Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) M/s. Cheminova India Limited (Technical Division)
(b)Name of the Company / Organisation CHEMINOVA INDIA LIMITED TECHNICAL DIVISION
(c)Registered Address The Centrium, Unit No. 2, 4th Floor, Phoenix Market City, LBS Marg, Kurla (West), Mumbai-400 070,Bharuch,Gujarat-394116
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Anil Narendra Shah
(b)Designation (Owner/ Partner/ CEO) FactoryManager
(c)Address M/s. Cheminova India Limited Technical Division, Plot No 241, 242/2, 241/P, GIDC Estate, Panoli, Tal. Ankleshwar, Dist. Bharuch 394116, Gujarat, India,,Anklesvar,Bharuch,Gujarat-394116
(d)Pin code 394116
(e)E-mail anil.shah@fmc.com
(f)STD Code. 903(f)Telephone No. 3978622
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Project/Activity5(b) Pesticides industry and pesticide specific intermediates (excluding formulations)
(b)Category A
(c)Proposal Number IA/GJ/IND2/89462/1997
(d)Master Proposal Number(Single Window) SW/89455/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot No. 241, 242/2, 241/P
(b)Pincode 394116
(c)Bounded Latitudes (North) FROM 21.57422 To 21.57599
(d)Bounded Longitudes (East) FROM 72.99638 To 72.99806
(e)Survey of India Topo Sheet No. F43M14, F43M15, F43N2, F43N3
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 26
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 8
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)GujaratBharuchAnklesvarPanoli
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number NIL
(b)Date of Apply of EC NIL
(c)Date of Issue of EC NIL
(d)Previous EC Letter NIL
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Project site is located in the Notified industrial
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By SPCB
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on NIL
(iii)Letter No. NA
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit N/A
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Agrochemicals & their intermediates35331205015583Tons per Annum(TPA)Road
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Plant-2AZOXY plant (G.F+2)Debottle necking or Addition of floorsPlant-2Please refer Annexure-16 for more details
(2.)Plant-1ACP plant (G.F+3)Debottle necking or Addition of floorsPlant-1Please refer Annexure-16 for more details
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 25 Jul 2017
(iv)Valid Upto 16 Apr 2022
(v)File No. CCA No. AWH-87335
(vi)Application No. --
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 365.92
(b) Funds Allocated for Environment Management (Capital) (in Crores) 17.15
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 2.76
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.9
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel 15500
(c)Total quantity of raw material/fuel 15500
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Natural Gas15500Cubic Meter per DayGujarat Gas LimitedPipe Conveyor15 LinkageCopy of Linkage
(2.)Furnace Oil4000Otherskilogram per dayLocal supplierRoad15 LinkageCopy of Linkage
(3.)High Speed Diesel4320Othersliter per dayLocal supplierRoad15 Open MarketCopy of Linkage
(4.)Raw material9189.49OthersMetric Tonne per monthIndigenous & ImportRoad300 LinkageCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Feb 2017 To 30 Apr 2017
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 9
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube33733NAAQS
(2.)PM10Micro Gram per Meter Cube916491NAAQS
(3.)NOxMicro Gram per Meter Cube32832NAAQS
(4.)SO2Micro Gram per Meter Cube26726NAAQS
    14.2.     No. of Ground Water monitoring locations : 9
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Chloridesmg/l369182501000
(2.)TSSmg/l70101010
(3.)Heavy MetalsZincmg/l0.20.2515
(4.)Total Hardnessmg/l4241122006000
(5.)pHNA8.317.0778.5
(6.)Fluoridemg/l1.050.511.5
(7.)TDSmg/l17301855002000
    14.3.     No. of Surface Water monitoring locations : 15
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)BODmg/l9515B
(2.)pHNA8.557.16B
(3.)CODmg/l20632B
(4.)DOmg/l7.51B
    14.4.     No. of Ambient Noise monitoring locations : 9
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))6633Noise Rules 2000
(2.)Leq(Day)A-weighted decibels(dB(A))7540Noise Rules 2000
    14.5.     No. of Soil Sample Monitored locations : 9
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)P(Phosphorus)Milligram per Kilogram9.433.5
(2.)pHOthers--8.557.74
(3.)N(Nitrogen)Percent0.050.05
(4.)K(Potassium)Milligram per Kilogram331.6864.356
(5.)Electric ConductivityOthersµ mhos/cm1556413.34
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 10 To 5
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 2 To 5
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface4101.89Copy of Permission LetterPipelineWeirRef: CIL/Tech/July/001, Connection No.: 208116 Jul 1996315
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic3550To be treated in STPGreen Belt Renewal Plant35
(2.)Industrial572620To be treated in ETP/MEE/RODischarge into Seawater Body,Reuse within the Plant & Recycling453119
16.1.
(a)Total Waste Water Generation 607
(b)Total Discharged Water 119
(c)Total Reused Water 488
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Stripped Solvent from StripperHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1200Tons50RoadOtherspremises/CHWIF/Co-processing/Autho users
(2.)Process WasteHazardous Waste (as per Hazardous and Other Waste Management rules 2016)28151Tons15RoadOthersIncineration/Co-processing
(3.)Acetic Acid/Sodium Acetate/OrganicByproducts etc.Hazardous Waste (as per Hazardous and Other Waste Management rules 2016)18224Tons50RoadOthersCHWIF/Autho users
(4.)Used or Spent OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)50.36Tons15RoadAuthorized Recyclers
(5.)Spent CatalystHazardous Waste (as per Hazardous and Other Waste Management rules 2016)90Tons15RoadOthersCHWIF/regenerator
(6.)NaCl Sol.n (19%)Hazardous Waste (as per Hazardous and Other Waste Management rules 2016)145Tons50RoadOthersAuthorized Userswith Rule 9 permission/TSDF/CHWIF
(7.)ETP SludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)905Tons15RoadTreatment, Storage and Disposal Facility(TSDF)
(8.)Evaporation SaltHazardous Waste (as per Hazardous and Other Waste Management rules 2016)13155Tons15RoadTreatment, Storage and Disposal Facility(TSDF)
(9.)Date-expired and off specification pesticidesHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1000Tons15RoadOthersCHWIF/Co-processing
(10.)EthanolHazardous Waste (as per Hazardous and Other Waste Management rules 2016)4520Tons50RoadOthersAuthorized Users having Rule 9 permission
(11.)Empty barrels/containers/linersHazardous Waste (as per Hazardous and Other Waste Management rules 2016)5362.11Tons15RoadOthersauthorized recyclers/premises/CHWIF/TSDF
(12.)Spent Solvent (MDC, EA, Acetone, etc.)Hazardous Waste (as per Hazardous and Other Waste Management rules 2016)2500Tons50RoadOtherspremises/CHWIF/Co-processing/Autho users
(13.)Distillation ResidueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)7300Tons15RoadOthersCHWIF/Co-processing
(14.)Spent Sulfuric Acid (50%)Hazardous Waste (as per Hazardous and Other Waste Management rules 2016)16400Tons50RoadOthersAuthorized Users having Rule 9 permission
(15.)HCl (30%)Hazardous Waste (as per Hazardous and Other Waste Management rules 2016)1220Tons50RoadOthersAuthorized Users having Rule 9 permission
(16.)Salts of per-acidsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)18864Tons50RoadOthersAuthorized Users having Rule 9 permission
(17.)Contaminated cotton,PPE/otherHazardous Waste (as per Hazardous and Other Waste Management rules 2016)50Tons15RoadOthersTSDF/CHWIF
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube841.780.03384.033NAAQS
(2.)SO2Microgram per Meter Cube221.780.38222.382NAAQS
(3.)NOxMicrogram per Meter Cube281.780.17828.178NAAQS
(4.)PM2.5Microgram per Meter Cube281.780.03328.033NAAQS
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Attached to reaction vessel of ACP plant--250.065OthersHCl & Chlorine20 mg/Nm3 & 9 mg/Nm3
(2.)Reaction vessel of 4S Zeta Cypermethrin--250.065OthersHCl20 mg/Nm3
(3.)Regenerative Thermal OxidizerNatural gas300.15OthersCO2 mg/Nm3
(4.)Boiler- WHRB- CPPNatural gas300.5SO2100 ppm
(5.)Boiler- 10 TPH & 5 TPHNatural gas & Furnace Oil300.6PM10150 mg/Nm3
(6.)Boiler- 10 TPH & 5 TPHNatural gas & Furnace Oil300.6NOx50 ppm
(7.)Thermic fluid heater- 10 lakh Kcal/hrNatural gas300.3SO2100 ppm
(8.)D.G. Set- 1500 KVAH.S.D110.2PM10150 mg/Nm3
(9.)D.G. Set- 1500 KVAH.S.D110.2SO2100 ppm
(10.)D.G. Set- 1500 KVAH.S.D110.2NOx50 ppm
(11.)Attached to reaction vessel of AZOXY Plant--250.075OthersHCl & Chlorine20 mg/Nm3 & 9 mg/Nm3
(12.)Reaction vessel of Sulfentrazone & DBC80--250.075OthersHCl20 mg/Nm3
(13.)Boiler- WHRB- CPPNatural gas300.5PM10150 mg/Nm3
(14.)Boiler- WHRB- CPPNatural gas300.5NOx50 ppm
(15.)Boiler- 10 TPH & 5 TPHNatural gas & furnace Oil300.6SO2100 ppm
(16.)D.G set- 1250 KVAH.S.D110.2PM10150 mg/Nm3
(17.)D.G. set- 1250 KVAH.S.D110.2SO2100 ppm
(18.)D.G. set- 1250 KVAH.S.D110.2NOx50 ppm
(19.)Thermic Fluid heater- 10 lakh Kcal/hrNatural gas300.3PM10150 mg/Nm3
(20.)Thermic Fluid Heater- 10 lakh Kcal/hrNatural gas300.3NOx50 ppm
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 3500
(b)Source Dakshin Gujarat Vij Company Limited (DGVCL)
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 1 no. of 1250 KVA & 1 no. of 1500 KVA
(e)Stack Height (in m) 11
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 0
(c)Government Land 0
(d)Revenue Land 0
(e)Other Land 4.0476941
    Total Land 4.0476941
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 19466
(b)Waste/Barren Land 5830
(c)Grazing/ Community Land 0.0
(d)Surface Water Bodies 521
(e)Settlements 2802
(f)Industrial 2797
(g)Forest 0.0
(h)Mangroves 0.0
(i)Marine Area 0.0
(j)Others : NA 0.0
    Total 31416
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Built Up Area2.207151
(2.)Green belt1.345
(3.)OthersOpen area0.4955431
Total 4.0476941
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNA0--
(2.)ESAsNA0--
(3.)ESZsNA0--
(4.)CorridorsNA0--
(5.)Wildlife CorridorsNA0--
(6.)Critically Polluted AreaNA0--
(7.)NPANA0--
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)OthersNANA0--
(2.)ForestNA0--
(3.)Archaeological SitesNA0--
(4.)Defence InstallationsNA0--
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) Not Applicable
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 4.0476941
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired NA
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Indian Peafowl
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Khadis, Canal, Ponds
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Khadis, Canal, Ponds
(ii)Direction of Water Bodies in Buffer Area North East
(iii)Distance of Water Bodies in Buffer Area 5
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 154
(b)Permanent Employment-During Operation 46
(c)Temporary Employment- During Construction 346
(d)Temporary Employment- During Operation 154
(e)No. of working days 320
(f)Total Manpower 700
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt1.07960.26541.345
(2.)No. of Plants16204502070
(3.)Percentage of Total Project Area26.676.5633.230000000000004
(4.)Funds Allocated5.41.56.9
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)FinancialRevenue Generation, Employment generation
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
Additional Detail Sought Additional Detail Sought, 3.
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1821/RA 0104
(ii)Name of the EIA Consultant M/s. Siddhi Green Excellence Pvt. Ltd.
(iii)Address “Kamal Arcade – The Vertical Sunclock”, Comm. Plot No. C-3/3, Nr. SBI Industrial Branch, Station Road, G.I.D.C, Ankleshwar – 393 002,Gujarat
(iv)Mobile No. 9824345895
(v)Landline No. 2646224805
(vi)Email Id siddhi.ank@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 27 Apr 2021
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NA