APPENDIX I
(See Paragraph-6)
FORM 1M
Note : If space provided against any parameter is inadequate,Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form 1M. Please note that all such Annexures must be part of single pdf document.
(I)Basic Informations
S.No.Item Details
(i).Name of the Mining Lease site Mining appln of Mr. Pramod Marotrao Bramhankar,Gut No.72,Bodad stone quarry proposal
(ii).Location / site (GPS Co-ordinate) 20°44'33.07"N, 78°23'35.18"E
Annexure-GPS file      
(iii).
Type of LeaseIndivisual Area
Size of the Mining Lease (in ha.)3.114 ha.
(iv).Capacity of the Mining Lease (TPA) 147187
(v).Period of Mining Lease 5
(vi).Expected cost of the Project 35
(vii).
Have you hired Consultant/Registered Qualified Person(RQP) for preparing document?Yes
Accreditation No.1518/RA0036 
Name of Consultant/RQPPrashil Shukla
Address Enviro Techno consult Pvt ltd., Nagpur
Mobile No.9225230146
Landline No.32027888
Email Idenvirotechnoconsult@gmail.com
(II) Environmental Sensitivity
S.No Areas Distance in kilometer / Details
1. (i).  Nearest rail or road bridge over the concerned river,rivulet,nallah etc. in kms.  0.436 km
2. (ii). Nearest Infrastructural along with distance in kms  7.5 km
(iii). Nearest Railway Line along with distance in kms  0.716 km
(iv). Nearest National Highway along with distance in kms  13.5 km
(v). Nearest State Highway along with distance in kms  1.315 km
(vi). Nearest Major District Road along with distance in kms 6.5 km
(vii). Nearest Any Other Road along with distance in kms  0.446 km
(viii). Nearest Electric transmission line pole or tower distance in kms  17 km
(ix). Nearest Canal or check dam or reservoirs or lake or ponds distance in kms  4.4 km
(x). Nearest In-take for drinking water pump house distance in kms  8.6 km
(xi). Nearest In-take for Irrigation canal pumps distance in kms  8.6 km
3. Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
Bor Santury-33 Km NE
4. Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Water Body –4.4 km N, ,Wardha river-8.6 km SW,Wet Land Not Notified for district ,Coastal Area 610 Km West,Biosphere Pachmadi -170 Km N,Mountains Govilgad Hills 20 Km N,
5. Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration Bor Santury-33 Km NE
6. Inland, coastal, marine or underground waters Water Body –4.4 km N, ,Wardha river-8.6 km SW,Coastal Area 610 Km, ,Marine Water -600 Km West
7. State, National boundaries 84 Km N
8. Routes or facilities used by the public for access to recreation or other tourist,pilgrim areas Wardha Rd – 1.26 km SE
9. Defence installations Pulgaon -3.5 Km S
10. Densely populated or built-up area, distance from nearest human habitation Bodad -1.315 km SW
11. Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship,community facilities) 8.5 Km Pulgaon SW
12. Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) Water Body –4.4 km N, ,Wardha river-8.6 km SW,Coastal Area 610 Km, ,Marine Water -600 Km West, West,quarry is agriculture area with single crop system, Fishing at Water Body 8.6 Km W, Minerals quarry Basalt
13. Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No
14. Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) No. Stone quarry is at safe distances from natural hazards like earthquake prone area, subsidence, landslide, erosion, flooding prone area
15.
Is proposed mining site located over or near fissure/fracture for ground water recharge?No
16.
Whether the proposal involves approval or clearance under the following Regulations or Acts namely?
(a).
The Forest (Conservation) Act,1980?No
(b).
The Wildlife (Protection) Act,1972?No
(c).
The Coastal Regulation Zone (C.R.Z) notification,2011?No
17.
Is forest land involved (ha)?No
18.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
19.
New/Expansion/ModernizationNew
Proposal NumberDIA/MH/MIN/19329/2018
File NumberDIA/MH/MIN/19329/2018
Date of Apply EC01 Dec 2018
Details of State of the project
S.No. State Name District Name Tehsil Name
(1.)MaharashtraWardhaWardha
(III) EC Attachments
1 Uploaded PFR (Pre Feasibility Report) File Annexure-PFR file
2 Uploaded Approved Mining Plan File Annexure-Approved Mining Plan file
3 Uploaded District survey report Annexure-District Survey Report
4 Uploaded Cover Letter Annexure-Cover Letter
Uploaded Additional attachments, if any
S.No. Attached File Date of Submission
NIL
(IV) Undertaking
The aforesaid application and documents furnished here with are true to my knowledge.
(IV).(i)
NamePROJECT PROPONENT
DesignationPROJECT PROPONENT
Company PROJECT PROPONENT
Address68, mahakali nagar nagpur
Print