APPENDIX I | (See Paragraph-6) | FORM 1M | | Note : If space provided against any parameter is inadequate,Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form 1M. Please note that all such Annexures must be part of single pdf document. | (I)Basic Informations | | (i). | Name of the Mining Lease site | Kharkena Dolomite Mine |
| (ii). | Location / site (GPS Co-ordinate) | Longitude E 82°01’44.2” to 82°01’53.2”
Latitude N 21°58’29.1” to 21°58’35.04”Annexure-GPS file |
| (iii). | |
Type of Lease | Indivisual Area | Size of the Mining Lease (in ha.) | 4.088 ha. | | | (iv). | Capacity of the Mining Lease (TPA) | 45000 | | (v). | Period of Mining Lease | 30 | | (vi). | Expected cost of the Project | 50 | | (vii). | Have you hired Consultant/Registered Qualified Person(RQP) for preparing document? | Yes | Accreditation No. | RQP/CG/24/ | Name of Consultant/RQP | Deepak Kumar Sahu | Address | Near Hemant Provision StoreShanti Vihar Colony DanganiyaRaipur (C.G) | Mobile No. | 9617160900 | Landline No. | 4070731 | Email Id | jagmohan11@gmail.com | | | (II) | Environmental Sensitivity | S.No | Areas | Distance in kilometer / Details | | | 1. | (i). Nearest rail or road bridge over the concerned river,rivulet,nallah etc. in kms. | 2.0 km |
| 2. | (ii). Nearest Infrastructural along with distance in kms | 2.0 km | | (iii). Nearest Railway Line along with distance in kms | 5.0 km | | (iv). Nearest National Highway along with distance in kms | 1.3 km | | (v). Nearest State Highway along with distance in kms | 6.0 km | | (vi). Nearest Major District Road along with distance in kms | 17 km | | (vii). Nearest Any Other Road along with distance in kms | 0.1 km | | (viii). Nearest Electric transmission line pole or tower distance in kms | 2.0 km | | (ix). Nearest Canal or check dam or reservoirs or lake or ponds distance in kms | 2.0 km | | (x). Nearest In-take for drinking water pump house distance in kms | 2.0 km | | (xi). Nearest In-take for Irrigation canal pumps distance in kms | 2.0 km |
| 3. | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | No area is protected under international convention, national or local legislation for their ecological landscape within 15km radius from the project site | 4. | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | no area present within 15km radius from the project site which are important or sensitive for ecological reason | 5. | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | ano area within 15km radius from the project site which are used by protected , important or sensitive species of flora or fauna | 6. | Inland, coastal, marine or underground waters | Maniyari river is present approx. 2.0 km from the project site | 7. | State, National boundaries | there is no state or national boundaries within 15km from the project site | 8. | Routes or facilities used by the public for access to recreation or other tourist,pilgrim areas | there is no routes or facilities used by the public for access to recreation or other tourist , pilgrim areas present within 15km from the project site | 9. | Defence installations | there is no defence installation within 15km from the project site | 10. | Densely populated or built-up area, distance from nearest human habitation | bilaspur city is approx. 17km from the project site | 11. | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship,community facilities) | Bilaspur city is approx. 17km from the project site | 12. | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | there is no area within 15km from the project site which are containing importanyt , high quality or scarce resources. | 13. | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | there is no area within 15km radius from the project site which are subjected to pollution or environmental damage | 14. | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) | there is no area within 15km from the project site which are susceptible to natural hazard which could cause the project to present environmental problems | 15. | Is proposed mining site located over or near fissure/fracture for ground water recharge? | No |
| 16. | Whether the proposal involves approval or clearance under the following Regulations or Acts namely? | | (a). | The Forest (Conservation) Act,1980? | No | | | (b). | The Wildlife (Protection) Act,1972? | No | | | (c). | The Coastal Regulation Zone (C.R.Z) notification,2011? | No |
| | | | 17. | Is forest land involved (ha)? | No | |
| 18. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No |
|
| 19. | New/Expansion/Modernization | New | Proposal Number | DIA/CG/MIN/4049/2017 | File Number | 4049/2017 | Date of Apply EC | 16 Jan 2017 |
| |
| Details of State of the project |
---|
S.No. | State Name | District Name | Tehsil Name |
---|
(1.) | Chhattisgarh | Bilaspur | Takhatpur | | (IV) | Undertaking | | The aforesaid application and documents furnished here with are true to my knowledge. | (IV).(i) | Name | AKASH DOLOMITE MINES | Designation | Owner | Company | AKASH DOLOMITE MINES | Address | Village : Kharkena Tehsil: Takatpur Dist: Bilaspur |
| |
|