APPENDIX I
(See Paragraph-6)
FORM 1M
Note : If space provided against any parameter is inadequate,Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form 1M. Please note that all such Annexures must be part of single pdf document.
(I)Basic Informations
S.No.Item Details
(i).Name of the Mining Lease site Smt Pujari Parvathamma Laterite Mine
(ii).Location / site (GPS Co-ordinate) 1.17°45'32.64"N 82°17'46.17"E 2.17°45'33.28"N 82°17'42.46"E 3.17°45'33.79"N 82°17'39.17"E 4.17°45'34.79"N 82°17'41.18"E 5.17°45'35.95"N 82°17'42.72"E 6.17°45'36.98"N 82°17'43.67"E 7.17°45'39.99"N 82°1
Annexure-GPS file      
(iii).
Type of LeaseIndivisual Area
Size of the Mining Lease (in ha.)3.090 ha.
(iv).Capacity of the Mining Lease (TPA) 293383.7
(v).Period of Mining Lease 20
(vi).Expected cost of the Project 30
(vii).
Have you hired Consultant/Registered Qualified Person(RQP) for preparing document?No
Reason for not hiring the Consultant/RQP Due to non availability of Consultants
(II) Environmental Sensitivity
S.No Areas Distance in kilometer / Details
1. (i).  Nearest rail or road bridge over the concerned river,rivulet,nallah etc. in kms.  51 km
2. (ii). Nearest Infrastructural along with distance in kms  0.14 km
(iii). Nearest Railway Line along with distance in kms  51 km
(iv). Nearest National Highway along with distance in kms  0 km
(v). Nearest State Highway along with distance in kms  0 km
(vi). Nearest Major District Road along with distance in kms 18 km
(vii). Nearest Any Other Road along with distance in kms  5 km
(viii). Nearest Electric transmission line pole or tower distance in kms  1 km
(ix). Nearest Canal or check dam or reservoirs or lake or ponds distance in kms  0 km
(x). Nearest In-take for drinking water pump house distance in kms  0.14 km
(xi). Nearest In-take for Irrigation canal pumps distance in kms  0 km
3. Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
There are no areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value
4. Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Bionti RF - 0.48km - S direction. Pedavalasa RF - 5.0 km - NE direction
5. Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration There are no areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration
6. Inland, coastal, marine or underground waters No
7. State, National boundaries No
8. Routes or facilities used by the public for access to recreation or other tourist,pilgrim areas No
9. Defence installations No
10. Densely populated or built-up area, distance from nearest human habitation The project impact area has no urban or semi-urban area. The PIA consists of rural area with low agricultural activity.
11. Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship,community facilities) The PIA consists of community facilities in various villages, however no major impact is anticipated, as the mine is away from the residential area.
12. Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No
13. Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) The area is undeveloped and consists of very few industries.
14. Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) No
15.
Is proposed mining site located over or near fissure/fracture for ground water recharge?No
16.
Whether the proposal involves approval or clearance under the following Regulations or Acts namely?
(a).
The Forest (Conservation) Act,1980?No
(b).
The Wildlife (Protection) Act,1972?No
(c).
The Coastal Regulation Zone (C.R.Z) notification,2011?No
17.
Is forest land involved (ha)?No
18.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
19.
New/Expansion/ModernizationNew
Proposal NumberDIA/AP/MIN/17143/2018
File Number7.6/deiaa/ap/vsp/18-19
Date of Apply EC07 Sep 2018
Details of State of the project
S.No. State Name District Name Tehsil Name
(1.)Andhra PradeshVisakhapatnamGudem kotha veedhi
(III) EC Attachments
1 Uploaded PFR (Pre Feasibility Report) File Annexure-PFR file
2 Uploaded Approved Mining Plan File Annexure-Approved Mining Plan file
3 Uploaded District survey report Annexure-District Survey Report
4 Uploaded Cover Letter Annexure-Cover Letter
Uploaded Additional attachments, if any
S.No. Attached File Date of Submission
(1.)FORM 107 Sep 2018
(2.)DD07 Sep 2018
(3.)500 mts Cluster Map07 Sep 2018
(IV) Undertaking
The aforesaid application and documents furnished here with are true to my knowledge.
(IV).(i)
NameSMT P PARVATHAMMA
DesignationBusiness
Company SMT P PARVATHAMMA
AddressSmt P Parvathamma W/o Rajarao D No 1-2 Chaparathipalem Village G K Veedhi Mandalam Visakhapatnam District Andhra Pradesh