APPENDIX I | (See Paragraph-6) | FORM 1M | | Note : If space provided against any parameter is inadequate,Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form 1M. Please note that all such Annexures must be part of single pdf document. | (I)Basic Informations | | (i). | Name of the Mining Lease site | Building Stone Quarry Of CH Sakariyya in S No:208 |
| (ii). | Location / site (GPS Co-ordinate) | 11 3 45.61 N to 11 03 49.97 E
76 21 29.34 N to 76 21 33.70 EAnnexure-GPS file |
| (iii). | |
Type of Lease | Indivisual Area | Size of the Mining Lease (in ha.) | 0.9653 ha. | | | (iv). | Capacity of the Mining Lease (TPA) | 20000 | | (v). | Period of Mining Lease | 1 | | (vi). | Expected cost of the Project | 50 | | (vii). | Have you hired Consultant/Registered Qualified Person(RQP) for preparing document? | Yes | Accreditation No. | RQP/BNG/2296/2013/A | Name of Consultant/RQP | Hareesh G Thampy | Address | Hareesh G Thampy
905-D-9th Street, Sankar Nagar, Kaimanam PO, Thiruvananthapuram-695040 | Mobile No. | 9387838782 | Landline No. | 04916666 | Email Id | gt.hareesh@gmail.com | | | (II) | Environmental Sensitivity | S.No | Areas | Distance in kilometer / Details | | | 1. | (i). Nearest rail or road bridge over the concerned river,rivulet,nallah etc. in kms. | 12 km |
| 2. | (ii). Nearest Infrastructural along with distance in kms | 50 km | | (iii). Nearest Railway Line along with distance in kms | 12 km | | (iv). Nearest National Highway along with distance in kms | 44 km | | (v). Nearest State Highway along with distance in kms | 7.7 km | | (vi). Nearest Major District Road along with distance in kms | 0.5 km | | (vii). Nearest Any Other Road along with distance in kms | 1 km | | (viii). Nearest Electric transmission line pole or tower distance in kms | 0.1 km | | (ix). Nearest Canal or check dam or reservoirs or lake or ponds distance in kms | 0 km | | (x). Nearest In-take for drinking water pump house distance in kms | .500 km | | (xi). Nearest In-take for Irrigation canal pumps distance in kms | .25 km |
| 3. | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | Nil | 4. | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | Nil | 5. | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | Nil | 6. | Inland, coastal, marine or underground waters | Kunthipuzha - 8.3 KM E | 7. | State, National boundaries | Nil | 8. | Routes or facilities used by the public for access to recreation or other tourist,pilgrim areas | Kulathippara view Point - 2.3 KM NE
Ponpara water falls-3.5 km-NE | 9. | Defence installations | Non with in 10 KM area | 10. | Densely populated or built-up area, distance from nearest human habitation | Edathanattukkara – 1 KM SW
Ambalappara - 2.7 KM E
Thiruvizhamkunnu - 3.6 KM SE | 11. | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship,community facilities) | Hospitals
Primary Health centre – 1.4 KM SW
MES Hospital - 1.6 KM W
KIMS Al-Shifa Super speciality hospital - 7 KM SW
Temples
Pathiramanna Siva temple – 2.1 KM S Pulakkurassy Siva temple – 1.6 KM S
Chavala Temple – 1.6 KM NW
Church
St. William Church – 2.0 KM N
Mosque
Kilayapadam Masjid – 1.5 KM N
Masjid Umarul Farooq – 1.8 KM N
Chuyikunnu Masjid -1.9 KM N
Thodukadu Salafi Masjid - 2.1 KM E
Masjid - 2.2 KM E
Tullakallu Masjid – 2.1 KM SE
Thiruvizh | 12. | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | Old quarry -1.60m S
Old quarry -70m SW
Old quarry -2.7 KM NW | 13. | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | Nil | 14. | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) | Nil | 15. | Is proposed mining site located over or near fissure/fracture for ground water recharge? | No |
| 16. | Whether the proposal involves approval or clearance under the following Regulations or Acts namely? | | (a). | The Forest (Conservation) Act,1980? | No | | | (b). | The Wildlife (Protection) Act,1972? | No | | | (c). | The Coastal Regulation Zone (C.R.Z) notification,2011? | No |
| | | | 17. | Is forest land involved (ha)? | No | |
| 18. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No |
|
| 19. | New/Expansion/Modernization | New | Proposal Number | DIA/KL/MIN/14560/2018 | File Number | DIA/KL/PL/18/2018 | Date of Apply EC | 16 Apr 2018 |
| |
| Details of State of the project |
---|
S.No. | State Name | District Name | Tehsil Name |
---|
(1.) | Kerala | Palakkad | Mannarkad | | (IV) | Undertaking | | The aforesaid application and documents furnished here with are true to my knowledge. | (IV).(i) | Name | SAKARIYYA MANNARKKAD | Designation | PROPONENT | Company | SAKARIYYA MANNARKKAD | Address | CH SAKARIYYA, PRESIDENT, MANNARKKAD KARINGAL QUARRY OPERETERSINDUSTRIAL COPERATIVE SOCIETY LTD,NO.S.IND(P)179, VIYAKARUSSI PO,MANNARKKAD,PALAKKAD DISTRICT |
| |
|