APPENDIX I
(See Paragraph-6)
FORM 1M
Note : If space provided against any parameter is inadequate,Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form 1M. Please note that all such Annexures must be part of single pdf document.
(I)Basic Informations
S.No.Item Details
(i).Name of the Mining Lease site LM BRICKS
(ii).Location / site (GPS Co-ordinate) 23°19'38.73"N 84°45'46.90"E
Annexure-GPS file      
(iii).
Type of LeaseIndivisual Area
Size of the Mining Lease (in ha.)0.80 ha.
(iv).Capacity of the Mining Lease (TPA) 2059
(v).Period of Mining Lease 5
(vi).Expected cost of the Project 20
(vii).
Have you hired Consultant/Registered Qualified Person(RQP) for preparing document?Yes
Accreditation No.RQP RNC 125 2007 A 
Name of Consultant/RQPSURENDRA SAI
Address 107D MANDIR MARG ASHOK NAGAR ROAD NO 1 RANCHI JHARKHAND 834002
Mobile No.9431766015
Landline No.2244933
Email Idsurendrasairqp@gmail.com
(II) Environmental Sensitivity
S.No Areas Distance in kilometer / Details
1. (i).  Nearest rail or road bridge over the concerned river,rivulet,nallah etc. in kms.  10 km
2. (ii). Nearest Infrastructural along with distance in kms  0.17 km
(iii). Nearest Railway Line along with distance in kms  11 km
(iv). Nearest National Highway along with distance in kms  16 km
(v). Nearest State Highway along with distance in kms  13 km
(vi). Nearest Major District Road along with distance in kms 5 km
(vii). Nearest Any Other Road along with distance in kms  0.5 km
(viii). Nearest Electric transmission line pole or tower distance in kms  1 km
(ix). Nearest Canal or check dam or reservoirs or lake or ponds distance in kms  0.39 km
(x). Nearest In-take for drinking water pump house distance in kms  0.40 km
(xi). Nearest In-take for Irrigation canal pumps distance in kms  1 km
3. Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
No such thing exists within 0.5 km of lease area
4. Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests No such area exists around the lease area.
5. Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration There are no Schedule I flora and fauna present within the study are .Sometimes local species like snakes, lizard are seen .
6. Inland, coastal, marine or underground waters NO
7. State, National boundaries Jharkhand - Chhattisgarh state Border is present West-south direction about 50 KM.
8. Routes or facilities used by the public for access to recreation or other tourist,pilgrim areas No routs passing through the project sit to recreation or other tourist, pilgrim areas.
9. Defence installations No defence installation present within 0.5 km.
10. Densely populated or built-up area, distance from nearest human habitation Bedal village near About 0.5 km north west direction.
11. Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship,community facilities) Hospitals is having dispensary and hospital at Bhandra at about 5 KM North East direction and Primary School is in the Bedal village. High School is available Bhandra at 5km and intermediate facility is available at lohardaga at 13 KM.
12. Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) Project Site doesn't contain Any such important high quality or scarce resources within the 0.5 km.
13. Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) There is no such area present .
14. Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) Area falls under Seismic Zone-III. There is no natural crisis due to the location of the project.
15.
Is proposed mining site located over or near fissure/fracture for ground water recharge?No
16.
Whether the proposal involves approval or clearance under the following Regulations or Acts namely?
(a).
The Forest (Conservation) Act,1980?No
(b).
The Wildlife (Protection) Act,1972?No
(c).
The Coastal Regulation Zone (C.R.Z) notification,2011?No
17.
Is forest land involved (ha)?No
18.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
19.
New/Expansion/ModernizationNew
Proposal NumberDIA/JH/MIN/19767/2019
File NumberTo be assigned
Date of Apply EC03 Jan 2019
Details of State of the project
S.No. State Name District Name Tehsil Name
(1.)JharkhandLohardagaBhandra
(III) EC Attachments
1 Uploaded PFR (Pre Feasibility Report) File Annexure-PFR file
2 Uploaded Approved Mining Plan File Annexure-Approved Mining Plan file
3 Uploaded District survey report Annexure-District Survey Report
4 Uploaded Cover Letter Annexure-Cover Letter
Uploaded Additional attachments, if any
S.No. Attached File Date of Submission
NIL
(IV) Undertaking
The aforesaid application and documents furnished here with are true to my knowledge.
(IV).(i)
NameSURENDRA AI
Designationrqp
Company SURENDRA AI
Addressashok nagar 1/107D Ranchi Jharkhand
Print