APPENDIX I | (See Paragraph-6) | FORM 1M | | Note : If space provided against any parameter is inadequate,Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form 1M. Please note that all such Annexures must be part of single pdf document. | (I)Basic Informations | | (i). | Name of the Mining Lease site | AROUD SAND MINE
APPLICANT:- SARPANCH
GRAM PANCHAYAT AROUD
VILL- AROUD, TEH- BALOD,
DISTT- BALOD.(C.G)
KHASRA NO- 01, AREA- 4.00 HECT |
| (ii). | Location / site (GPS Co-ordinate) | Latitude(N) : 20°48'17.89"N to 20°48'33.82"N
Longitude(E): 81°14'0.49"E to 81°14'11.92"EAnnexure-GPS file |
| (iii). | |
Type of Lease | Indivisual Area | Size of the Mining Lease (in ha.) | 4 ha. | | | (iv). | Capacity of the Mining Lease (TPA) | 45000 | | (v). | Period of Mining Lease | . | | (vi). | Expected cost of the Project | 5 | | (vii). | Have you hired Consultant/Registered Qualified Person(RQP) for preparing document? | No | Reason for not hiring the Consultant/RQP | NA | | | (II) | Environmental Sensitivity | S.No | Areas | Distance in kilometer / Details | | | 1. | (i). Nearest rail or road bridge over the concerned river,rivulet,nallah etc. in kms. | . km |
| 2. | (ii). Nearest Infrastructural along with distance in kms | . km | | (iii). Nearest Railway Line along with distance in kms | 3 km | | (iv). Nearest National Highway along with distance in kms | 9 km | | (v). Nearest State Highway along with distance in kms | 1.5 km | | (vi). Nearest Major District Road along with distance in kms | 1.5 km | | (vii). Nearest Any Other Road along with distance in kms | . km | | (viii). Nearest Electric transmission line pole or tower distance in kms | 1 km | | (ix). Nearest Canal or check dam or reservoirs or lake or ponds distance in kms | 2 km | | (x). Nearest In-take for drinking water pump house distance in kms | . km | | (xi). Nearest In-take for Irrigation canal pumps distance in kms | . km |
| 3. | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | No such area is located within the 10 km radius of the mining lease area. | 4. | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | It is a sand mine .Sand mine is situated in river. So water courses are available in the lease area. | 5. | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | No such area is located within the 10 km radius of the mining lease area. | 6. | Inland, coastal, marine or underground waters | No such area is located within the 10 km radius of the mining lease area. | 7. | State, National boundaries | There is no any state or national boundaries within the 10 km radius of the mining lease area. | 8. | Routes or facilities used by the public for access to recreation or other tourist,pilgrim areas | No routes facilities are available in the lease area which is used for recreation or other tourist. | 9. | Defence installations | The area is not located close to any of the defence installation. | 10. | Densely populated or built-up area, distance from nearest human habitation | Densly Populated Area- Balod at 10 km, human habitation – village Aroud at 1.5 km | 11. | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship,community facilities) | School in Aroud is about 1.5 km | 12. | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | - | 13. | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | None around 10 km | 14. | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) | There is no incidence of landslide erosion , flooding or extreme or adverse climatic conditions in the area. | 15. | Is proposed mining site located over or near fissure/fracture for ground water recharge? | No |
| 16. | Whether the proposal involves approval or clearance under the following Regulations or Acts namely? | | (a). | The Forest (Conservation) Act,1980? | No | | | (b). | The Wildlife (Protection) Act,1972? | No | | | (c). | The Coastal Regulation Zone (C.R.Z) notification,2011? | No |
| | | | 17. | Is forest land involved (ha)? | No | |
| 18. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No |
|
| 19. | New/Expansion/Modernization | New | Proposal Number | DIA/CG/MIN/15265/2018 | File Number | DEIAA_Balod_2018-19_006 | Date of Apply EC | 17 May 2018 |
| |
|