APPENDIX I
(See Paragraph-6)
FORM 1M
Note : If space provided against any parameter is inadequate,Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form 1M. Please note that all such Annexures must be part of single pdf document.
(I)Basic Informations
S.No.Item Details
(i).Name of the Mining Lease site SURGAON STONE QUARRY Mr. Nagsen Zinger Lokhande proposed Stone Quarry at village Surgaon, Tal: umredDist: Nagpur Gat no.192
(ii).Location / site (GPS Co-ordinate) 21°00'47.24"N 79° 13'02.68"E 21°00'47.30"N 79° 13'04.73"E 21°00'48.74"N 79° 13'05.29"E 21°00'50.24"N 79° 13'05.23"E 21°00'51.00"N 79° 13'04.78"E 21°00'50.69"N 79° 13'01.36"E
Annexure-GPS file      
(iii).
Type of LeaseIndivisual Area
Size of the Mining Lease (in ha.)1.00 ha.
(iv).Capacity of the Mining Lease (TPA) 23773
(v).Period of Mining Lease 5
(vi).Expected cost of the Project 50.5
(vii).
Have you hired Consultant/Registered Qualified Person(RQP) for preparing document?Yes
Accreditation No.NABET/EIA/1720/IA0022 
Name of Consultant/RQPJV Analytical Services
Address Samay Building , Bhau Patil Road,Bopodi, Pune
Mobile No.9371049343
Landline No.25811129
Email Idjvlabpune@gmail.com
(II) Environmental Sensitivity
S.No Areas Distance in kilometer / Details
1. (i).  Nearest rail or road bridge over the concerned river,rivulet,nallah etc. in kms.  7.12 km
2. (ii). Nearest Infrastructural along with distance in kms  1.41 km
(iii). Nearest Railway Line along with distance in kms  10.23 km
(iv). Nearest National Highway along with distance in kms  14.36 km
(v). Nearest State Highway along with distance in kms  0.17 km
(vi). Nearest Major District Road along with distance in kms 3.18 km
(vii). Nearest Any Other Road along with distance in kms  0.67 km
(viii). Nearest Electric transmission line pole or tower distance in kms  1.41 km
(ix). Nearest Canal or check dam or reservoirs or lake or ponds distance in kms  1.15 km
(x). Nearest In-take for drinking water pump house distance in kms  1.25 km
(xi). Nearest In-take for Irrigation canal pumps distance in kms  1.21 km
3. Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
Does not exist in 5 Km Radius
4. Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Mangli Lake is 1.15 km from project site.pazar talv is 4.65 km away from project site
5. Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration Umred Karhandla Wildlife sanctury is 30.52 km away from project site
6. Inland, coastal, marine or underground waters Does not exist in 5 Km Radius
7. State, National boundaries Does not exist in 5 Km Radius
8. Routes or facilities used by the public for access to recreation or other tourist,pilgrim areas Does not exist in 5 Km Radius
9. Defence installations Does not exist in 5 Km Radius
10. Densely populated or built-up area, distance from nearest human habitation Undari village is 1.26 km from project site and Surgaon village is 1.41 km away from project site
11. Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship,community facilities) Shri Jaggnnath Dham durga mata mandir is 3.24 km from project site.ZPPS school at surgaon is 1.50 km
12. Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) Mangli Lake is 1.15 km from project site.pazar talv is 4.65 km away from project site
13. Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No
14. Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) No
15.
Is proposed mining site located over or near fissure/fracture for ground water recharge?No
16.
Whether the proposal involves approval or clearance under the following Regulations or Acts namely?
(a).
The Forest (Conservation) Act,1980?No
(b).
The Wildlife (Protection) Act,1972?No
(c).
The Coastal Regulation Zone (C.R.Z) notification,2011?No
17.
Is forest land involved (ha)?No
18.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
19.
New/Expansion/ModernizationNew
Proposal NumberDIA/MH/MIN/14758/2018
File NumberDEIAA/A18/01
Date of Apply EC25 Apr 2018
Details of State of the project
S.No. State Name District Name Tehsil Name
(1.)MaharashtraNagpurUmred
(III) EC Attachments
1 Uploaded PFR (Pre Feasibility Report) File Annexure-PFR file
2 Uploaded Approved Mining Plan File Annexure-Approved Mining Plan file
3 Uploaded District survey report Annexure-District Survey Report
4 Uploaded Cover Letter Annexure-Cover Letter
Uploaded Additional attachments, if any
S.No. Attached File Date of Submission
NIL
(IV) Undertaking
The aforesaid application and documents furnished here with are true to my knowledge.
(IV).(i)
NameJV ANALYTICAL SERVICES
DesignationPartner
Company JV ANALYTICAL SERVICES
Address40/A, 1st & 2 nd Floor Samay Apartment, Bhau Patil Road, Bopodi, Pune
Print