APPENDIX I | (See Paragraph-6) | FORM 1M | | Note : If space provided against any parameter is inadequate,Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form 1M. Please note that all such Annexures must be part of single pdf document. | (I)Basic Informations | | (i). | Name of the Mining Lease site | Mauja & Mohal Riwali Mining Project |
| (ii). | Location / site (GPS Co-ordinate) | 77° 29' 22.71” E 31°21'12.97” N
77° 28' 57.83” E 31°21'11.19” NAnnexure-GPS file |
| (iii). | |
Type of Lease | Indivisual Area | Size of the Mining Lease (in ha.) | 0.5119 ha. | | | (iv). | Capacity of the Mining Lease (TPA) | 11557 | | (v). | Period of Mining Lease | 5 | | (vi). | Expected cost of the Project | 20.51 | | (vii). | Have you hired Consultant/Registered Qualified Person(RQP) for preparing document? | No | Reason for not hiring the Consultant/RQP | PROPONENT IS SELF CAPABLE | | | (II) | Environmental Sensitivity | S.No | Areas | Distance in kilometer / Details | | | 1. | (i). Nearest rail or road bridge over the concerned river,rivulet,nallah etc. in kms. | 0.24 km |
| 2. | (ii). Nearest Infrastructural along with distance in kms | 135 km | | (iii). Nearest Railway Line along with distance in kms | 105 km | | (iv). Nearest National Highway along with distance in kms | 0.055 km | | (v). Nearest State Highway along with distance in kms | 0 km | | (vi). Nearest Major District Road along with distance in kms | 0 km | | (vii). Nearest Any Other Road along with distance in kms | 0 km | | (viii). Nearest Electric transmission line pole or tower distance in kms | 0.008 km | | (ix). Nearest Canal or check dam or reservoirs or lake or ponds distance in kms | 0.24 km | | (x). Nearest In-take for drinking water pump house distance in kms | 0 km | | (xi). Nearest In-take for Irrigation canal pumps distance in kms | 0 km |
| 3. | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | No | 4. | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | No | 5. | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | No | 6. | Inland, coastal, marine or underground waters | No | 7. | State, National boundaries | BEYOND 10KM | 8. | Routes or facilities used by the public for access to recreation or other tourist,pilgrim areas | NO | 9. | Defence installations | NO | 10. | Densely populated or built-up area, distance from nearest human habitation | Rampur Bushehar = 25 Kms.
Dutt Nagar = 8 Kms.
Kumarsain = 20 Kms. | 11. | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship,community facilities) | PHC Banot = 971 meters.
School = 383 meters
Temple Kepu= 2020 meters
Bridge = 606 meters
NH Shimla-Rampur = 55 meters | 12. | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | Satluj River is about 240 meters away from the lease area
No ground water source, surface water source, forestry, agriculture, fisheries farms, tourist place or mineral wealth exist near the lease area | 13. | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | NO | 14. | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) | NO | 15. | Is proposed mining site located over or near fissure/fracture for ground water recharge? | No |
| 16. | Whether the proposal involves approval or clearance under the following Regulations or Acts namely? | | (a). | The Forest (Conservation) Act,1980? | No | | | (b). | The Wildlife (Protection) Act,1972? | No | | | (c). | The Coastal Regulation Zone (C.R.Z) notification,2011? | No |
| | | | 17. | Is forest land involved (ha)? | No | |
| 18. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No |
|
| 19. | New/Expansion/Modernization | New | Proposal Number | DIA/HP/MIN/8411/2017 | File Number | To be assigned | Date of Apply EC | 15 Aug 2017 |
| |
|