APPENDIX I
(See Paragraph-6)
FORM 1M
Note : If space provided against any parameter is inadequate,Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form 1M. Please note that all such Annexures must be part of single pdf document.
(I)Basic Informations
S.No.Item Details
(i).Name of the Mining Lease site Quarzite Quarry in Kulasekaranallur, In Sf No 222 & 223 over an extent of 4.44.0 hectare
(ii).Location / site (GPS Co-ordinate) Label Latitude Longitude A 08o54’09.60” 77o59’27.42” B 08o54’11.22” 77o59’29.94” C 08o54’07.38” 77o59’32.40” D 08o54’03.66” 77o59’35.52” E 08o54’01.87” 77o59’30.18” F 08o54’01.59” 77o59’28.45”
Annexure-GPS file      
(iii).
Type of LeaseIndivisual Area
Size of the Mining Lease (in ha.)4.44.0 ha.
(iv).Capacity of the Mining Lease (TPA) 29800
(v).Period of Mining Lease 10
(vi).Expected cost of the Project 95
(vii).
Have you hired Consultant/Registered Qualified Person(RQP) for preparing document?Yes
Accreditation No.130/98/A 
Name of Consultant/RQPN.ravinthiran
Address 1699/1, Madurai Road, sankarNagar,Tirunelveli
Mobile No.9842126699
Landline No.2302067
Email Idjpr.industry2gmail.com
(II) Environmental Sensitivity
S.No Areas Distance in kilometer / Details
1. (i).  Nearest rail or road bridge over the concerned river,rivulet,nallah etc. in kms.  30 km
2. (ii). Nearest Infrastructural along with distance in kms  30 km
(iii). Nearest Railway Line along with distance in kms  16 km
(iv). Nearest National Highway along with distance in kms  5 km
(v). Nearest State Highway along with distance in kms  3 km
(vi). Nearest Major District Road along with distance in kms 3 km
(vii). Nearest Any Other Road along with distance in kms  3 km
(viii). Nearest Electric transmission line pole or tower distance in kms  0 km
(ix). Nearest Canal or check dam or reservoirs or lake or ponds distance in kms  5 km
(x). Nearest In-take for drinking water pump house distance in kms  3 km
(xi). Nearest In-take for Irrigation canal pumps distance in kms  3 km
3. Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
There are no such protected under ecological landscape, cultural area etc identified with in 5 km radius
4. Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests there is two small seasonal pond is situated in western side and another the south-east side away from 400 m of applied area
5. Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration There are no such flora or fauna for breeding, resting, foraging, migration with in 15 km radius
6. Inland, coastal, marine or underground waters There are no such coastal marine or underground water within 10 km rdius
7. State, National boundaries There are no such state, national boundaries with in 15 km from the lease boundary
8. Routes or facilities used by the public for access to recreation or other tourist,pilgrim areas There are no such tourist, pilgrim areas within 1 km raius
9. Defence installations No defence installation found with in10 km from lease area
10. Densely populated or built-up area, distance from nearest human habitation Sl. No Direction Village Population Distance 1 N East Ceylon colony 300 3 Km 2 East Ottapidaram 5000 4. Km 3 South Nil 4 West Kulasekaranallur 500 2 km
11. Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship,community facilities) Thoothukudiis having all facilities which are at a distance of 30 km from the lease area.
12. Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) Quarry operation is restricted only upto a depth of 5 m below ground level.Hence ground water will not be affected beside the area is devoid of agricultural ,forestry, tourist place etc.
13. Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) This is the fresh quarry project, hence the area has not subjected to pollution or environmental damage
14. Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) The area is not susceptible to natural hazards like earth quake, landslides etc. It is a high stable land
15.
Is proposed mining site located over or near fissure/fracture for ground water recharge?No
16.
Whether the proposal involves approval or clearance under the following Regulations or Acts namely?
(a).
The Forest (Conservation) Act,1980?No
(b).
The Wildlife (Protection) Act,1972?No
(c).
The Coastal Regulation Zone (C.R.Z) notification,2011?No
17.
Is forest land involved (ha)?No
18.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
19.
New/Expansion/ModernizationNew
Proposal NumberDIA/TN/MIN/18288/2018
File NumberTo be assigned
Date of Apply EC18 Oct 2018
Details of State of the project
S.No. State Name District Name Tehsil Name
(1.)Tamil NaduThoothukkudiOttapidaram
(III) EC Attachments
1 Uploaded PFR (Pre Feasibility Report) File Annexure-PFR file
2 Uploaded Approved Mining Plan File Annexure-Approved Mining Plan file
3 Uploaded District survey report Annexure-District Survey Report
4 Uploaded Cover Letter Annexure-Cover Letter
Uploaded Additional attachments, if any
S.No. Attached File Date of Submission
NIL
(IV) Undertaking
The aforesaid application and documents furnished here with are true to my knowledge.
(IV).(i)
NameQUARTZITE RRMINERAL
DesignationPartner
Company QUARTZITE RRMINERAL
AddressRR Mineral,1242, Annanar west, Chennai-40
Print