No. J-11015/212/2010-IA.II(M)

Government of India

Ministry of Environment & Forests

Paryavaran Bhawan,

CGO Complex,

New Delhi-110510.

To

Dated: 4th November 2010

Shri A.K. Singh,

General Manager,

Katras Area,

M/s Bharat Coking Coal Ltd.,

PO- Sijua, Dist. Dhanbad,

Jharkhand – 828121.

 

Sub:     Cluster No. IV (5 mines of a peak prodn. of 3.706 MTPA in a combined ML area of

1123.79 ha) of M/s Bharat Coking Coal Ltd., located in Jharia coalfields, in dist. Dhanbad, Jharkhand - Terms of Reference  (TOR) – reg.

 

Sir,

            This is with reference to letter no. 43011/20/2010 dated 13.05.2010  regarding the aforesaid proposal which was considered in the EAC (T&C) meeting held on 27th -28th September 2010. It was noted that the cluster consists of 5 mines as given below.

                                               

S.N.

Name of the Mines

Production Capacity

Lease Area (ha)

Normative

Peak

1.

Salanpur Colliery UG

0.15

0.195

177.49

2.

Katras Choitudih Colliery UG

0.22

0.286

228.00

3.

a) Amalgamated Keshalpur & West Mududih UG

b) Amalgamated Keshalpur West Mududih

    0.19

 

     2.00

0.247

 

2.6

 

325.00

 

 

4.

Amalgamated Angarpathra &

Ramkanali Colliery UG

    0.291

      0.378

254.64

5.

Gastiland Colliery UG

    0.00

       0.00

138.66

TOTAL

2.851

3.706

1123.79

 

The details of integration of Jharia Action Plan has been summarised below:

 

Unstable Sites

51

No. of houses to be rehabilitated

7012

Cost

Rs 26274 lakhs

Affected Areas

1078829 m3

Areas affected by Fire

35827 m3

 

 

The details of Conceptual Post Mining Land use of Cluster IV were presented:

 

S.N.

Type of Land Use

Existing Land Use (ha)

Post Mining Land Use (in ha)

 

1.

Quarry

- Active

- Not backfilled

 

71.63

31.68

 

Nil

Nil

 

Abandoned Quarry

- Backfilled

- Not Backfilled

 

14.26

87.48

 

 

Nil

2.

Service Building/Mine Infrastructure

17.02

17.02

3.

Ext. OB Dump

14.82

Nil

4.

Coal Dump

4.36

Nil

5.

Homestead Land

132.71

132.71

6.

Road and Rail

106.52

106.52

7.

Agricultural land

21.22

21.22

8.

Plantation

74.67

794.09

9.

Water Body

 

48.31

10.

Barren Land

495.19

Nil

11.

Others

 

3.92

TOTAL

1123.79

1123.79

 

 

Based on the application along with documents and presentation thereon and discussions held, the Committee prescribed the following TOR:

 

(i)        An Integrated EIA-EMP for the cluster of mines shall be prepared clearly bringing out the present status of 5 mines in Cluster IV as above- status of env. quality and the extent of pollution load from each mine and the combined pollution load from the cluster of mines that would be reduced by taking suitable mitigative measures for the individual mines and for the cluster and the expected improvement in the environmental quality of the mines in the cluster and within the coalfield after the implementation of the measures through an Integrated Environmental Plan formulated on the aforesaid basis.  A fresh baseline data on the env. quality – air, water, land, biotic community, etc. shall be generated through collection of data and information, generation of data on impacts. Baseline data collection can be for any season except monsoon. Details of the present land use and post mining land use of the operating and abandoned mines individually and as a cluster shall be furnished as part of the EIA. A detailed Mine Closure Plan and a Mine Reclamation Plan for the abandoned mines (UG and OC)/pits/quarries found in the cluster shall be furnished as a part of EIA-EMP study. The closure of UG mines should ensure that no illegal mining is done thereafter from the mines. Details of long term benefits to environment because of cluster approach of mining shall be clearly addressed in the EIA-EMP study. In addition to the above, details of an Action Plan for project specific R&R and CSR shall also be formulated and presented in the EIA-EMP. The aforesaid Integrated Environmental Management Plan shall be dovetailed with the Jharia Action Plan and details of its implementation with specific time-lines should be provided.

(ii)       The Integrated EIA-EMP shall be based on the generic structure specified in Appendix III of the EIA Notification 2006 and incorporate an Environmental Action Plan for mitigating the environmental degradation existing in the cluster and for improvement of the environmental quality (air, water and land) so that the region (Dhanbad), which is presently critically polluted, and show by implementation of the Env. Action Plan the discernible improvement of its environmental quality.

(iii)       A map specifying locations of the State, District and Project location. A map showing the Jharia Coalfields and the locations of the mines in the cluster.

(iv)       A Study area map of the core zone and 10km area of the buffer zone (1: 50,000 scale) clearly delineating the major topographical features such as the land use, surface drainage of rivers/streams/nalas/canals, locations of mines in the cluster, locations of human habitations, major constructions including railways, roads, pipelines, major industries/mines and other polluting sources.

(v)        Land use map (1: 50,000 scale) based on a recent satellite imagery of the study area may also be provided with explanatory note of the land use. Satellite imagery per se is not required.

(vi)       Map showing the core zone delineating the agricultural land (irrigated and unirrigated, uncultivable land (as defined in the revenue records), forest areas (as per records), along with other physical features such as water bodies, etc should be furnished.

(vii)      A contour map showing the area drainage of the core zone and 2-5 km of the buffer zone (where the water courses of the core zone ultimately join the major rivers/streams outside the lease/project area) should also be clearly indicated as a separate map.

(viii)      A detailed Site plan of the cluster of mines showing the various proposed break-up of the land for mining operations such as the quarry area, OB dumps, green belt, safety zone, buildings, infrastructure, CHP, ETP, Stockyard, township/colony (within and adjacent to the ML), undisturbed area and if any, in topography such as existing roads, drains/natural water bodies are to be left undisturbed along with any natural drainage adjoining the lease /project and modification of thereof in terms of construction of embankments/bunds, proposed diversion/rechannelling of the water courses, etc., approach roads, major haul roads, etc.

In case of any proposed diversion of nallah/canal/river, the proposed route of diversion/modification of drainage and their realignment, construction of embankment etc. should also be shown on the map.

Similarly if the project involves diversion of any road/railway line passing through the ML/project area of the mines of the cluster, the proposed route of diversion and its realignment should be shown.

(ix)       Break up of lease/project area as per different land uses and their stage of acquisition of each mine in the cluster.

(x)        Break-up of lease/project area as per mining operations of each mine in the cluster.

(xi)       Impact of changes in the land use due to the start of the projects if much of the land being acquired is agricultural land/forestland/grazing land.

(xii)       Collection of one-season (non-monsoon) primary baseline data on environmental quality - air (PM10, PM2.5, SOx , NOx and heavy metals such as Hg, Pb, Cr, As, etc), noise, water (surface and groundwater), soil.

(xiii)      Map of the study area (1: 50, 000 scale) (core and buffer zone clearly delineating the location of various stations superimposed with location of habitats, other industries/mines, polluting sources. The number and location of the stations in both core zone and buffer zone should be selected on the basis of size of lease/project area, the proposed impacts in the downwind (air)/downstream (surface water)/groundwater regime (based on flow). One station should be in the upwind/upstream/non-impact/non-polluting area as a control station. The monitoring should be as per CPCB guidelines and parameters for water testing for both ground water and surface water as per ISI  standards and CPCB classification wherever applicable.

(xiv)      Details of mineral reserves, geological status of the study are and the seams to be worked, ultimate working depth and progressive stage-wise working scheme until end of mine life should be reflected on the basis of the approved rated capacity and calendar plans of production from the approved Mining Plan. Geological maps and sections should be included. The progressive mine development and final mine closure plan should also be shown in figures.

(xv)      Details of mining methods, technology, equipment to be used, etc., rationale for selection of that technology and equipment proposed to be used vis-à-vis the potential impacts.

(xvi)      Study on subsidence, measures for mitigation/prevention of subsidence, modelling subsidence prediction and its use during mine operation, safety issues.

(xvii)     Impact of mining on hydrology, modification of natural drainage, diversion and channelling of the existing rivers/water courses flowing though the ML and adjoining the lease/project and the impact on the existing users and impacts of mining operations thereon.

(xviii)    Detailed water balance should be provided. The break up of water requirement for the various mine operations should be given separately for the cluster and for each mine separately.

(xix)      Source of water for use in mine, sanction of the competent authority in the State Govt. and impacts vis-à-vis the competing users.

(xx)       Impact of mining and water abstraction use in mines on the hydrogeology and groundwater regime within the core zone and 10 km buffer zone including long–term modelling studies on. Details of rainwater harvesting and measures for recharge of groundwater should be reflected in case there us a declining trend of groundwater availability and/or if the area falls within dark/grey zone.

(xxi)      Impact of blasting, noise and vibrations.                   

(xxii)     Impacts of mineral transportation in an integrated manner using road-cum rail or rail network– within and outside the lease/project along with flow-chart indicating the specific areas generating fugitive emissions. Impacts of transportation, handling, transfer of mineral and waste on air quality, generation of effluents from workshop, management plan for maintenance of HEMM, machinery, equipment. Details of various facilities to be provided in terms of parking, rest areas, canteen, and effluents/pollution load from these activities.

(xxiii)    Details of waste generation – OB, topsoil – as per the approved calendar programme, and their management shown in figures as well explanatory chapter with tables giving progressive development and mine closure plan, green belt development, backfilling programme and conceptual post mining land use. OB dump heights and terracing should based on slope stability studies with a max of 28o angle as the ultimate slope. Sections of dumps (ultimate) (both longitudinal and cross section) with relation to the adjacent area should be shown.

(xxiv)    Impact and management of wastes and issues of rehandling and backfilling and progressive mine closure and reclamation for each mine in the cluster.

(xxv)     Flow chart of water balance. Treatment of effluents from workshop, township, domestic wastewater, mine water discharge, etc. Details of STP in colony and ETP in mine. Recycling of water to the max. possible extent.

(xxvi)    Occupational health issues. Baseline data on the health of the population in the impact zone and measures for occupational health and safety of the personnel and manpower for the mine.

(xxvii) Details of fire affected sites and areas affected by subsidence and unstable sites as given in Jharia Action Plan for Cluster III Group of Mines and their management for each along with time schedule for mitigation under the Jharia Action Plan.

(xxviii)   Integrating in the Env. Management Plan with measures for minimising use of natural resources - water, land, energy, etc.

(xxix)    Progressive Green belt and afforestation plan (both in text, figures as well as in tables prepared by MOEF) for each mine along with selection of species (local) for the afforestation/plantation programme based on original survey/landuse.

(xxx)     Conceptual Final Mine Closure Plan for existing and abandoned mines with specific time lines and costs, post mining land use and restoration of land/habitat to pre-mining for each mine in the cluster. A Plan for the ecological restoration of the area post mining and for land use should be prepared with detailed cost provisions. The Committee desired that the abandoned quarries/mined out pits/voids left over form the pre-nationalisation period should be properly backfilled and biologically reclaimed in to either plantation or restored to agricultural land. The Committee desired that details of land use end of mine life and post mining be furnished in the standard tables prepared by MOEF. In case, exploration does not indicate sizeable reserves, the proponent may consider surrendering the lease after completion of reclamation of the abandoned mines and worked out OC and UG mines.

(xxxi) Including cost of EMP (capital and recurring) in the project cost and for progressive and final mine closure plan.

(xxxii)    Details of R&R in Jharia Action Plan for the cluster and its integration with the EMP. Cluster specific details of R&R Plan with data on the existing socio-economic status of the population (including tribals, SC/ST, BPL families) found in the study area and broad plan for resettlement of the displaced population, site for the resettlement colony, alternate livelihood concerns/employment for the displaced people, civic and housing amenities being offered, etc and costs along with the schedule of the implementation of the R&R Plan.

The Committee also sought a detailed CSR Plan for the entire cluster and Rs 5 per tonne of coal to be earmarked for activities under CSR.

(xxxiii) Public Hearing for the entire cluster should cover the details of notices issued in the newspaper, proceedings/minutes of public hearing, the points raised by the general public and commitments made by the proponent should be presented in a tabular form. If the Public Hearing is in the regional language, an authenticated English Translation of the same should be provided.

(xxxiv) In built mechanism of self-monitoring of compliance of environmental regulations.

(xxxv) Status of any litigations/ court cases filed/pending on the project.

(xxxvi) Submission of sample test analysis of:

Characteristics of coal - this includes grade of coal and other characteristics – ash, S and heavy metals including levels of Hg, As, Pb, Cr etc.

(xxxvi)   Copy of clearances/approvals – such as Forestry clearances, Mining Plan Approval, NOC from Flood and Irrigation Dept. (if req.), etc.

 

The following general points should be noted:

(i)         All documents should be properly indexed, page numbered.

(ii)        Period/date of data collection should be clearly indicated.

(iii)       Authenticated English translation of all material provided in Regional languages.

(iv)       After the preparation of the draft Integrated EIA-EMP Report as per the aforesaid TOR, the proponent shall get the Public Hearing conducted as prescribed in the EIA Notification 2006 and take necessary action for obtaining environmental clearance under the provisions of the EIA Notification 2006.

(v)                The letter/application for EC should quote the MOEF file No. and also attach a copy of the letter prescribing the TOR.

(vi)              The copy of the letter received from the Ministry on the TOR prescribed for the project should be attached as an annexure to the final EIA-EMP Report.

(vii)      The final EIA-EMP report submitted to the Ministry must incorporate the issues in TOR and that raised in Public Hearing. The index of the final EIA-EMP report, must indicate the specific chapter and page no. of the EIA-EMP Report where the specific TOR prescribed by Ministry and the issue raised in the P.H. have been incorporated. Mining Questionnaire (posted on MOEF website) with all sections duly filled in shall also be submitted at the time of applying for EC.

(viii)      MOEF Circular dated 22.03.2010 may kindly be referred to regarding time limit for validity of Terms of Reference (TOR) prescribed under EIA Notification, 2006 for undertaking detailed EIA studies for development projects requiring environmental clearance.

 

                                                                Yours faithfully,

 

 

 

 

(Dr.T.Chandini)

Director

 

 

Copy to: Member-Secretary, Jharkhand State Pollution Control Board, TA Building, HEC Complex, P.O.    Dhurva, Ranchi - 834002.

 

Untitled Page