No. J-11015/08/2008-IA.II(M)
Government of India
Ministry of Environment & Forests
Paryavaran Bhawan,
CGO Complex,
New Delhi-110510.
To
Dated: 12th June 2008
Chief General Manager,
M/s Neyveli Lignite
Corp. Ltd.,
Neyveli House,
135, Periyar, EVR High Road,
Kilpauk, Chennai – 600101.
Sub: Hadla Lignite Mine Project (2.5 MTPA) of M/s Neyveli Lignite Corp. Ltd., in
villages Hadlan Rawaloton, Hadlan Bhatiyan, Mokha, Dist.
Bikaner, Rajasathn (TOR)
Sir,
This
is with reference to your letter No. GM/P&BD/HLMP/MOEF/EIA-EMP/2008 dated
30.01.2008 on the aforesaid subject and its consideration in the Expert
Appraisal Committee (Thermal & Coal Mining) held on 25-26th
March 2008. It was noted that the proposal is for establishing a new Hadla
Lignite Mine Project in district Bikaner involving a total land area of 2001.61
ha which is mostly private land (1999.08 ha) and Govt. land (2.53 ha). It is
located at a distance of the Barsingsar lignite mine and TPP at a distance of
about 15 km. The Hadla Lignite mine project is for the proposed expansion of
the Barsingsar TPP (2 x 125 MW) by another 250 MW for which a separate
application has been made. The life of the proposed lignite mine is 20-25
years. EC for Barsingsar was transferred from M/s Hindustan Vidyut Power Corp.
Ltd. along with the mining lease.
It was informed that there are no streams, lake,
reservoirs, dams, water curses, surface water body. There are no major
population within a radius of 15km. During monsoon (from July to Oct.) some
crops are cultivated. Groundwater is found at a depth of 140m. The main source
of water supply for the villages and for the Barsingsar Project is the Indira
Gandhi Nahar Pariyojana (IGNP) although in some areas borewells are in use. It
was informed that the State Government has allocated 46 cusecs of water for
industrial use for to M/s NLC of which about 0.5 cusec of water would be used
for the Hadla Project. It was informed that in the Barsingsar mine, groundwater
has not been encountered even at 70-100m depth of lignite seam. There are 3
villages located within the 2000 ha lease area. No R&R except land oustees
involving about 250 persons. OB dumps proposed is bout 70-90m high. Occasional
blasting is required due to presence of sandstone. Lignite removal is by
shovel-dumper.
The Committee was of the view that the total land requirement for the project appeared to be high and needed to be reworked for the surrender of the land of about 500ha including the non-mineralised area and areas with habitation to minimise land oustees and R&R. The Committee desired that a study on the detailed ecology on the endemic and endangered species found in the study area should be carried out. This should also include the economically important species including medicinal plants found in the area. The study could involve the BSI-ZSI and the Desert Medicinal Plant Board, Jodhpur and also CAZRI. The Committee desired that a detailed R&R survey should be carried out and a detailed R&R Plan be prepared. The plan should include provision of water from the IGNP for the resettled villagers. The Committee desired that no groundwater should be used for the lignite mine. The Committee also desired that a detailed survey of the use of ground water in the area and the impact of mining on the groundwater regime (including quantity and quality) be undertaken. Mitigative measures in case of discharge of saline water require to be addressed by establishing RO Plant and by treatment and disposal of the brine sludge. The Committee desired that since the linked TPP is about a distance of only 15km, the PP should examine transport of coal by conveyors and not by road. The site and height of the OB dump also requires to be relooked to ensure minimal impact on township and habitation.
Based on the application along with documents and
presentation thereon and discussions held, the Committee prescribed the
following TOR:
(i) An EIA-EMP
Report would be prepared for opencast lignite mine of 2.5 MTPA rated capacity based on the generic structure specified in
Appendix III of the EIA Notification 2006. The EIA-EMP Report would be prepared
for 2.5 MTPA rated capacity based on project specific activities
on the environment of the region, and the environmental quality – air, water,
land, biotic community, etc. through collection of data and information,
generation of data on impacts including prediction modelling for 2.5 MTPA of coal production based on approval of project/Mining
Plan for 2.5 MTPA. Baseline data collection can be for any season except
monsoon.
(ii) An EIA-EMP
Report should be prepared for a peak capacity of 2.5 MTPA addressing the impacts of the project
including the aspects of mineral transportation and issues of impacts on
hydrogeology, plan for conservation of flora/fauna and afforestation/
plantation programme. Baseline data
collection can be for any season except monsoon. The EIA-EMP report should
cover the environmental impacts and management plan for the individual project
specific activities and those activities which have an inter-connection
(transportation of mineral, power, water, colony, lignite stockyard, lignite
handling plant, transportation and usage of approach roads from mine ) on the
environmental quality – air, water, land, biotic community, etc. through
collection of baseline data and information generation on impacts through
prediction modelling.
(iii) A map specifying
locations of the State, District and Project location.
(iv) A Study area map of the
core zone and 10km area of the buffer clearly delineating the major
topographical features such as the land use, ecologically sensitive areas such
as Biosphere Reserves/National Parks/WL Sanctuaries/ Elephant Reserves, forests
(Reserved/Protected), migratory corridors of fauna, and areas where endangered
fauna and plants of medicinal and economic importance are found in the area,
surface drainage of rivers/streams/nalas/canals, locations of human
habitations, major constructions including railways, roads, pipelines, major
industries/mines and other polluting sources.
(v) Land use map (1: 50,000 or 100,000)
based on a recent satellite imagery of the study area may also be provided with
explanatory note of the land use.
(vi) Map showing the core zone delineating the
agricultural land (irrigated and irrigated, uncultivable land (as defined in
the revenue records), forest areas (as per records).
(vii) Details of original land use (agricultural
land/forestland/grazing land/wasteland/water bodies) of the area Impacts of
project, if any on the landuse, in particular, area (in ha) agricultural
land/forestland/grazing land/water bodies falling within the lease and acquired
for mining operations.
(viii) Contour map at 3 m
intervals and Site plan of the mine showing the various proposed break-up of
the land for mining operations such as the quarry area, OB dumps, green belt,
safety zone, buildings, infrastructure,
Lignite HP, ETP, Stockyard, township/colony (within and adjacent to the
ML), undisturbed area and if any, in topography such as existing roads,
drains/natural water bodies are to be left undisturbed along with any natural
drainage adjoining the lease and modification of thereof in terms of
construction of embankments/bunds, proposed diversion/rechannelling of the
water courses, etc., approach roads, major haul roads, etc.
(ix) The
Committee was of the view that the total land requirement for the project
appeared to be high and needed to be reworked for the surrender of the land of
about 500ha including the non-mineralised area and areas with habitation to
minimise land oustees and R&R. Break up of
lease area as per different land uses and their stage of acquisition.
(x) Break-up of lease area
as per mining operations.
(xi) Impact of changes in
the land use due to the start of the combined projects since much of the land
being acquired is agricultural land.
(xii) Collection of
one-season (non-monsoon) primary base-line data on environmental quality - air
(SPM, RSPM, SOx and NOx), noise, water (surface and groundwater), soil.
(xiii) Map of the study area
(core and buffer zone clearly delineating the location of various stations
superimposed with location of habitats, other industries/mines, pouting
sources. The number and location of the stations should be selected on the
basis of the proposed impacts in the downwind (air)/downstream (surface
water)/groundwater regime (based on flow). One station should be in the
upwind/upstream/non-impact/non-polluting area as a control station. The
monitoring should be as per CPCB guidelines and parameters for water testing
for ground water as per ISI standards and surface water as per CPCB guidelines.
(xiv) The
Committee desired that a study on the detailed ecology on the endemic and
endangered species found in the study area should be carried out. This should
also include the economically important species including medicinal plants
found in the area. The study could involve the BSI-ZSI and the Desert Medicinal
Plant Board, Jodhpur and also CAZRI. The
list of flora and fauna duly authenticated separately for the core and buffer
zone and a statement clearly specifying whether the study area forms a part of
the migratory corridor of any endangered fauna.
(xv) Details of mineral
reserves, geological status of the study are and the seams to be worked,
ultimate working depth and progressive stage-wise working scheme until end of
mine life should be reflected on the basis of the approved rated capacity and
calendar plans of production from the approved Mining Plan. Geological maps
should be included.
Details of mining methods, technology, equipment to be used, etc. rationale for selection of that technology
and equipment proposed to be used vis-à-vis
the potential impacts.
(xvii) Impact of mining on
hydrology, modification of natural drainage, diversion and channelling of the
existing rivers/water courses flowing though the ML and adjoining the lease and
the impact on the existing users and impacts of mining operations thereon.
(xviii) .
The Committee desired that no groundwater should be used for the lignite mine.
The Committee also desired that a detailed survey of the use of ground water in
the area and the impact of mining on the groundwater regime (including quantity
and quality) be undertaken. Detailed water balance
should be provided. The break up of water requirement for each the mine
operations should be given separately.
(xix) Source of water for use
in mine, sanction of the competent authority in the State Govt. and impacts
vis-à-vis the competing users.
(xx) Impact of mining and
water abstraction use in mine on the hydrogeology and groundwater regime of
within the core zone and 10km buffer zone including long–term modelling studies
on. Details of rainwater harvesting and measures for recharge of groundwater
should be reflected.
(xxi) Impact of blasting,
noise and vibrations.
(xxii) Impacts of mining on the
AAQ, predictive modelling including ISCT-3 (Revised) or latest model available.
Impacts of mineral transportation – within and outside the lease along
with flow-chart. Impacts of transportation, handling, transfer of mineral and
waste on air quality, generation of effluents from workshop, management plan
for maintenance of HEMM, machinery, equipment. Details of various facilities to
be provided in terms of parking, rest areas, canteen, and effluents/pollution
load from these activities. The Committee desired
that since the linked TPP is about a distance of only 15km, the PP should
examine transport of coal by conveyors and not by road.
(xxiv) The
site and height of the OB dump also requires to be relooked to ensure minimal
impact on township and habitation. Details of waste
generation – OB, topsoil – as per the approved calendar programme, and their
management shown in figures as well explanatory chapter with tables giving
progressive development and mine closure plan, green belt development,
backfilling programme and conceptual post mining land use. OB dump heights and
terracing should based on slope stability studies with a max of 28o
angle as the ultimate slope. Sections of dumps (ultimate) (both longitudinal
and cross section) with relation to the adjacent area should be shown.
(xxv) Flow chart of water
balance. Treatment of effluents from workshop, township, domestic wastewater,
mine water discharge, treatment details, etc. Details of STP in colony and ETP
in mine. Recycling of water to the max. possible extent.
(xxvi) Occupational health
issues. Baseline data on the health of the population and measures for
occupational health and safety of the personnel and manpower for the mine.
Impact and management of wastes and issues of rehandling and
backfilling and progressive mine closure and reclamation.
(xxviii)Disaster Management Plan.
(xxix) Integrating in the Env.
Management Plan with measures for minimising use of natural resources - water,
land, energy, etc.
(xxx) Progressive Green belt and afforestation plan (both in text,
figures as well as in tables).
and reasons for
selection of species for the afforestation/plantation programme.
(xxxi) Conservation Plan for the
endangered/endemic flora and fauna found in the study area and for safety of
animals visiting/residing in the study area and also those using the study area
as a migratory corridor.
(xxxii) Mine closure issues, post mining land use and restoration of
land to pre- mining (agricultural use).
(xxxiii) Including cost of EMP (capital and recurring) in the project
cost and for progressive
and final mine closure
plan.
(xxxiv) The Committee desired that a detailed
R&R survey should be carried out and a detailed R&R Plan be prepared with data on the existing socio-economic status of the population
affected by R&R in the project area and broad plan for resettlement of the
displaced population, site for the resettlement colony, alternate livelihood
concerns/employment for the displaced people, civic and housing amenities being
offered, etc and the schedule of the implementation of the R&R Plan.
(xxxv) Public Hearing should
cover the details of notices issued in the newspaper, proceedings/minutes of
public hearing, the points raised by the general public and commitments made in
a tabular form. If the Public Hearing is in the regional language, an
authenticated English Translation of the same should be provided.
(xxxvi) In built mechanism of self monitoring of compliance of
environmental regulations.
(xxxvii) Status of any
litigations/ court cases filed/pending on the project.
(xxxviii)Authenticated English translation of all material provided in
Regional languages.
The following general points should be noted:
(i) All documents should
be properly indexed, page numbered.
(ii) Period/date of data
collection should be clearly indicated.
(iii) Authenticated English
translation of all material in Regional languages provided/enclosed with the
application.
(iv) After the preparation of the draft EIA-EMP Report as per the aforesaid TOR, the proponent shall get the Public Hearing conducted as prescribed in the EIA Notification 2006 and take necessary action for obtaining environmental clearance under the provisions of the EIA Notification 2006.
(v) The letter/application
for EC should quote the MOEF file No. and also attach a copy of the letter
prescribing the TOR.
(vi) The copy of the letter
received from the Ministry on the TOR prescribed for the project should be
attached as an annexure to the final EIA-EMP Report.
(vii) The final EIA-EMP report submitted to the
Ministry must incorporate the issues in TOR and that raised in Public Hearing.
The index of the final EIA-EMP report, must indicate the specific chapter and
page no. of the EIA-EMP Report where the specific TOR prescribed by Ministry
and the issue raised in the P.H. have been incorporated.
Yours faithfully,
(Dr.T.Chandini)
Director
Copy
to: Chairman,
Rajasthan State Pollution Control Board, A-4, Jalane Dungri Institutional Area,
JAIPUR – 302004.