(I)Basic Informations
S.No.Item Details
(i).Name of the Mining Lease site Sunil Kumar Khasra no 2185, 2186, 2190, 2191, 2192/2 mauza & mohal Fatehpur tehsil & District Una measuring 01-80-35Hac private land river bed
(ii).Location / site (GPS Co-ordinate) Latitude : 31°23'2.11"N Longitude : 76°17'17.90"E
Annexure-GPS file      
(iii).
Type of LeaseCluster Area
Size of the Mining Lease (in ha.)3.8275 ha.
(iv).Capacity of the Mining Lease (TPA) 34600
(v).Period of Mining Lease 5
(vi).Expected cost of the Project 3
(vii).
Have you hired Consultant/Registered Qualified Person(RQP) for preparing document?No
Reason for not hiring the Consultant/RQP mining plan prepared by RQP Sh JL Sud HPRQP/02/201
(II) Environmental Sensitivity
S.No Areas Distance in kilometer / Details
1. (i).  Nearest rail or road bridge over the concerned river,rivulet,nallah etc. in kms.  3.5 km
2. (ii). Nearest Infrastructural along with distance in kms  2 km
(iii). Nearest Railway Line along with distance in kms  6 km
(iv). Nearest National Highway along with distance in kms  5 km
(v). Nearest State Highway along with distance in kms  7 km
(vi). Nearest Major District Road along with distance in kms 1 km
(vii). Nearest Any Other Road along with distance in kms  0 km
(viii). Nearest Electric transmission line pole or tower distance in kms  0 km
(ix). Nearest Canal or check dam or reservoirs or lake or ponds distance in kms  0 km
(x). Nearest In-take for drinking water pump house distance in kms  0 km
(xi). Nearest In-take for Irrigation canal pumps distance in kms  0 km
3. Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
NA
4. Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests NA
5. Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration NA
6. Inland, coastal, marine or underground waters NA
7. State, National boundaries HIMACHAL -PUNJAB 5
8. Routes or facilities used by the public for access to recreation or other tourist,pilgrim areas NA
9. Defence installations NA
10. Densely populated or built-up area, distance from nearest human habitation FATEHPUR 1.5
11. Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship,community facilities) JNV PHEKHUBELA 3
12. Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) NA
13. Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) NA
14. Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) NA
15.
Is proposed mining site located over or near fissure/fracture for ground water recharge?No
16.
Whether the proposal involves approval or clearance under the following Regulations or Acts namely?
(a).
The Forest (Conservation) Act,1980?No
(b).
The Wildlife (Protection) Act,1972?No
(c).
The Coastal Regulation Zone (C.R.Z) notification,2011?No
17.
Is forest land involved (ha)?No
18.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
19.
New/Expansion/ModernizationNew
Proposal NumberDIA/HP/MIN/13986/2018
File Numberdeiaa/una/2017/035
Date of Apply EC19 Mar 2018
Details of State of the project
S.No. State Name District Name Tehsil Name
(1.)Himachal PradeshUnaUna(T)
(III) EC Attachments
1 Uploaded PFR (Pre Feasibility Report) File Annexure-PFR file
2 Uploaded Approved Mining Plan File Annexure-Approved Mining Plan file
3 Uploaded District Survey Report Annexure-District Survey Report
4 Uploaded Cover Letter Annexure-Cover Letter
Uploaded Additional attachments, if any
S.No. Attached File Date of Submission
(1.)Letter of Intent19 Mar 2018
(2.)distance certificate19 Mar 2018
(IV) Undertaking
The aforesaid application and documents furnished here with are true to my knowledge.
(IV).(i)
NameDSANOH
DesignationOwner
Company DSANOH