APPENDIX I
(See Paragraph-6)
FORM 1M
Note : If space provided against any parameter is inadequate,Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form 1M. Please note that all such Annexures must be part of single pdf document.
(I)Basic Informations
S.No.Item Details
(i).Name of the Mining Lease site PARA 1 SAND GHAT
(ii).Location / site (GPS Co-ordinate) 18 39 21.8 N 75 49 04 E
Annexure-GPS file      
(iii).
Type of LeaseIndivisual Area
Size of the Mining Lease (in ha.)0.37 ha.
(iv).Capacity of the Mining Lease (TPA) 5158
(v).Period of Mining Lease 1
(vi).Expected cost of the Project 385
(vii).
Have you hired Consultant/Registered Qualified Person(RQP) for preparing document?Yes
Accreditation No.NABET/EIA/1518/SA036 
Name of Consultant/RQPP SHUKLA
Address NAGPUR
Mobile No.9225230146
Landline No.9225230146
Email Idenvirotechnoconsult@gmail.com
(II) Environmental Sensitivity
S.No Areas Distance in kilometer / Details
1. (i).  Nearest rail or road bridge over the concerned river,rivulet,nallah etc. in kms.  0.67 km
2. (ii). Nearest Infrastructural along with distance in kms  2.13 km
(iii). Nearest Railway Line along with distance in kms  40.65 km
(iv). Nearest National Highway along with distance in kms  12.44 km
(v). Nearest State Highway along with distance in kms  14.17 km
(vi). Nearest Major District Road along with distance in kms 2.91 km
(vii). Nearest Any Other Road along with distance in kms  0.67 km
(viii). Nearest Electric transmission line pole or tower distance in kms  4 km
(ix). Nearest Canal or check dam or reservoirs or lake or ponds distance in kms  28.53 km
(x). Nearest In-take for drinking water pump house distance in kms  1.50 km
(xi). Nearest In-take for Irrigation canal pumps distance in kms  37.20 km
3. Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
NOT WITHIN 5 KM AREA
4. Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests PACHMADHI 502 KM WET LAND NOT REGISTERED SATPURA RANGE 307 KM,COASTAL ZONE 309 KM
5. Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration NOT WITHIN 5 KM AREA
6. Inland, coastal, marine or underground waters COASTAL AREA 309 KM
7. State, National boundaries 131 KARNATAKA
8. Routes or facilities used by the public for access to recreation or other tourist,pilgrim areas PARLI72 KM NE
9. Defence installations AURANGABAD 140.57 KM N
10. Densely populated or built-up area, distance from nearest human habitation PARA 2.13 KM SOUTH
11. Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship,community facilities) WASHI 12.42 KM SOUTH
12. Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) NO
13. Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) NO
14. Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) NO
15.
Is proposed mining site located over or near fissure/fracture for ground water recharge?No
16.
Whether the proposal involves approval or clearance under the following Regulations or Acts namely?
(a).
The Forest (Conservation) Act,1980?No
(b).
The Wildlife (Protection) Act,1972?No
(c).
The Coastal Regulation Zone (C.R.Z) notification,2011?No
17.
Is forest land involved (ha)?No
18.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
19.
New/Expansion/ModernizationNew
Proposal NumberDIA/MH/MIN/17409/2018
File NumberDIA/MH/MIN/17409/2018
Date of Apply EC17 Sep 2018
Details of State of the project
S.No. State Name District Name Tehsil Name
(1.)MaharashtraOsmanabadWashi
(III) EC Attachments
1 Uploaded PFR (Pre Feasibility Report) File Annexure-PFR file
2 Uploaded Approved Mining Plan File Annexure-Approved Mining Plan file
3 Uploaded District survey report Annexure-District Survey Report
4 Uploaded Cover Letter Annexure-Cover Letter
Uploaded Additional attachments, if any
S.No. Attached File Date of Submission
(1.)EIA-EMP17 Sep 2018
(IV) Undertaking
The aforesaid application and documents furnished here with are true to my knowledge.
(IV).(i)
NamePROJECT PROPONENT
DesignationPROJECT PROPONENT
Company PROJECT PROPONENT
Address68, mahakali nagar nagpur
Print