43
(124.)Rolling Mill RHF (0.3 MTPA) - 1LSHS603.6PM100.72
(125.)BF (0.992 MTPA) StoveCoke352.2NOx5.83
(126.)Strip Mill (0.4 MTPA)LSHS804NOx5.56
(127.)DP Mill (0.2 MTPA)LSHS603NOx2.78
(128.)Cement Plant (2300 TPD) RM/KilnCoal804NOx0.78
(129.)BG gas based power plantBF gas303OthersPM2.50.44
(130.)Power Plant Dedusting-2Coal and Char455OthersPM2.52.26
(131.)Cement Pkant (2600 TPD) Plant Mill-604OthersPM2.52.85
(132.)DRI K5 & K6 PSBCoal351.8PM100.76
(133.)Sinter Plant (1.051 MTPA) MainCoke Breeze806.5SO26.57
(134.)Sinter Plant (1.051 MTPA) DedustingCoke Breeze552.5OthersPM2.50.82
(135.)Rolling Mill RHF (0.3 MTPA) - 01LSHS603.6NOx2.89
(136.)Rolling Mill RHF (0.3 MTPA) - 01LSHS603.6OthersPM2.50.42
(137.)Power Plant 2X250 TPH RMHX - 02Coal & Char455PM102.62
(138.)Coke Oven Gas based PPCoke Oven Gas303PM100.85
(139.)DRI K1&K2 RMHSCoal351.7OthersPM2.50.36
(140.)DRI K1&K2 PSBCoal351.7OthersPM2.50.36
(141.)BF Stove (0.567 MTPA) BF - 01Coke351.8OthersPM2.50.14
(142.)Sinter (0.611 MTPA) SP - MSCoke Breeze555NOx0.02
(143.)Coke Oven SP - MSCoke852.5OthersPM2.50.52
(144.)Rolling Mill (0.8 MTPA) RH-04LSHS603SO26.58
(145.)Strip Mill (1X0.45 MTPA)LSHS804OthersPM2.50.63
(146.)BF SH (0.567 MTPA) BF-02Coke471.8OthersPM2.50.28
(147.)DP Mill (1x0.2 MTPA)LSHS603OthersPM2.50.28
(148.)Coke Oven Gas based PP (14 MW)Coke Oven Gas302.5PM100.5
(149.)DRI K5&K6 CDHCoal301.5OthersPM2.50.24
(150.)Pellet Plant (1X1.434 MTPA) ESPProducer Gas704SO25.45
(151.)Pellet Plant (1x1.434 MTPA) PHSProducer Gas301.5OthersPM2.50.19
(152.)DP Mill (0.2 MTPA)LSHS603PM100.48
(153.)Power Plant (2X250 TPH) RMHSCoal and Char454.5OthersPM2.50.75
(154.)DRI-2X500 TPD WHRB K1 & K2Coal802.75OthersPM 2.51.497
(155.)DRI-K3&K4Coal351.8PM100.76
(156.)Pellet plant PHS 03Producer gas301.5OthersPM2.50.1
(157.)DRI K3 & K4, CDHCoal301.5OthersPM 2.50.24
(158.)DRI 2x600 TPD, WHRB K3 & K4Coal803PM103.02
(159.)Sinter (0.611 MTPA)Coke breeze555SO23.82
(160.)Sinter (0.611 MTPA)Coke breeze452PM100.83
(161.)SMS-90 T, EAF-EAF01-604OthersPM 2.50.19
(162.)Rolling Mill (0.8 MTPA RH 2)LHSH603PM100.48
(163.)Strip Mill (1x0.45 MTPA)LSHS804SO210.58
(164.)Power Plant (2x250TPH FBB-2)Coa, middling, coal fines ,char1107OthersPM2.52.24
(165.)Coke oven Gas based power plant (14 MW)Coke oven gas302.5OthersPM 2.50.29
(166.)DRI(2x600 TPD K5&K6)Coal803PM103.02
(167.)Blast Furnace (0.992 MTPA) DedustingCoke472.2PM100.85
(168.)BF Stove (0.567 MTPA) BF01Coke351.8PM100.25
(169.)DP Mill (0.2 MTPA)LSHS603SO24.27
(170.)Cement Plant (2300 TPD) RM/KilnCoal804OthersPM2.51.79
(171.)Cement Plant (2300 TPD) Packing-351PM100.13
(172.)Power Plant 2x250 TPH RMHSCoal and Char454.5PM101.31
(173.)Power Plant 2X250 TPH RHMS 2Coal and Char455OthersPM2.51.51
(174.)Rolling Mill (0.8 MTPA) RH-04LSHS603OthersPM2.50.28
(175.)Power Plant 2X125 TPH FBB-01Coal, Middling, Coal fines, char906OthersPM2.51.12
(176.)Coal Washery (1.524 MTPA)Coal351.7PM100.27
(177.)Cement Plant (2300 TPD) Plan Mill-604PM104.21
(178.)Rolling Mill RHF (0.2 MTPA) - 03LSHS603SO26.58
(179.)DRI 2X500 TPD WHRB K1 & K2Coal802.75SO229.79
(180.)SMS IF 05-352PM100.61
(181.)Cemet Plant (2600 TPD) RM/KilnCoal804NOx1.31
(182.)DRI K1& K2, RMHSCoal351.7PM100.625
(183.)BF gas power plant (11MW)Bf gas302.5NOx0.27
(184.)Sinter Plant (1.05 MTPA) - MainCoke Breeze806.5OthersPM2.58.89
(185.)Pellet Plant 1x1.134 MTPA - ESPProducer Gas704NOx0.08
(186.)Strip Mill (1X0.45 MTPA)LSHS804PM101.09
(187.)Power Plant (2X125 TPH) FBB-01Coal, Middling, coal fines, char906NOx17.28
(188.)Coke Oven Gas Based Power PlantCoke Oven Gas303NOx1.81
(189.)Power Plant Dedusting-2Coal, Char455PM103.93
(190.)Cement Plant (2300 TPD) Plant Mill-604OthersPM2.52.42
(191.)BF Stove (0.567 MTPA) BF-01Coke351.8NOx3.33
(192.)Cement Plant (2300 TPD) Crushing-302PM100.7
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 385
(b)Source Capive Power Plant
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 2x1500 and 6X3500 KVA
(e)Stack Height (in m) 15
20.
Land Ownership Pattern:
(a)Forest Land 3.156
(b)Private Land 218.82
(c)Government Land 51.094
(d)Revenue Land 0
(e)Other Land 0
    Total Land 273.07
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 218.82
(b)Waste/Barren Land 0
(c)Grazing/ Community Land 28.567
(d)Surface Water Bodies 0
(e)Settlements 0
(f)Industrial 0
(g)Forest 3.156
(h)Mangroves 0
(i)Marine Area 0
(j)Others : Leasable 22.529
    Total 273.072
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Green belt90.11
(2.)Water Reservoir12.14
(3.)Area for Solid Waste Management22.34
(4.)Built Up Area0.57
(5.)OthersStock Yard and Road37.15
(6.)Main Plant110.76
Total 273.07
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNIL.NIL
(2.)ESAsNIl.NIL
(3.)CorridorsNIL.NIL
(4.)Critically Polluted AreaNIL.NIL
(5.)NPANIL.NIL
(6.)Wildlife CorridorsNIL.NIL
(7.)ESZsNIL.NIL
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestForest within project area.3.156 ha forest land within project area
(2.)Defence InstallationsNIL.NIL
(3.)Archaeological SitesNIL.NIL
(4.)OthersNILNIL.NIL
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 335
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 246.254
(b)Land yet to be acquired(Ha) 26.818
(c)Status of Land acquisition if not acquired pending with Tahsil office hindol
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 3
(b)No. of Households 18
(c)No. of PDFs (Project Displaced Families) 54
(d)No. of PAFs (Project Affected Families) 54
(e)Funds Allocated for R&R(in Rs) 378
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 586.53 lakhs
(iii)Period of Implementation 10 year
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? Yes
(i)Uploaded copy of approval Copy of approval
(ii)Letter No. 3188/1WL-SSP-10/2015
(iii)Date of issue 09 Apr 2015
(iv)Recommendation Conservation plan has been prepared in compliance
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Brahmani river
(ii)Direction of Water Bodies in Buffer Area North
(iii)Distance of Water Bodies in Buffer Area 7.35
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 200
(b)Permanent Employment-During Operation 800
(c)Temporary Employment- During Construction 400
(d)Temporary Employment- During Operation 1200
(e)No. of working days 350
(f)Total Manpower 2600
32.
Green Belt in Ha:
(a)Total Area of Green Belt 90.11
(b)Percentage of Total Project Area 33.00
(c)No. of Plants to be Planted 225275
(d)Funds Allocated for Plantation 22528000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)FinancialSteady income generation to employee and associated persons, revenue generation to state etc
(2.)EnvironmentalGreenbelt development, plantation, cleanness drive etc.
(3.)SocialDirect & Indirect employment generation, CSR & CER activities in near by villages
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 1
S. No.Item Details
Additional Detail Sought Additional Detail Sought, 3.
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. HC of Delhi orders in LPA 110/2014 and CM No.2175/
(ii)Name of the EIA Consultant Min Mec Consultancy Pvt. Ltd.
(iii)Address A 121 PARYAVARAN COMPLEX, IGNOU Road
(iv)Mobile No. 9811077603
(v)Landline No. 0112953223
(vi)Email Id minmec@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 1
(ix)Validity of Accreditation 29 Apr 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NA

Proposal deferred for want of additional information

07 May 2019
2. ADS LetterNA 14 May 2019
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantAjaya Kumar Mallick
DesignationCGM (Elect)
Name of Company (Applicant Name should not be given here)RUNGTA MINES LTD
AddressRungta Office, Main Road, At/PO: Barbil, Odisha