No. J-11015/ /2012-IA.II(M)

Government of India

Ministry of Environment & Forests

Paryavaran Bhawan,

CGO Complex,

New Delhi-110510.

To

Dated: 23rd March 2012 

Chief General Manager (E &F),

M/s Western Coalfields Ltd.,

Coal Estate, Civil Lines,

NAGPUR -440001.

 

Sub:     Shivani Opencast Coalmine Project (1.25 MTPA normative and 1.4375 MTPA peak          capacity in an ML area of 780 ha) of M/s WCL, located in dist. Yavatmal,       Maharashtra - Terms of Reference  (TOR) – reg.

 

Sir,

            This is with reference to letter no. 43011/2/2012-CPAM dated 05.01.2012 of Ministry of Coal regarding the aforesaid proposal which was considered in the meeting of the Expert Appraisal Committee (Thermal & Coal Mining Projects) held on 21st-22nd February 2012. It was informed that the proposal is for opening anew opencast coalmine of 1.25 MTPA in an ML area of 780 ha. The mine is located adjacent to River Wardha and an embankment of a length of 2km and 6m height is proposed. No forestland is involved. Life of the mine is 20 years. R&R of 269 households of Shivani village is involved. The total Ml area consists of 738.60 ah of agricultural land and 41.40 ha of wasteland. No forestland is involved. Of the total ML area, area for excavation is 214 ha, ext. Ob dump is 250.85 ha, embankment is 48 ha, infrastructure/roads is 30 ha, area required for rationalisation and blasting zone is 213.15 ha, colony is 15 ha and R&R site is 15 ha. Depth of the mine is 60m to 175m. Of the total OB generation, 26% (33.80 Mm3) would be dumped internally. An estimated 134.78 Mm3 of OB would be stored in an external OB dump of an area of 250ha and height of 90m. It was informed that it is proposed to leave a final void of 190 ha and 175m depth at the post mining stage.

 

The Committee desired that various options of reducing external dumping and for reducing final void should be examined in the EIA-EMP. The Committee after discussions recommended the project for TOR for opencast operations as given below:

(i)                  An EIA-EMP Report should be prepared for Shivani Opencast Coalmine Project for a peak capacity of 1.25 MTPA normative and 1.4375 MTPA peak capacity in an ML area of 780 ha addressing the impacts of the underground coalmine project including the aspects of mineral transportation and issues of impacts on hydrogeology, plan for conservation of flora/fauna and afforestation/plantation programme based on the generic structure specified in Appendix III of the EIA Notification 2006. Baseline data collection can be for any season except monsoon.

(ii)                The EIA-EMP report should also cover the impacts and management plan for the project specific activities on the environment of the region, and the environmental quality – air, water, land, biotic community, etc. through collection of baseline data and information, generation of baseline data on impacts for 1.25 MTPA normative and 1.4375 MTPA peak capacity of coal production based on approval of project/Mining Plan. Baseline data collection can be for any season except monsoon.

(iii)               A map specifying locations of the State, District and Project location.

(iv)              A Study area map of the core zone and 10km area of the buffer zone (1: 50,000 scale) clearly delineating the major topographical features such as the land use, surface drainage of rivers/streams/nalas/canals, locations of human habitations, major constructions including railways, roads, pipelines, major industries/mines and other polluting sources. In case of ecologically sensitive areas such as Biosphere Reserves/National Parks/WL Sanctuaries/ Elephant Reserves, forests (Reserved/Protected), migratory corridors of fauna, and areas where endangered fauna and plants of medicinal and economic importance found in the 15 km area of the buffer zone should be given.

(v)                Land use map (1: 50,000 scale) based on a recent satellite imagery of the study area may also be provided with explanatory note of the land use. Satellite imagery per se is not required.

(vi)              Map showing the core zone delineating the agricultural land (irrigated and unirrigated, uncultivable land (as defined in the revenue records), forest areas (as per records), along with other physical features such as water bodies, etc should be furnished.

(vii)             A contour map showing the area drainage of the core zone and 2-5 km of the buffer zone (where the water courses of the core zone ultimately join the major rivers/streams outside the lease/project area) should also be clearly indicated as a separate map.

(viii)           A detailed Site plan of the mine showing the various proposed break-up of the land for mining operations such as the quarry area, OB dumps, green belt, safety zone, buildings, infrastructure, CHP, ETP, Stockyard, township/colony (within and adjacent to the ML), undisturbed area and if any, in topography such as existing roads, drains/natural water bodies are to be left undisturbed along with any natural drainage adjoining the lease /project and modification of thereof in terms of construction of embankments/bunds, proposed diversion/rechannelling of the water courses, etc., approach roads, major haul roads, etc.

(ix)               Map showing the complete route of mineral transportation from mine face to end users indicating the extent of transport in km by road, conveyors, rail, etc.

(x)                In case of any proposed diversion of nallah/canal/river, the proposed route of diversion/modification of drainage and their realignment, construction of embankment etc. should also be shown on the map.

(xi)               Similarly if the project involves diversion of any road/railway line passing through the ML/project area, the proposed route of diversion and its realignment should be shown.

(xii)             Break up of lease/project area as per different land uses and their stage of acquisition.

 

            LANDUSE DETAILS FOR OPENCAST PROJECT

S.N.

LANDUSE

Within ML Area (ha)

Outside ML Area (ha)

TOTAL

1.

Agricultural land

 

 

 

2.

Forest land

 

 

 

3.

Wasteland

 

 

 

4.

Grazing land

 

 

 

5.

Surface water bodies

 

 

 

6.

Settlements

 

 

 

7.

Others (specify)

 

 

 

 

 

TOTAL

 

 

 

 

(xv)             Break-up of lease/project area as per mining operations.

(xvi)           Impact of changes in the land use due to the start of the projects if much of the land being acquired is agricultural land/forestland/grazing land.

(xvii)          Collection of one-season (non-monsoon) primary baseline data on environmental quality - air (PM10, PM2.5, SOx, NOx and heavy metals such as Hg, Pb, Cr, As, etc), noise, water (surface and groundwater), soil along with one-season met data coinciding with the same season for AAQ collection period.

(xviii)        Map of the study area (1: 50, 000 scale) (core and buffer zone clearly delineating the location of various stations superimposed with location of habitats, other industries/mines, polluting sources. The number and location of the stations in both core zone and buffer zone should be selected on the basis of size of lease/project area, the proposed impacts in the downwind (air)/downstream (surface water)/groundwater regime (based on flow). One station should be in the upwind/upstream/non-impact/non-polluting area as a control station. The monitoring should be as per CPCB guidelines and parameters for water testing for both ground water and surface water as per ISI standards and CPCB classification wherever applicable. Values should be provided based on desirable limits.

(xix)            Study on the existing flora and fauna in the study area (10km) carried out by an institution of relevant discipline and the list of flora and fauna duly authenticated separately for the core and buffer zone and a statement clearly specifying whether the study area forms a part of the migratory corridor of any endangered fauna. If the study area has endangered flora and fauna, or if the area is occasionally visited or used as a habitat by Schedule-I fauna, or if the project falls within 15 km of an ecologically sensitive area, or used as a migratory corridor then a comprehensive Conservation Plan should be prepared and submitted with EIA-EMP Report and comments from the CWLW of the State Govt. also obtained and furnished.

(xx)             Details of mineral reserves, geological status of the study are and the seams to be worked, ultimate working depth and progressive stage-wise working scheme until end of mine life should be reflected on the basis of the approved rated capacity and calendar plans of production from the approved Mining Plan. Geological maps and sections should be included. The progressive mine development and Conceptual Final Mine Closure Plan should also be shown in figures.

(xxi)            Details of mining methods, technology, equipment to be used, etc., rationale for selection of that technology and equipment proposed to be used vis-à-vis the potential impacts.

(xxii)          Impact of mining on hydrology, modification of natural drainage, diversion and channelling of the existing rivers/water courses flowing though the ML and adjoining the lease/project and the impact on the existing users and impacts of mining operations thereon.

(xxiii)         Detailed water balance should be provided. The break up of water requirement for the various mine operations should be given separately.

(xxiv)        Source of water for use in mine, sanction of the competent authority in the State Govt. and impacts vis-à-vis the competing users.

(xxv)          Impact of mining and water abstraction use in mine on the hydrogeology and groundwater regime within the core zone and 10 km buffer zone including long–term modelling studies on. Details of rainwater harvesting and measures for recharge of groundwater should be reflected in case there us a declining trend of groundwater availability and/or if the area falls within dark/grey zone.

(xxvi)        Impact of blasting, noise and vibrations.                       

(xxvii)       Impacts of mining on the AAQ, predictive modelling using the ISCST-3 (Revised) or latest model.

(xxviii)     Impacts of mineral transportation – within and outside the lease/project along with flow-chart indicating the specific areas generating fugitive emissions. Impacts of transportation, handling, transfer of mineral and waste on air quality, generation of effluents from workshop, management plan for maintenance of HEMM, machinery, equipment. Details of various facilities to be provided in terms of parking, rest areas, canteen, and effluents/pollution load from these activities.

(xxix)         Details of waste generation – OB, topsoil – as per the approved calendar programme, and their management shown in figures as well explanatory chapter with tables giving progressive development and mine closure plan, green belt development, backfilling programme and conceptual post mining land use. OB dump heights and terracing should based on slope stability studies with a max of 28o angle as the ultimate slope. Sections of dumps (ultimate) (both longitudinal and cross section) with relation to the adjacent area should be shown.

 

Project

Total waste generation (Mm3)

Topsoil

(Mm3)

Total OB generation (Mm3)

Total OB

in Ext. Dump

Total OB

Backfilled

(Mm3)

Original Project (ha)

 

 

 

 

 

Expansion Project (ha) (balance life)

 

 

 

 

 

 

TOTAL (Mm3)

 

 

 

 

 

 

(xxx)          Progressive Green belt and afforestation plan (both in text, figures as well as in tables prepared by MOEF) and selection of species (local) for the afforestation/plantation programme based on original survey/landuse.

 

            Table 1: Stage-wise Landuse and Reclamation Area (ha)

S.N.

Land use Category

Present

(1st Year)

5th Year

10th Year

20th year

24th Year (end of Mine life)*

1.

Backfilled Area (Reclaimed with plantation)

 

 

 

 

 

2.

Excavated Area (not reclaimed)/void

 

 

 

 

 

 

3.

External OB dump

Reclaimed with plantation)

 

 

 

 

 

4.

Reclaimed Top soil dump

 

 

 

 

 

5.

Green Built Area

 

 

 

 

 

 

6.

Undisturbed area (brought under plantation)

 

 

 

 

 

7.

Roads (avenue plantation)

 

 

 

 

 

8.

Area around buildings and Infrastructure

 

 

 

 

 

 

 

TOTAL

110*

110*

110*

110*

110*

            * As a representative example

 

 

            Table 2: Stage-wise Cumulative Plantation

S.N.

YEAR*

Green Belt

External Dump

Backfilled Area

Others

(Undisturbed

Area/etc)

TOTAL

 

 

Area

(ha)

No. of trees

Area

(ha)

No. of Trees

Area

(ha)

No. of Trees

Area

(ha)

No. of

 Trees

Area

(ha)

No. of

 Trees

1.

1st year

 

 

 

 

 

 

 

 

 

 

2.

3rd year

 

 

 

 

 

 

 

 

 

 

3.

5th year

 

 

 

 

 

 

 

 

 

 

4.

10th yesr

 

 

 

 

 

 

 

 

 

 

5.

15th year

 

 

 

 

 

 

 

 

 

 

6.

20th year

 

 

 

 

 

 

 

 

 

 

7.

25th year

 

 

 

 

 

 

 

 

 

 

8.

30th year

 

 

 

 

 

 

 

 

 

 

9.

34th year (end of mine life)

 

 

 

 

 

 

 

 

 

 

10.

34-37th Year (Post-mining)

 

 

 

 

 

 

 

 

85

 

            * As a representative example

 

 

(xxxi)         Conceptual Final Mine Closure Plan, post mining land use and restoration of land/habitat to pre- mining. A Plan for the ecological restoration of the area post mining and for land use should be prepared with detailed cost provisions. Impact and management of wastes and issues of rehandling (wherever applicable) and backfilling and progressive mine closure and reclamation.

 

            Table 3: Post-Mining Landuse Pattern of ML/Project Area (ha)

S.N.

Land use during Mining

Land Use (ha)

1.

External OB Dump

Plantation

Water Body

Public Use

Undisturbed

TOTAL

2.

Top soil Dump

 

 

 

 

 

3.

Excavation

 

 

 

 

 

4.

Roads

 

 

 

 

 

4.

Built up area

 

 

 

 

 

5.

Green Belt

 

 

 

 

 

6.

Undisturbed Area

 

 

 

 

 

 

TOTAL

85

 

 

 

110

 

(xxxii)       Flow chart of water balance. Treatment of effluents from workshop, township, domestic wastewater, mine water discharge, etc. Details of STP in colony and ETP in mine. Recycling of water to the max. possible extent.

(xxxiii)      Occupational health issues. Baseline data on the health of the population in the impact zone and measures for occupational health and safety of the personnel and manpower for the mine.

(xxxiv)     Risk Assessment and Disaster Preparedness and Management Plan.

(xxxv)       Integrating in the Env. Management Plan with measures for minimising use of natural resources - water, land, energy, etc.

(xxxvi)     Including cost of EMP (capital and recurring) in the project cost and for progressive and final mine closure plan.

(xxxvii)    Details of R&R.  Detailed project specific R&R Plan with data on the existing socio-economic status of the population (including tribals, SC/ST, BPL families) found in the study area and broad plan for resettlement of the displaced population, site for the resettlement colony, alternate livelihood concerns/employment for the displaced people, civic and housing amenities being offered, etc and costs along with the schedule of the implementation of the R&R Plan.

(xxxviii)  CSR Plan along with details of villages and specific budgetary provisions (capital and recurring) for specific activities over the life of the project.

(xxxix)      Public Hearing should cover the details of notices issued in the newspaper, proceedings/minutes of public hearing, the points raised by the general public and commitments made by the proponent should be presented in a tabular form. If the Public Hearing is in the regional language, an authenticated English Translation of the same should be provided.

(xl)               In built mechanism of self-monitoring of compliance of environmental regulations.

(xxxx)  Status of any litigations/ court cases filed/pending on the project.

(xxxxi) Submission of sample test analysis of:

Characteristics of coal - this includes grade of coal and other characteristics – ash, S and heavy metals including levels of Hg, As, Pb, Cr etc.

(xxxxii) Copy of clearances/approvals – such as Forestry clearances, Mining Plan Approval,

            NOC from Flood and Irrigation Dept. (if req.), etc. wherever applicable.

 

            (A) FORESTRY CLEARANCE

 

TOTAL ML/PROJECT 

AREA (ha)

TOTAL FORESTLAND (ha)

Date of FC

Extent of forestland

Balance area for which FC is yet to be obtained

Status of appl. for diversion of

forestland

 

 

If more than one, provide details of each FC

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

            (B)        MINING PLAN/PROJECT APPROVAL

                        Date of Approval of Mining Plan/Project Approval:

                        Copy of Letter of Approval of Mining Plan/Project Approval

(xxxviii) Corporate Environment Responsibility:

a)     The Company must have a well laid down Environment Policy approved by the Board of Directors.

b)     The Environment Policy must prescribe for standard operating process/procedures to bring into focus any infringements/deviation/violation of the environmental or forest norms/conditions.

c)     The hierarchical system or Administrative Order of the company to deal with environmental issues and for ensuring compliance with the environmental clearance conditions must be furnished.

d)  To have proper checks and balances, the company should have a well laid down system of reporting of non-compliances/violations of environmental norms to the Board of Directors of the company and/or shareholders or stakeholders at large.

 

The following general points should be noted:

 

(i)         All documents should be properly indexed, page numbered.

(ii)        Period/date of data collection should be clearly indicated.

(iii)       Authenticated English translation of all material provided in Regional languages.

(iv)       After the preparation of the draft EIA-EMP Report as per the aforesaid TOR, the proponent shall get the Public Hearing conducted as prescribed in the EIA Notification 2006 and take necessary action for obtaining environmental clearance under the provisions of the EIA Notification 2006.

(v)                The letter/application for EC should quote the MOEF file No. and also attach a copy of the letter prescribing the TOR.

(vi)              The copy of the letter received from the Ministry on the TOR prescribed for the project should be attached as an annexure to the final EIA-EMP Report.

(vii)      The final EIA-EMP report submitted to the Ministry must incorporate the issues in TOR and that raised in Public Hearing. The index of the final EIA-EMP report, must indicate the specific chapter and page no. of the EIA-EMP Report where the specific TOR prescribed by Ministry and the issue raised in the P.H. have been incorporated. Mining Questionnaire (posted on MOEF website) with all sections duly filled in shall also be submitted at the time of applying for EC.

(viii)      General Instructions for the preparation and presentation before the EAC of TOR/EC projects of Coal Sector should be incorporated/followed.

(viii)      The aforesaid TOR has a validity of two years only.

 

The following additional points are also to be noted:

(i)                  Grant of TOR does not necessarily mean grant of EC.

(ii)                Grant of TOR/EC to the present project does not necessarily mean grant of TOR/EC to the captive/linked project.

(iii)               Grant of TOR/EC to the present project does not necessarily mean grant of approvals in other regulations such as the Forest (Conservation) Act 1980 or the Wildlife (Protection) Act, 1972.

(iv)       Grant of EC is also subject to Circulars issued under the EIA Notification 2006, which are available on the MOEF website: www.envfor.nic.in

Yours faithfully,

 

 

 

(Dr.T.Chandini)

Director

 

 

Copy to: Member-Secretary, Maharashtra State Pollution Control Board, 3rd & 4th Floor, Sion Matunga

            Scheme Road. No.8, Opp. Cine Planet Cinema, Near Sion Circle, Sion (E), MUMBAI – 400002.

 

Untitled Page