(I)Basic Informations
S.No.Item Details
(i).Name of the Mining Lease site Building Stone Quarry of E Vasanth Kumar
(ii).Location / site (GPS Co-ordinate) N14014’48.9” & E 76021’14.3” N14014’48.9” & E 76021’16.0” N14014’46.3” & E 76021’16.1” N14014’46.3” & E 76021’14.4”
Annexure-GPS file      
(iii).
Type of LeaseIndivisual Area
Size of the Mining Lease (in ha.)0.40 ha.
(iv).Capacity of the Mining Lease (TPA) 14788
(v).Period of Mining Lease 20
(vi).Expected cost of the Project 24
(vii).
Have you hired Consultant/Registered Qualified Person(RQP) for preparing document?Yes
Accreditation No.NABET 0030 
Name of Consultant/RQPS. Kameswara Rao
Address Global Environment & Mining Services, 3rd Main Road, Basaveswara Badawane, Hospet-583201, Ballari District, Karnataka
Mobile No.9448479433
Landline No.651111
Email Idgems_hpt@yahoo.com
(II) Environmental Sensitivity
S.No Areas Distance in kilometer / Details
1. (i).  Nearest rail or road bridge over the concerned river,rivulet,nallah etc. in kms.  3.60 km
2. (ii). Nearest Infrastructural along with distance in kms  0 km
(iii). Nearest Railway Line along with distance in kms  5.0 km
(iv). Nearest National Highway along with distance in kms  1.5 km
(v). Nearest State Highway along with distance in kms  3.2 km
(vi). Nearest Major District Road along with distance in kms 3.2 km
(vii). Nearest Any Other Road along with distance in kms  1.8 km
(viii). Nearest Electric transmission line pole or tower distance in kms  1.5 km
(ix). Nearest Canal or check dam or reservoirs or lake or ponds distance in kms  4.5 km
(x). Nearest In-take for drinking water pump house distance in kms  1.5 km
(xi). Nearest In-take for Irrigation canal pumps distance in kms  0 km
3. Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
Nil
4. Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Agricultural lands are located in buffer zone area. The village pond is located at Chikkapura at about 2.2km towards West from the lease. These water bodies are far away from the quarry area. There are no biospheres, Mountains etc.,
5. Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration There is no sensitive flora & fauna in this area for breeding, nesting, foraging resting over wintering migration.
6. Inland, coastal, marine or underground waters Nil
7. State, National boundaries Nil
8. Routes or facilities used by the public for access to recreation or other tourist,pilgrim areas Nil
9. Defence installations Nil
10. Densely populated or built-up area, distance from nearest human habitation The Village Echalanagenahalli at a distance of 1.5 km from the quarry area by road. The population of Echalanagenahalli is about 1197.
11. Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship,community facilities) Primary Schools are located at Chitradurga village. The hospitals, colleges, places of worship community facilities etc., are located at Chitradurga town which is at a distance of 6.0kms by road from the lease area. However, the major Hospital, Colleges etc. facilities are available at Chitradurga.
12. Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) The agricultural activities, minerals are in buffer zone area. There are few Building Stone Quarries are located in buffer zone.
13. Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) The existing building stone quarry are producing small quantities. Hence, there may not be much impact on air pollution.
14. Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) Nil
15.
Is proposed mining site located over or near fissure/fracture for ground water recharge?No
16.
Whether the proposal involves approval or clearance under the following Regulations or Acts namely?
(a).
The Forest (Conservation) Act,1980?No
(b).
The Wildlife (Protection) Act,1972?No
(c).
The Coastal Regulation Zone (C.R.Z) notification,2011?No
17.
Is forest land involved (ha)?No
18.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
19.
New/Expansion/ModernizationNew
Proposal NumberDIA/KA/MIN/7595/2017
File NumberDEIAA:47/2017-18
Date of Apply EC19 Jul 2017
Details of State of the project
S.No. State Name District Name Tehsil Name
(1.)KarnatakaChitradurgaChitradurga
(III) EC Attachments
1 Uploaded PFR (Pre Feasibility Report) File Annexure-PFR file
2 Uploaded Approved Mining Plan File Annexure-Approved Mining Plan file
3 Uploaded District survey report Annexure-District Survey Report
4 Uploaded Cover Letter Annexure-Cover Letter
Uploaded Additional attachments, if any
S.No. Attached File Date of Submission
NIL
(IV) Undertaking
The aforesaid application and documents furnished here with are true to my knowledge.
(IV).(i)
NameBUILDING STONE QUARRY OF E VASANTH KUMAR
DesignationOwner
Company BUILDING STONE QUARRY OF E VASANTH KUMAR
AddressBuilding Stone Quarry of E Vasanth Kumar, Sy No. 14/P1 of Echalanagenahalli Village, Chitradurga Taluk and District, Karnataka