Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Samaleswari OCP Expn. (Phase IV) 15 Mty
(b)Name of the Company / Organisation SAMALESWARI OCP EXPN. (PHASE IV) MAHANADI COALFIELDS LIMITED
(c)Registered Address Project Officer, Samaleswari OCP, P. O. Rampur Colliery, via. Brajrajnagar, Dist. Jharsuguda, Odisha,,Jharsuguda,Orissa-768225
(d)Legal Status of the Company Central PSU
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Prahlad Prasad Gupta
(b)Designation (Owner/ Partner/ CEO) ProjectOfficer
(c)Address Project Officer, Samaleswari OCP, P. O. Rampur Colliery, via. Brajrajnagar, Dist. Jharsuguda, Odisha,,Brajarajnagar,Jharsuguda,Orissa-768225
(d)Pin code 768225
(e)E-mail socpexpansion@gmail.com
(f)STD Code. 664(f)Telephone No. 5244153
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(a) Mining of minerals
Minor Activity
(b)Category A
(c)Proposal Number IA/OR/CMIN/24722/2008
(d)Master Proposal Number(Single Window) SW/90646/2019
(e)EAC concerned (for category A Projects only) Coal Mining
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Samaleswari Open Cast Project Expn. IB Valley Area
(b)Pincode 768216
(c)Bounded Latitudes (North)
From
Degree 214648
Minutes
Second
From
Degree 214922
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 835223
Minutes
Second
From
Degree 835600
Minutes
Second
(e)Survey of India Topo Sheet No. F/44/R-13 (RF 1:50000)
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 256
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Orissa
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)OrissaJharsugudaBrajarajnagar
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11015/183/2008-IA.II(M)
(c)Date of Issue of TOR 14 Jul 2008
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 16 Sep 2014
(c)Date of Issue of EC 06 Feb 2015
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :05 Nov 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :14 Dec 2018
Distance of Public Hearing Venue from the Proposed Project :5
Ib Valley Kalyan Mandap
State :Orissa
District :Jharsuguda
Tehsil :Brajarajnagar
Village :Brajrajnagar
336Issues were mainly related to Resettlement and Rehabilitation,Air pollution and health issues, road conditions and EmploymentOthersAdditional Disitrict Magistrate
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bhubaneswar
(iii)Letter No. 101-962/EPE
(iv)Status of Compliance Partially Complied
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Sep 18 2018 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Area928.264406.6481334.912Hectares(ha)Road,Rail
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Opencast Coal Mining15 MTY15 MTY15 MTYNo Capacity Expansion
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 26 Mar 2016
(iv)Valid Upto 31 Mar 2019
(v)File No. 5105/IND-I-CON-1298
(vi)Application No. 412988
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 636.24
(b) Funds Allocated for Environment Management (Capital) (in Crores) 49.4809
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.1433
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 3.582
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel 59.46
(c)Total quantity of raw material/fuel 59.46
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Fuel Energy19170.80Kilo Litre per DayLocalRoad0 Fuel Supply AgreementOIL PSUCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 09 Feb 2018 To 28 Apr 2018
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube11055102.64100
(2.)PM2.5Micro Gram per Meter Cube63336360
(3.)SO2Micro Gram per Meter Cube37.5017.5036.6180
(4.)NOxMicro Gram per Meter Cube37.8020.2036.5880
    14.2.     No. of Ground Water monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSmg/l00100100
(2.)Total Hardnessmg/l328.3159.2200600
(3.)Chloridesmg/l38.7621.142501000
(4.)Fluoridemg/l0.60.411.5
(5.)pHNA7.547.368.58.5
(6.)TDSmg/l2521215002000
(7.)Heavy MetalsCadmiummg/l000.0030.003
    14.3.     No. of Surface Water monitoring locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA6.956.83C
(2.)BODmg/l9.18.9C
(3.)DOmg/l4.34.2C
(4.)CODmg/l00C
    14.4.     No. of Ambient Noise monitoring locations : 10
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))44.936.870
(2.)Leq(Day)A-weighted decibels(dB(A))54.741.575
    14.5.     No. of Soil Sample Monitored locations : 4
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare333187
(2.)P(Phosphorus)Kilogram per hectare7.413.87
(3.)K(Potassium)Kilogram per hectare14234
(4.)pHOthers1:2.5/w:v7.686.21
(5.)Electric ConductivityOthersmicroS/cm438142
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 2.30 To 4.88
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.51 To 4.75
(c)Whether Ground Water Intersection will be there ? Yes
(d)Upload Copy of Central Ground Water Authority Letter Copy of Central Ground Water Authority Letter
(e)Letter No. 21/4/2052/OR/MIN/2018
(f)Date of Issue 11 Aug 2018
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersMine Water50150Copy of Permission LetterPipelineOthersPumping000007 Jan 20190
(2.)Surface4160.7Copy of Permission LetterPipelineOthersPumping3283(WE)31 Mar 20189003
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Workshop124960ETPReuse within the Plant & Recycling124
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 124
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 124
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)OverburdenOthersOB Dump5215039.97Tons0RoadOthersBackfilling
(2.)Oily sludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)297Tons0.5RoadOthersImpervious Land pit
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube28.300028.30120
(2.)NOxMicrogram per Meter Cube32.800032.80120
(3.)PM10Microgram per Meter Cube132.330108.63240.96300
(4.)PM2.5Microgram per Meter Cube79.16014.3693.520
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Not Applicable000000OthersNot Applicable00
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 1827.69
(b)Source Jorabaga Central Substation
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) Not Applicable
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 580.292
(b)Private Land (ha.) 0
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 754.62
    Total Land (ha.) 1334.912
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 86.448
(b)Waste/Barren Land (ha.) 644.852
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 23.32
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 580.292
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : 0 0
    Total (ha.) 1334.912
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)OB Dump Area24.86
(2.)Quarry Area856.759
(3.)Built Up Area54.005
(4.)OthersForest Land outside Quarry Area90.784
(5.)Safety Zone308.504
Total (ha.) 1334.912
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaSamleswari OCP0Samleswari OCP falls in "Ib Valley Area''critically polluted cluster.The Moratarium imposed on Ib Valley area has been lifted vide O.M dated 05.07.2011
(2.)NPANot Applicable0Not Applicable
(3.)ESZsNot Applicable0Not Applicable
(4.)WLSNot Applicable0Not Applicable
(5.)Wildlife CorridorsNot Applicable0Not Applicable
(6.)ESAsNot Applicable0Not Applicable
(7.)CorridorsNot Applicable0Not Applicable
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Others1Rampur RF2.9NA
(2.)ForestBikramkhol3.5Reserve Forest
(3.)Archaeological SitesNot Applicable0NA
(4.)Defence InstallationsNot Applicable0NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? Yes
(a)Forests Clearance Status Application for Forest Clearance yet to be submitted
(b)Legal Status of Forest Land Village Forest
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 189
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Not Applicable
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 1
(b)No. of Households 184
(c)No. of PDFs (Project Displaced Families) 307
(d)No. of PAFs (Project Affected Families) 80
(e)Funds Allocated for R&R(in INR) (in Lacs) 630.66
(f)Status of R&R In-Progress
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Pandren Nallah
(b)Whether there is Diversion Required ? Yes
(i)Details of Diversion Required Attached with the permission letter.
(ii)Details of Study Conducted As attached with the permission letter
(c)Whether permission has been obtained from competent authority ? Yes
(i)Uploaded copy of permission Copy of permission
(ii)Letter No. 3050/WR,Irr.-II-WRC-10/14
(iii)Date of issue 17 Feb 2014
(iv)Recommendation NA
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area IB River
(ii)Direction of Water Bodies in Buffer Area East
(iii)Distance of Water Bodies in Buffer Area 0.7
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 158
(b)Permanent Employment-During Operation 0
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 330
(f)Total Manpower 158
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt322.1315.257337.387
(2.)Percentage of Total Project Area34.71.1135.81
(3.)No. of Plants78916138142827303
(4.)Funds Allocated273.98171.64445.62
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Social(i) Improvement in Physical Infrastructure (ii) Improvement in Social Infrastructure (iii) Increase in employment potential (iv) Contribution to the Exchequer (both State and Central Govt.) (v) Post mining enhancement of Green Cover (vi) Improvement of Electrical Power Generation and availability of electricity for 24x7 in rural areas (vii) Overall economic growth of the country.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)CoalMajor
2.
Mine Capacity in ROM (Run of Mine) 15 MTY
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. F.No.CPAM-34011/36/2017-CPAM
(b)Date of Approval 20 Nov 2017
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department Coal
(e)Approved Mining Lease Area 1334.912
(f)Approved Capacity 15
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 179.75
(b)Mineable Reserves (Million Ton) 143.49
(c)Extractable Reserves(Million Ton) 143.49
(d)Percent(%) of Extraction 87.79
(e)Grade of Coal /Ore /Mineral G 12 & G 13
(f)Stripping Ratio 1.81 : 1
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) NA
(h)Average Gradient(Degree) 3-4
(i)Mining Method Opencast
(j)Life of Mine (Years) 10
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area No
7.
Details of Seams:
(a)Whether details of seam applicable Yes
(b)No. of seams 6
(c)Thickness of seams to be worked on 12.55
(d)Maximum Thickness of Seams (metres) 23.9
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 1334.912
(b)Whether obtained Letter of Intent (LOI) from the state government ? No
(i)Reason thereof Acquired under CBA(A&D) act 1957
(c)Whether Lease Deed Executed ? No
(i)Reason thereof Acquired under CBA(A&D) act 1957
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof Acquired under CBA(A&D) act 1957
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps
(ii)Total Area (in Hectare)
(iii)Height (in meter)
(iv)Quantity (in Million Cubic meter)
(v)No. of year back fill up
(b) Details of Internal Dumps:
(i)No. of Internal Dumps
(ii)Total Area (in Hectare)
(iii)Height (in meter)
(iv)Quantity (in Million Cubic meter)
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 0.44
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 0.68
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare)
(b)Depth (in meter)
(c)Volume (in Million Cubic meter)
12.
Details of Quarry:
(a)Final Void of 73.787 (hectare) at a Depth of 183 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 856.759
13.
Details of Transportation:
(a)In Pit/Underground to Surface Dumpers & Tippers
(b)Surface to Siding/Loading Tippers & Payloader
(c)Transportation / Conveyor Details NA
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)WASTE LAND644.8520644.852
(2.)OTHERS(Specify)NA000
(3.)AGRICULTURE LAND86.448086.448
(4.)FOREST LAND580.2920580.292
(5.)GRAZING LAND000
(6.)SURFACE WATER BODIES23.320023.32
(7.)SETTLEMENTS049.85549.855
TOTAL1334.91249.8551384.767
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)OtherDanger Zone for Blasting2070101.587308.587
(2.)EXTERNAL OB DUMPS250025
(3.)ROADS10.801043.20454.005
(4.)VIRGIN AREA90.7840090.784
(5.)INTERNAL OB DUMPS0000
(6.)GREEN BELT0000
(7.)EXCAVATION/QUARRY571.09373.787212856.88
(8.)TOP SOIL STORAGE0000
(9.)BUILT UP AREA (COLONY/OFFICE)504550
TOTAL909.67873.787401.79101385.256
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 24.86
(b)Internal Dump(in hectare) 782.972
(c)Quarry(in hectare) 856.759
(d)Safety Zone(in hectare) 308.504
(e)Final Void of 73.787 (hectare) at a Depth of 183 meter which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 2500
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 54.005
(h)Total afforestation plant (in hectare) 909.455
17.
Status of progressive Mining Closure Plan:
Copy of Implementation of Various Activities as per Approved Progressive Mine Closure Plan Copy of Implementation of Various Activities as per Approved Progressive Mine Closure Plan
Any Deviation from the Approved Progressive Mine Closure Plan No
Total Area Excavated (in hectare) 500.562
Total Area Backfilled after Excavation (in hectare) 379.70
Total Area Reclaimed (in hectare) 115.770
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)19910000.6690
(2.)19963002.4600
(3.)19973003.3840.384
(4.)19993303.8360.836
(5.)20033303.8430.843
(6.)20053304.8251.825
(7.)20063305.7772.777
(8.)20075507.6692.669
(9.)20085509.7084.708
(10.)200955010.1855.185
(11.)20125011116
(12.)2013111111110
(13.)2014111115110
(14.)201515151512.4050
(15.)201815151514.3170
(16.)19900000.1090
(17.)2010551110.7590
(18.)19943001.7520
(19.)20191515157.2550
(20.)19953002.0070
(21.)2011551111.4836.483
(22.)201615151514.5940
(23.)19923000.9840
(24.)19933001.4090
(25.)19983004.0111.011
(26.)20003303.4940.494
(27.)20023304.0881.088
(28.)20043304.5461.546
(29.)201715151514.7110
(30.)20013303.4950.495
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? Yes
(b)Name of the Court Districts Courts
(c)Name of the Sub Court Bilaspur
(d)Case No. 2(c) cc No:172/2013 dated 11/02/2013
(e)Orders/Directions of the court ,if any and its relevance with the proposed project NA
(f)Case Details The case has been filed by the Collector Jharsugud
(g)Uploaded Court Order Copy of Court Order
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1720/RA/0092
(ii)Name of the EIA Consultant Central Mine Planning and Design Institute
(iii)Address Gondwana Palace,Kanke Road,Ranchi,Jharkhand 834031
(iv)Mobile No. 8987788797
(v)Landline No. 0651223005
(vi)Email Id gmenv.cmpdi@coalindia.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation Coal Mining
(ix)Validity of Accreditation 01 Oct 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPlease provide/inform/clarify the following:- - EC dated 6/2/2015 against column 6(d) of Form-2. - Public hearing proceedings against column 7.1 of Form-2. - Status of diversion of forest land within the present mine lease area of 928.264 ha, and also that in the revised/proposed mine lease area of 1334.912 ha. - Jharsuguda still figures in the list of Critically Polluted Areas identified by CPCB, and the moratorium imposed earlier is still in force. Keeping in view, how the present expansion is admissible. 10 Jan 2019
2.NAThe correction have been made as per the instruction received 11 Jan 2019
3.NARegional Office vide their monitoring report dated 14/12/2018 for compliance status of the conditions stipulated in the EC dated 6/2/2015, has asked for the information and action plan against many of their observations. Needful may please be done for consideration of the proposal. 25 Jan 2019
4.NAThe correction have been made as per the instruction received 28 Jan 2019
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantPrahlad Prasad Gupta
DesignationProjectOfficer
Name of Company (Applicant Name should not be given here)SAMALESWARI OCP EXPN. (PHASE IV) MAHANADI COALFIELDS LIMITED
AddressProject Officer, Samaleswari OCP, P. O. Rampur Colliery, via. Brajrajnagar, Dist. Jharsuguda, Odisha