APPENDIX I
(See Paragraph-6)
FORM 1M
Note : If space provided against any parameter is inadequate,Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form 1M. Please note that all such Annexures must be part of single pdf document.
(I)Basic Informations
S.No.Item Details
(i).Name of the Mining Lease site BUILDING STONE QUARRY OF MOHAMMED KK
(ii).Location / site (GPS Co-ordinate) Latitude : 11°17'32.82"N to 11°17'28.42"N Longitude : 76°3'43.35"E to 76°3'38.55"E
Annexure-GPS file      
(iii).
Type of LeaseIndivisual Area
Size of the Mining Lease (in ha.)0.9199 ha.
(iv).Capacity of the Mining Lease (TPA) 53294
(v).Period of Mining Lease 5
(vi).Expected cost of the Project 30
(vii).
Have you hired Consultant/Registered Qualified Person(RQP) for preparing document?Yes
Accreditation No.RQP/7/2016 
Name of Consultant/RQPNAZAR AHAMED KV
Address N SQUARE MINING & ENVIRONMENTAL SOLUTIONS LTD, XAITOON COMPLEX, EDAPPAL, PO, MALAPPURAM, KERALA.
Mobile No.9447177533
Landline No.2677533
Email Idgeologistna@gmail.com
(II) Environmental Sensitivity
S.No Areas Distance in kilometer / Details
1. (i).  Nearest rail or road bridge over the concerned river,rivulet,nallah etc. in kms.  1.5 km
2. (ii). Nearest Infrastructural along with distance in kms  1.5 km
(iii). Nearest Railway Line along with distance in kms  46 km
(iv). Nearest National Highway along with distance in kms  26 km
(v). Nearest State Highway along with distance in kms  7 km
(vi). Nearest Major District Road along with distance in kms 1.5 km
(vii). Nearest Any Other Road along with distance in kms  4 km
(viii). Nearest Electric transmission line pole or tower distance in kms  3 km
(ix). Nearest Canal or check dam or reservoirs or lake or ponds distance in kms  1.5 km
(x). Nearest In-take for drinking water pump house distance in kms  1.5 km
(xi). Nearest In-take for Irrigation canal pumps distance in kms  0 km
3. Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
KAKKADAMPOYIL– 20 Km
4. Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests KODUMPUZHA FOREST,AREACODE-8 KM
5. Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration KODUMPUZHA FOREST,AREACODE-8 KM
6. Inland, coastal, marine or underground waters None within 0. 5 Kms of the project site
7. State, National boundaries NADUKANI-GUDALLUR-76 KM
8. Routes or facilities used by the public for access to recreation or other tourist,pilgrim areas KAKKADUMPOYIL-20 KM
9. Defence installations MSP CAMP-AREACODE 10KM
10. Densely populated or built-up area, distance from nearest human habitation Areacode - 10km, Mukkam - 10km
11. Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship,community facilities) School: st. Mary High School - 1.5km Hospital: CHC, Vettilappura - 5km Place Of Worship: st.marys church-thottumukkam - 1.7km
12. Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) None within 0.5 Km of the project site
13. Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) Not applicable
14. Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) No, Permit area is not susceptible to natural hazard,as there is no history of such incidents
15.
Is proposed mining site located over or near fissure/fracture for ground water recharge?No
16.
Whether the proposal involves approval or clearance under the following Regulations or Acts namely?
(a).
The Forest (Conservation) Act,1980?No
(b).
The Wildlife (Protection) Act,1972?No
(c).
The Coastal Regulation Zone (C.R.Z) notification,2011?No
17.
Is forest land involved (ha)?No
18.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
19.
New/Expansion/ModernizationNew
Proposal NumberDIA/KL/MIN/14780/2018
File NumberH-3749/2018
Date of Apply EC25 Apr 2018
Details of State of the project
S.No. State Name District Name Tehsil Name
(1.)KeralaKozhikodeKozhikode
(III) EC Attachments
1 Uploaded PFR (Pre Feasibility Report) File Annexure-PFR file
2 Uploaded Approved Mining Plan File Annexure-Approved Mining Plan file
3 Uploaded District survey report Annexure-District Survey Report
4 Uploaded Cover Letter Annexure-Cover Letter
Uploaded Additional attachments, if any
S.No. Attached File Date of Submission
(1.)APPROVALLETTER25 Apr 2018
(2.)500mCERTIFICATE25 Apr 2018
(3.)LOI25 Apr 2018
(4.)PROPONENTAFFIDAVITS25 Apr 2018
(5.)RQPCERTIFICATE25 Apr 2018
(IV) Undertaking
The aforesaid application and documents furnished here with are true to my knowledge.
(IV).(i)
NameMOHAMMEDKK
DesignationSingleOwner
Company MOHAMMEDKK
AddressKodakkodan House, Poovathikkal Post, Urangattiri, Malappuram district, Kerala.
Print