APPENDIX I
(See Paragraph-6)
FORM 1M
Note : If space provided against any parameter is inadequate,Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form 1M. Please note that all such Annexures must be part of single pdf document.
(I)Basic Informations
S.No.Item Details
(i).Name of the Mining Lease site Chuwa Stone Deposit of Sri Suresh Kumar in Village Chuwa, Area-3.46Ha, Mob-9123133648
(ii).Location / site (GPS Co-ordinate) The Applied area is bounded by Longitude 87°34'39.68" E & 87°34'49.63" E and latitude 25°12'45.91" N & 25°12'56.11" N
Annexure-GPS file      
(iii).
Type of LeaseIndivisual Area
Size of the Mining Lease (in ha.)3.46 ha.
(iv).Capacity of the Mining Lease (TPA) 260562.8
(v).Period of Mining Lease 10
(vi).Expected cost of the Project 80
(vii).
Have you hired Consultant/Registered Qualified Person(RQP) for preparing document?Yes
Accreditation No.30/13/1835 
Name of Consultant/RQPRAVINDRA KUMAR PRAKASH
Address ENVIRON MANTRA CONSULTING CENTER DEEP MANSION KASHYAP VIHAR OPP ASHOK NAGAR GATE NO 4 RANCHI 834002
Mobile No.8757538142
Landline No.6561605
Email Idenvironmantra@gmail.com
(II) Environmental Sensitivity
S.No Areas Distance in kilometer / Details
1. (i).  Nearest rail or road bridge over the concerned river,rivulet,nallah etc. in kms.  8 km
2. (ii). Nearest Infrastructural along with distance in kms  4 km
(iii). Nearest Railway Line along with distance in kms  8 km
(iv). Nearest National Highway along with distance in kms  12 km
(v). Nearest State Highway along with distance in kms  12 km
(vi). Nearest Major District Road along with distance in kms 4 km
(vii). Nearest Any Other Road along with distance in kms  1.5 km
(viii). Nearest Electric transmission line pole or tower distance in kms  4 km
(ix). Nearest Canal or check dam or reservoirs or lake or ponds distance in kms  10 km
(x). Nearest In-take for drinking water pump house distance in kms  15 km
(xi). Nearest In-take for Irrigation canal pumps distance in kms  15 km
3. Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
There is no such things within 5 km radius of ML area
4. Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests The area is more than 500m from the forest and other sensitive area is not within a radius of 5 km.
5. Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration There is no such area is within 5 km radius of ML area
6. Inland, coastal, marine or underground waters River Ganga is 10 KM from the proposed area
7. State, National boundaries State boundary is more than 10 km from the ML area
8. Routes or facilities used by the public for access to recreation or other tourist,pilgrim areas There is no such important facilitate area within 5 km radius of ML area
9. Defence installations There is a army camp in sahibganj 10 km from the ML area.
10. Densely populated or built-up area, distance from nearest human habitation Mahadevganj is dense populated village 4 km from the ML area.
11. Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship,community facilities) There is a hospital 8 km from the applied area, A temple is there 4 km from the ML area
12. Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No such important things within 10 km radius of ML area.
13. Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No such area within 5 km radius of ML area
14. Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) No such area within 10 km radius of ML area.
15.
Is proposed mining site located over or near fissure/fracture for ground water recharge?No
16.
Whether the proposal involves approval or clearance under the following Regulations or Acts namely?
(a).
The Forest (Conservation) Act,1980?No
(b).
The Wildlife (Protection) Act,1972?No
(c).
The Coastal Regulation Zone (C.R.Z) notification,2011?No
17.
Is forest land involved (ha)?No
18.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
19.
New/Expansion/ModernizationNew
Proposal NumberDIA/JH/MIN/11883/2017
File NumberFile No.-133/18
Date of Apply EC26 Dec 2017
Details of State of the project
S.No. State Name District Name Tehsil Name
(1.)JharkhandSahibganjMandro
(III) EC Attachments
1 Uploaded PFR (Pre Feasibility Report) File Annexure-PFR file
2 Uploaded Approved Mining Plan File Annexure-Approved Mining Plan file
3 Uploaded District survey report Annexure-District Survey Report
4 Uploaded Cover Letter Annexure-Cover Letter
Uploaded Additional attachments, if any
S.No. Attached File Date of Submission
(1.)Hydrogeology Report26 Dec 2017
(IV) Undertaking
The aforesaid application and documents furnished here with are true to my knowledge.
(IV).(i)
NameENVIRON MANTRA CONSULTING CENTER
DesignationManaging Director
Company ENVIRON MANTRA CONSULTING CENTER
AddressENVIRON MANTRA CONSULTING CENTER, DEEP MANSION, KASHYAP VIHAR
Print