APPENDIX I
(See Paragraph-6)
FORM 1M
Note : If space provided against any parameter is inadequate,Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form 1M. Please note that all such Annexures must be part of single pdf document.
(I)Basic Informations
S.No.Item Details
(i).Name of the Mining Lease site Hanumalapura Building Stone Quarry
(ii).Location / site (GPS Co-ordinate) N13°52'49.5" E75°58'42.9" N13°52'46.8" E75°58'43.1" N13°52'47.2" E75°58'40.9" N13°52'49.7" E75°58'40.6"
Annexure-GPS file      
(iii).
Type of LeaseIndivisual Area
Size of the Mining Lease (in ha.)0.4047 ha.
(iv).Capacity of the Mining Lease (TPA) 12675
(v).Period of Mining Lease 20
(vi).Expected cost of the Project 40
(vii).
Have you hired Consultant/Registered Qualified Person(RQP) for preparing document?No
Reason for not hiring the Consultant/RQP B2 category project
(II) Environmental Sensitivity
S.No Areas Distance in kilometer / Details
1. (i).  Nearest rail or road bridge over the concerned river,rivulet,nallah etc. in kms.  0.6 km
2. (ii). Nearest Infrastructural along with distance in kms  0.6 km
(iii). Nearest Railway Line along with distance in kms  17 km
(iv). Nearest National Highway along with distance in kms  15 km
(v). Nearest State Highway along with distance in kms  0.4 km
(vi). Nearest Major District Road along with distance in kms 66 km
(vii). Nearest Any Other Road along with distance in kms  0.6 km
(viii). Nearest Electric transmission line pole or tower distance in kms  .55 km
(ix). Nearest Canal or check dam or reservoirs or lake or ponds distance in kms  3.2 km
(x). Nearest In-take for drinking water pump house distance in kms  0 km
(xi). Nearest In-take for Irrigation canal pumps distance in kms  0 km
3. Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
The area is not covered under any international convention.
4. Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Applied QL is approx. 1.3 km away from Malleshwara Minor Forest area.
5. Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration None in 5km radius
6. Inland, coastal, marine or underground waters There is no inland, coastal & marine water. However, Underground water table is 50-60m from general surface in surrounding area.
7. State, National boundaries No State or National boundaries within 5kms radius
8. Routes or facilities used by the public for access to recreation or other tourist,pilgrim areas Not Applicable
9. Defence installations There is no Defence installations in the applied/study area.
10. Densely populated or built-up area, distance from nearest human habitation The quarry lease area lies towards Northeast of Malleshawara village at a distance of 0.6 km.
11. Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship,community facilities) No sensitive man made land use in core zone. The quarry lease area lies towards Northeast of Malleshawara village at a distance of 0.6 km approximately and is having the School facilities for primary education. Channagiri is the Taluk Head quarter at a distance of about 17Kms NW and has schools and primary health centres and private hospitals.
12. Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No scarce resources in core zone. Areas containing important, high quality or scarce resources are far from the applied area.
13. Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) Not Applicable.
14. Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) Not applicable. The project site is in low seismic damage zone. It is situated in earthquake sensitive zone-II as defined in IS: 1893-2002
15.
Is proposed mining site located over or near fissure/fracture for ground water recharge?No
16.
Whether the proposal involves approval or clearance under the following Regulations or Acts namely?
(a).
The Forest (Conservation) Act,1980?No
(b).
The Wildlife (Protection) Act,1972?No
(c).
The Coastal Regulation Zone (C.R.Z) notification,2011?No
17.
Is forest land involved (ha)?No
18.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
19.
New/Expansion/ModernizationNew
Proposal NumberDIA/KA/MIN/16604/2018
File NumberEC/CR/8/18-19
Date of Apply EC02 Aug 2018
Details of State of the project
S.No. State Name District Name Tehsil Name
(1.)KarnatakaDavanagereChannagiri
(III) EC Attachments
1 Uploaded PFR (Pre Feasibility Report) File Annexure-PFR file
2 Uploaded Approved Mining Plan File Annexure-Approved Mining Plan file
3 Uploaded District survey report Annexure-District Survey Report
4 Uploaded Cover Letter Annexure-Cover Letter
Uploaded Additional attachments, if any
S.No. Attached File Date of Submission
NIL
(IV) Undertaking
The aforesaid application and documents furnished here with are true to my knowledge.
(IV).(i)
NameVEERABHADRA
DesignationProponent
Company VEERABHADRA
AddressLalitha Sadana, Meenakshi bhavan, Shimoga
Print