No. J-11015/185/2010-IA.II(M)

Government of India

Ministry of Environment & Forests

Paryavaran Bhawan,

CGO Complex,

New Delhi-110510.

To

Dated: 28th May 2010

Chief General Manager (Env.),

M/s Bharat Coking Coal Ltd.,

Koyla Bhawan, Dhanbad.

 

Sub:     Cluster XVI coalmines (Dahibari-Basantimata OCP, Basantimata under Ground Mine, New Laikdih OCP (includes Dahibori washery), Laikdih Deep UG ,Chanch UG) of M/s Bharat Coking Coal Ltd., in Raniganj Coalfields, dist. Asansol, West Bengal (TOR) –reg.

 

Sir,

 

            This refers to consideration of the aforesaid proposal in the EAC (T&C) meeting held on 28th -29th April 2010. It was informed that the application is being made for EC for a cluster of coalmines for their renewal of lease. It was informed that the cluster is located in the Raniganj coalfields at a distance of 50km from Dhanbad and 30km from Asansol. The cluster consists of 5 mines – 2 operating mines, (1 OCP and 1 UGP) and 3 abandoned mines (1 OCP and 2 UGP).

 

S.N.

Name of Mine

Status of the mine

Prod. Capacity

(MTPA)

Peak Prod. Cap.

(MTPA)

ML Area

(ha)

1.

Dahibari Basantimala OCP

Operating

1.30

1.69

385.68

2.

Basantimal UG

Operating

0.21

0.273

417

3.

New Laikdih OCP

(includes Proposed Dahibari Washery)

Abandoned

Nil

Nil

305.10

4.

Laikdih Deep UG

Abandoned

Nil

Nil

281

5.

Chanch UG

Abandoned

Nil

Nil

575.43

TOTAL

 

1.51

1.963

1964.21

6.

Dahibari Washery

 

1.60

12 ha within Laikdih lease

 

 

It was informed that the existing abandoned mines (including earlier worked out pits/quarries) would be closed and reclaimed in an environmentally scientific manner. Plantation would be developed in the area. It was informed that the area is being explored for coal reserves found in great depths for future UG mining which may take about 8-10 years. In addition, a new Dahibari Coal Washery of a capacity of 1.6 MTPA raw coal is proposed in the abadnoned Laikdih OCP to cater to the requirements of washing coking grade coal of Basantimala OCP. The distance between the mine and the proposed washery is about 6 km. The site for the washery has been chosen on the basis of the proximity of the Dahibari railway track and siding exiting and a water body/pond of an excavated void existing which can meet the water requirements of the washery. An estimated one million tonnes of coal rejects would be generated and 0.6 MTPA of clean coal would be transported by rail. It was informed that in addition to the above, certain fire affected areas would be taken up for fire control and reclamation under the Raniganj Action Plan.

 

The Committee sought details of long term benefits to environment because of cluster approach of mining to be clearly addressed in the EIA-EMP study. The Committee desired that details of the present land use and post mining land use of the operating and abandoned mines individually and as a cluster be furnished as part of the EIA. The Committee desired that the EIA-EMP should clearly bring out the present status of env. quality, the extent of pollution load that would be reduced by taking suitable mitigative measures and the expected improvements in the cluster and tin the coalfield after the implementation of the measures. The Committee desired that an Integrated Environmental Plan should be formulated on the aforesaid basis and also desired that fresh baseline data on the env. quality should be generated on the new NAAQM Notification. In addition to the above, details of an Action Plan for project specific R&R and CSR should also be formulated and presented in the EIA-EMP. The Committee further desired that an FBC based TPP be also established near the washery so that the coal rejects could be entirely used in the TPP, which the proponent agreed to. The ash could be used in briquette making (flyash based bricks) and used in-house by the company and also sold to other users. This would help enhance the existing env. quality by use and disposal of the solid waste in an environmentally friendly manner.

 

Based on the application along with documents and presentation thereon and discussions held, the Committee prescribed the following TOR:

 

(i)         The environmental status and impacts of each mine in the cluster should be provided and a combined env. management plan with specific details for each mine as well as for the cluster as a whole should be formulated. An Integrated EIA-EMP for the cluster of mines should be prepared clearly bringing out the present status of env. quality, the extent of pollution load that would be reduced by taking suitable mitigative measures for the cluster and the expected improvement of the environmental quality of the mines in the cluster and within the coalfield after the implementation of the measures through an Integrated Environmental Plan formulated on the aforesaid basis.  A fresh baseline data on the env. quality should be generated on the new NAAQM Notification. Baseline data collection can be for any season except monsoon. Details of the present land use and post mining land use of the operating and abandoned mines individually and as a cluster be furnished as part of the EIA. A detailed Mine Closure Plan and a Mine Reclamation Plan for the abandoned mines (OC and UG)/pits/quarries found in the cluster should be furnished as apart of EIA-EMP study. The closure of UG mines should ensure that no illegal mining is done thereafter from the mines. Details of long term benefits to environment because of cluster approach of mining to be clearly addressed in the EIA-EMP study. In addition to the above, details of an Action Plan for project specific R&R and CSR should also be formulated and presented in the EIA-EMP.

(ii)        An Integrated EIA-EMP Report would be prepared for 1.963 MTPA rated capacity in an cluster of a total combine area of 1964.21 ha consisting of individual ML/project area indicated in table based on the generic structure specified in Appendix III of the EIA Notification 2006.

(iii)       A map specifying locations of the State, District and Project location.

(iv)       A Study area map of the core zone and 10km area of the buffer zone (1: 50,000 scale) clearly delineating the major topographical features such as the land use, surface drainage of rivers/streams/nalas/canals, locations of human habitations, major constructions including railways, roads, pipelines, major industries/mines and other polluting sources. In case of ecologically sensitive areas such as Biosphere Reserves/National Parks/WL Sanctuaries/ Elephant Reserves, forests (Reserved/Protected), migratory corridors of fauna, and areas where endangered fauna and plants of medicinal and economic importance found in the 15 km area of the buffer zone should be given.

(v)        Land use map (1: 50,000 scale) based on a recent satellite imagery of the study area may also be provided with explanatory note of the land use. Satellite imagery per se is not required.

(vi)       Map showing the core zone of each mine delineating the agricultural land (irrigated and unirrigated, uncultivable land (as defined in the revenue records), forest areas (as per records), along with other physical features such as water bodies, etc should be furnished.

(vii)      A contour map showing the area drainage of the core zone and 2-5 km of the buffer zone (where the water courses of the core zone ultimately join the major rivers/streams outside the lease/project area) should also be clearly indicated as a separate map.

(viii)     A detailed Site plan of the cluster of mines showing the various proposed break-up of the land for mining operations such as the quarry area, OB dumps, green belt, safety zone, buildings, infrastructure, CHP, ETP, Stockyard, township/colony (within and adjacent to the ML), undisturbed area and if any, in topography such as existing roads, drains/natural water bodies are to be left undisturbed along with any natural drainage adjoining the lease /project and modification of thereof in terms of construction of embankments/bunds, proposed diversion/rechannelling of the water courses, etc., approach roads, major haul roads, etc.

In case of any proposed diversion of nallah/canal/river, the proposed route of diversion/modification of drainage and their realignment, construction of embankment etc. should also be shown on the map.

Similarly if the project involves diversion of any road/railway line passing through the ML/project area, the proposed route of diversion and its realignment should be shown.

(iv)               Break up area of cluster and for individual lease/project area as per different land uses and their stage of acquisition.

(x)        Break-up of area of cluster and for individual lease/project area as per mining operations.

(xi)       Impact of changes in the land use due to the start of the projects if much of the land being acquired is agricultural land/forestland/grazing land.

(xii)      Collection of one-season (non-monsoon) primary baseline data on environmental quality - air (PM10, PM2.5, SOx , NOx and heavy metals such as Hg, Pb, Cr, As, etc), noise, water (surface and groundwater), soil.

(xiii)     Map of the study area (1: 50, 000 scale) (cluster with the individual mines clearly delineating the location of various stations superimposed with location of habitats, other industries/mines, polluting sources. The number and location of the stations in both core zone and buffer zone should be selected on the basis of size of lease/project area, the proposed impacts in the downwind (air)/downstream (surface water)/groundwater regime (based on flow). One station should be in the upwind/upstream/non-impact/non-polluting area as a control station. The monitoring should be as per CPCB guidelines and parameters for water testing for both ground water and surface water as per ISI standards and CPCB classification wherever applicable.

(xiv)      Study on the existing flora and fauna in the study area (10km) carried out by an institution of relevant discipline and the list of flora and fauna duly authenticated separately for the core and buffer zone and a statement clearly specifying whether the study area forms a part of the migratory corridor of any endangered fauna. If the study area has endangered flora and fauna, or if the project falls within 15 km of an ecologically sensitive area, then a comprehensive Conservation Plan should be prepared and furnished along with comments from the CWLW of the State Govt.

(xv)       Details of mineral reserves, geological status of the study are and the seams to be worked, ultimate working depth and progressive stage-wise working scheme until end of mine life should be reflected on the basis of the approved rated capacity and calendar plans of production from the approved Mining Plan. Geological maps and sections should be included. The progressive mine development and final mine closure plan should also be shown in figures.

(xvi)      Details of mining methods, technology, equipment to be used, etc., rationale for selection of that technology and equipment proposed to be used vis-à-vis the potential impacts.

(xvi)           Study on subsidence, measures for mitigation/prevention of subsidence, modelling subsidence prediction and its use during mine operation, safety issues.

(xviii)    Impact of mining on hydrology, modification of natural drainage, diversion and channelling of the existing rivers/water courses flowing though the ML and adjoining the lease/project and the impact on the existing users and impacts of mining operations thereon.

(xix)      Detailed water balance should be provided. The break up of water requirement for the various mine operations should be given separately.

(xx)       Source of water for use in mine, sanction of the competent authority in the State Govt. and impacts vis-à-vis the competing users.

(xxi)      Impact of mining and water abstraction use in mine on the hydrogeology and groundwater regime within the core zone and 10 km buffer zone including long–term modelling studies on. Details of rainwater harvesting and measures for recharge of groundwater should be reflected in case there us a declining trend of groundwater availability and/or if the area falls within dark/grey zone.

(xxii)     Impact of blasting, noise and vibrations.                  

(xxiii)    Impacts of mining on the AAQ, predictive modelling using the ISCST-3 (Revised) or latest model.

(xxiv)    Impacts of mineral transportation – within and outside the lease/project along with flow-chart indicating the specific areas generating fugitive emissions. Impacts of transportation, handling, transfer of mineral and waste on air quality, generation of effluents from workshop, management plan for maintenance of HEMM, machinery, equipment. Details of various facilities to be provided in terms of parking, rest areas, canteen, and effluents/pollution load from these activities.

(xxv)     Details of waste generation – OB, topsoil – as per the approved calendar programme, and their management shown in figures as well explanatory chapter with tables giving progressive development and mine closure plan, green belt development, backfilling programme and conceptual post mining land use. OB dump heights and terracing should based on slope stability studies with a max of 28o angle as the ultimate slope. Sections of dumps (ultimate) (both longitudinal and cross section) with relation to the adjacent area should be shown.

(xxvi)    Impact and management of wastes and issues of rehandling and backfilling and progressive mine closure and reclamation.

(xxvii)   Flow chart of water balance. Treatment of effluents from workshop, township, domestic wastewater, mine water discharge, etc. Details of STP in colony and ETP in mine. Recycling of water to the max. possible extent.

(xxviii)  Occupational health issues. Baseline data on the health of the population in the impact zone and measures for occupational health and safety of the personnel and manpower for the mine.

(xxix)    Disaster Management Plan.

(xxx)     Integrating in the Env. Management Plan with measures for minimising use of natural resources - water, land, energy, etc.

(xxxi)    Progressive Green belt and afforestation plan (both in text, figures as well as in tables prepared by MOEF).  And selection of species (local) for the afforestation/plantation programme based on original survey/landuse.

(xxxii)   Final Mine closure issues, post mining land use and restoration of land/habitat to pre- mining. A Plan for the ecological restoration of the area post mining and for land use should be prepared with detailed cost provisions.

(xxxiii) Including cost of EMP (capital and recurring) in the project cost and for progressive and final mine closure plan.

(xxxiv) Details of R&R.  Detailed project specific R&R Plan with data on the existing socio-economic status of the population (including tribals, SC/ST, BPL families)  found in the study area and broad plan for resettlement of the displaced population, site for the resettlement colony, alternate livelihood concerns/employment for the displaced people, civic and housing amenities being offered, etc and costs along with the schedule of the implementation of the R&R Plan.

(xxxv) Public Hearing should cover the details of notices issued in the newspaper, proceedings/minutes of public hearing, the points raised by the general public and commitments made by the proponent should be presented in a tabular form. If the Public Hearing is in the regional language, an authenticated English Translation of the same should be provided.

(xxxvi) In built mechanism of self-monitoring of compliance of environmental regulations.

(xxxvi)                  Status of any litigations/ court cases filed/pending on the project.

(xxxviii) Submission of sample test analysis of:

Characteristics of coal - this includes grade of coal and other characteristics – ash, S and heavy metals including levels of Hg, As, Pb, Cr etc.

(xxxviii)Copy of clearances/approvals – such as Forestry clearances, Mining Plan Approval, NOC form Flood and Irrigation Dept. (if req.), etc. In case clearances have not been obtained, copy of application made as annexure tot eh Mining Questionnaire.

 

TOR FOR COAL WASHERY

Based on the presentation made and discussions held, the Committee prescribed the following TOR for the Coal Washery, which will be integrated as part of the EIA-EMP Report for the cluster of mines:

(i)         A brief description of the plant, the technology used, the source of coal, the mode of transport of incoming unwashed coal and the outgoing washed coal. Specific pollution control and mitigative measures for the entire process.

(ii)        The EIA-EMP report should cover the impacts and management plan for the project of the capacity for EC is sought and the impacts of specific activities on the environment of the region, and the environmental quality – air, water, land, biotic community, etc. through collection of data and information, generation of data on impacts for the rated capacity. If the washery is captive to a coal mine/TPP/Plant the cumulative impacts on the environment and usage of water should be brought out along with the EMP.

(iii)       A Study area map of the core zone and 10km area of the buffer showing major industries/mines and other polluting sources, which shall also indicate the migratory corridors of fauna, if any and the areas where endangered fauna and plants of medicinal and economic importance are found in the area. If there are any ecologically sensitive areas found within the 15km buffer zone, the shortest distance form the National Park/WL Sanctuary Tiger Reserve, etc should be shown and the comments of the Chief Wildlife Warden of the State Government should be furnished.

(iv)       Collection of one-season (non-monsoon) primary base-line data on environmental quality – air (PM10, PM2.5, SOx and NOx), noise, water (surface and groundwater), soil.

(v)        Detailed water balance should be provided. The break up of water requirement as per different activities in the mining operations vis-à-vis washery should be given separately. Source of water for use in mine, sanction of the competent authority in the State Govt.. and examine if the unit can be zero discharge including recycling and reuse of the wastewater for other uses such as green belt, etc.

(vi)       Impact of choice of the selected use of technology and impact on air quality and waste generation (emissions and effluents). 

(vii)      Impacts of mineral transportation - the entire sequence of mineral production, transportation, handling, transfer and storage of mineral and waste, if any, and their impacts on air quality should be shown in a flow chart with the specific points where fugitive emissions can arise and the specific pollution control/mitigative measures proposed to be put in place.

(viii)     Details of various facilities to be provided for the personnel involved in mineral transportation in terms of parking, rest areas, canteen, and effluents/pollution load from these activities.  Examine whether existing roads are adequate to take care of the additional load of mineral [and rejects] transportation, their impacts. Details of workshop, if any, and treatment of workshop effluents.

(ix)       Impacts of CHP, if any on air and water quality. A flow chart of water use and whether the unit can be made a zero-discharge unit.

(x)        Details of green belt development.

(xi)       Including cost of EMP (capital and recurring) in the project cost.

(xiv)      Public Hearing details of the coal washery to include details of notices issued in the newspaper, proceedings/minutes of public hearing, the points raised by the general public and commitments made in a tabular form. If the Public Hearing is in the regional language, an authenticated English Translation of the same should be provided.

(xv)       Status of any litigations/ court cases filed/pending on the project.

(xvi)      Submission of sample test analysis of:

a.   Characteristics of coal to be washed- this includes grade of coal and other

                  characteristics – ash, S and and heavy metals including levels of Hg, As, Pb, Cr etc.

b.   Characteristics and quantum of washed coal.

c.   Characteristics and quantum of coal waste rejects.

(xvii)     Management/disposal/Use of coal waste rejects.

(xviii)    The Committee desired that an FBC based TPP be also established near the washery so that the coal rejects could be entirely used in the TPP, which the proponent agreed to. The ash could be used in briquette making (flyash based bricks) and used in-house by the company and also sold to other users. This would help enhance the existing env. quality by use and disposal of the solid waste in an environmentally friendly manner. The broad details of this would be presented in the EIA-EMP Report. An application for the FBC Plant would require to be made a separate application, however the broad details should be furnished as part of the Integrated EIA-EMP Report for the cluster of mines-cum-coal washery.

(xix)      Submission of sample test analysis of:

Characteristics of coal to be washed- this includes grade of coal and other characteristics – ash, S.

 

The following general points should be noted:

(i)         All documents should be properly indexed, page numbered.

(ii)        Period/date of data collection should be clearly indicated.

(iii)       Authenticated English translation of all material provided in Regional languages.

(iv)       After the preparation of the draft Integrated EIA-EMP Report for the cluster of mines as per the aforesaid TOR, the proponent shall get the Public Hearing conducted as prescribed in the EIA Notification 2006 and take necessary action for obtaining environmental clearance under the provisions of the EIA Notification 2006.

(v)        The letter/application for EC should quote the MOEF file No. and also attach a copy of the letter prescribing the TOR.

(vi)       The copy of the letter received from the Ministry on the TOR prescribed for the project should be attached as an annexure to the final EIA-EMP Report.

(vii)      The final Integrated EIA-EMP report for the cluster of mines submitted to the Ministry must incorporate the issues in TOR and that raised in Public Hearing. The index of the final EIA-EMP report, must indicate the specific chapter and page no. of the EIA-EMP Report where the specific TOR prescribed by Ministry and the issue raised in the P.H. have been incorporated. Mining Questionnaire (posted on MOEF website) with all sections duly filled in shall also be submitted at the time of applying for EC.

(viii)     MOEF Circular dated 22.03.2010 may kindly be referred to regarding time limit for validity of Terms of Reference (TORs) prescribed under EIA Notification, 2006 for undertaking detailed EIA studies for development projects requiring environmental clearance.

 

 

Yours faithfully,

 

 

(Dr.T.Chandini)

Director

 

Copy to: Member-Secretary, West Bengal State Pollution Control Board, Paribesh Bhawan,

              10A- Block LA, Sector –III, Salt Lake City, KOLKATTA – 700 098.

 

Untitled Page