(i).Name of the Mining Lease site GRANITE BUILDING STONE QUARRY OF Smt MOLY SHAJI
(ii).Location / site (GPS Co-ordinate) 10°42'17.33"N to 10°42'20.67"N 76°21'27.69"E to 76°21'32.35"E
Annexure-GPS file      
(iii).
Type of LeaseIndivisual Area
Size of the Mining Lease (in ha.)0.971 ha.
(iv).Capacity of the Mining Lease (TPA) 40022
(v).Period of Mining Lease 5
(vi).Expected cost of the Project 35
(vii).
Have you hired Consultant/Registered Qualified Person(RQP) for preparing document?Yes
Accreditation No.DMG/KERALA/RQP/7/2016 
Name of Consultant/RQPNAZAR AHAMED KV
Address NSQUARE MINING AND ENVIRONMENTAL SOLUTIONS,XAITOON PLAZA,EDAPPAL,MALAPPURAM
Mobile No.9447177533
Landline No.2677533
Email Idgeologistna@gmail.com
(II) Environmental Sensitivity
S.No Areas Distance in kilometer / Details
1. (i).  Nearest rail or road bridge over the concerned river,rivulet,nallah etc. in kms.  9 km
2. (ii). Nearest Infrastructural along with distance in kms  2 km
(iii). Nearest Railway Line along with distance in kms  9 km
(iv). Nearest National Highway along with distance in kms  14 km
(v). Nearest State Highway along with distance in kms  3 km
(vi). Nearest Major District Road along with distance in kms 1 km
(vii). Nearest Any Other Road along with distance in kms  0.5 km
(viii). Nearest Electric transmission line pole or tower distance in kms  0.5 km
(ix). Nearest Canal or check dam or reservoirs or lake or ponds distance in kms  1.5 km
(x). Nearest In-take for drinking water pump house distance in kms  0.5 km
(xi). Nearest In-take for Irrigation canal pumps distance in kms  0.5 km
3. Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
None within 0.5 Kms of the project site
4. Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Pudhu kollam pond-1.5Km River-Bharathapuzha-4km Coastal area-45 km Peechi-Vazhani wild life sanctuary-24km Chulanur peafowl sanctuary -13km Forest-Kerakakunnu-3.5km
5. Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No such Protected important species within the 0.5Km radius from the project site.
6. Inland, coastal, marine or underground waters Coastal Area-45Km, Water Bodies-Bharathapuzha-4Km, Pudhu kollam pond-1.5km
7. State, National boundaries State boundary-54km
8. Routes or facilities used by the public for access to recreation or other tourist,pilgrim areas NH 47-14Km, State high way: Chelakkara-Pazhayannur-3Km District road: Chelakkara-Karukkakadavu Road-1Km, Panchayath Road: Melamkole Panchayath Road-0.5Km
9. Defence installations None within 0. 5 Km of the project site
10. Densely populated or built-up area, distance from nearest human habitation The nearest human settlements are more than 100m away from project site.
11. Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship,community facilities) Hospital : Chelakkara Taluk Hospital, 2 Kms. School : NMLP school 1 Kms. Church : Chelakkara 2km. Temple : : Chelakkara, 2Kms. Mosque/Masjid :Parakkad Poovathani juma masjid,2 Kms.
12. Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) Forest- Kerakakunnu-3.5km Peechi-Vazhani wild life sanctuary-24km Chulanur peafowl sanctuary -13km
13. Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) Not applicable, since this is Fresh proposal
14. Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) No, Permit area is not susceptible to natural Hazard, as there is no history of such incidents
15.
Is proposed mining site located over or near fissure/fracture for ground water recharge?No
16.
Whether the proposal involves approval or clearance under the following Regulations or Acts namely?
(a).
The Forest (Conservation) Act,1980?No
(b).
The Wildlife (Protection) Act,1972?No
(c).
The Coastal Regulation Zone (C.R.Z) notification,2011?No
17.
Is forest land involved (ha)?No
18.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
19.
New/Expansion/ModernizationNew
Proposal NumberDIA/KL/MIN/17099/2018
File NumberE1-13300/2018
Date of Apply EC04 Sep 2018
Details of State of the project
S.No. State Name District Name Tehsil Name
(1.)KeralaThrissurThalapilly
(III) EC Attachments
1 Uploaded PFR (Pre Feasibility Report) File Annexure-PFR file
2 Uploaded Approved Mining Plan File Annexure-Approved Mining Plan file
3 Uploaded District survey report Annexure-District Survey Report
4 Uploaded Cover Letter Annexure-Cover Letter
Uploaded Additional attachments, if any
S.No. Attached File Date of Submission
(1.)ID CARD & PHOTO ID04 Sep 2018
(2.)LOI&MPAL04 Sep 2018
(3.)FORM1M04 Sep 2018
(4.)RQP04 Sep 2018
(5.)VILLAGE DOCUMENTS04 Sep 2018
(IV) Undertaking
The aforesaid application and documents furnished here with are true to my knowledge.
(IV).(i)
NameGRANITE BUILDING STONE QUARRY OF SMT MOLY SHAJI
DesignationPROPRIETOR
Company GRANITE BUILDING STONE QUARRY OF SMT MOLY SHAJI
AddressVENGANELLUR VILLAGE,THALAPPILLY TALUK,THRISSUR DISTRICT
Print