No. J-11015/29/2012-IA.II(M)

Government of India

Ministry of Environment & Forests

Paryavaran Bhawan,

CGO Complex,

New Delhi-110510.

To

Dated: 23rd March 2012

Shri Chanakya Choudhary,

Chief Resident Executive,

M/s Tata Steel Ltd.,

Jeevan Bharati Building Tower 1,

10th Floor, 124, Connaught Circus,

New Delhi – 110 001.

 

Sub:     Bhelatand Amalgamated Colliery (expansion from 0.38 MTPA to 0.41 MTPA in an ML area of 521.68 ha) & Expn. of Bhelatand Washery (0.96 MTPA to 1.5 MTPA in 8 ha) of M/s Tata Steel Ltd., Dhanbad, Jharkhand - Terms of Reference  (TOR) – reg.

Sir,

 

              This is with reference to letter no. TSLDEL/541/2011 dated 16.01.2012 regarding the aforesaid proposal which was considered in the meeting of the Expert Appraisal Committee (Thermal & Coal Mining Projects) held on 21st -22nd February 2012. It was informed that the proposal is for expansion of the existing Bhelatand Amalgamated Colliery from 0.38 MTPA to 0.41 MTPA and expansion of existing Bhelatand Coking Coal Washery from 0.96 MTPA to 1.5 MTPA for use in linked Steel Plant which is expanding from 6.8 MTPA to 10 MTPA. It was informed that the project falls under Sijua Group of Collieries and does not fall in CPA, Dhanbad. It was also informed that no fires have been reported in the mine as nitrogen gas is used under DGMS supervision to form a protective layer all around mine working to prevent fires raging presently at a distance of about 5km in the BCCL mines in Jharia coalfields. It was informed that a number of villages, colony, infrastructure and buildings, railways and roads exist in the land within the core zone. It was informed that depillaring would be undertaken with stowing and no depillaring would be undertaken wherever mining involves caving.

 

It was stated that the existing washery is located in an area of 8ha within the premises of Bhelatand Colliery. Current level of the washery capacity is 0.9 MTPA. The expansion in washery would be by introduction of wet process and the unit would operate on zero-discharge. The washery effluents would be completely recycled with no discharge into Jarian Nala and Kajri Nala flowing along the mine boundary which outfall into River Damodar. The ash content in raw coal is about 30-32%, and middling (20% in quantity) with ash content in the range of 44-48%, which goes to TPS as per MOU with Min. of Coal and the balance coal rejects would be utilised in the captive 10MW FBC based TPP. It was informed that the entire coal transportation is by underground conveyors to the washery and thereafter by rail to the linked Steel Plant of the company at Jamshedpur. It was stated that water from the Bhelatand Colliery would be collected in reservoirs and used for mine and washery operations and for sand stowing. Treated mine water is being used of colony.

 

The Committee desired that the mitigative measures outlined in Jharia Action Plan particularly for coalmines and coal washeries should be integrated into the EIA-EMP of the project. The Committee recommended TOR as given below:

(i)                  An Integrated EIA-EMP Report should be prepared for expansion from 0.38 MTPA to 0.41 MTPA in an ML area of 521.68 ha) & expansion of Bhelatand Washery (0.96 MTPA to 1.5 MTPA in 8 ha) addressing the impacts of the underground coalmine project including the aspects of mineral transportation and issues of impacts on hydrogeology, plan for conservation of flora/fauna and afforestation/plantation programme based on the generic structure specified in Appendix III of the EIA Notification 2006.. Baseline data collection can be for any season except monsoon. The mitigative measures outlined in Jharia Action Plan particularly for coalmines and coal washeries should be integrated into the EIA-EMP of the project.

(ii)                The EIA-EMP report should also cover the impacts and management plan for the project specific activities on the environment of the region, and the environmental quality – air, water, land, biotic community, etc. through collection of baseline data and information, generation of baseline data on impacts for 0.41. MTPA of coal production based on approval of project/Mining Plan.

(iii)               A Study area map of the core zone and 10km area of the buffer zone (15 km of the buffer zone in case of ecologically sensitive areas) delineating the major topographical features such as the land use, drainage, locations of habitats, major construction including railways, roads, pipelines, major industries/mines and other polluting sources, which shall also indicate the migratory corridors of fauna, if any and the areas where endangered fauna and plants of medicinal and economic importance are found in the area.

(iv)              Map showing the core zone along with 3-5 km of the buffer zone) delineating the agricultural land (irrigated and unirrigated, uncultivable land (as defined in the revenue records), forest areas (as per records) and grazing land and wasteland and water bodies.

(v)                Contour map at 3m interval along with Site plan of the mine (lease/project area with about 3-5 km of the buffer zone) showing the various surface structures such as buildings, infrastructure, CHP, ETP, Stockyard, township/colony (within/adjacent to the ML), green belt and undisturbed area and if any existing roads, drains/natural water bodies are to be left undisturbed along with details of natural drainage adjoining the lease/project and modification of thereof in terms of construction of embankments/bunds, proposed diversion/rechannelling of the water courses, etc., highways, passing through the lease/project area.

(vi)              Original land use (agricultural land/forestland/grazing land/wasteland/water bodies) of the area. Impacts of project, if any on the landuse, in particular, agricultural land/forestland/grazing land/water bodies falling within the lease/project and acquired for mining operations. Extent of area under surface rights and under mining rights.

 

S.N.

 ML/Project

Land use

Area under Surface Rights (ha)

Area Under Mining Rights (ha)

Area under Both (ha)

1.

Agricultural land

 

 

 

2.

Forest Land

 

 

 

3.

Grazing Land

 

 

 

4.

Settlements

 

 

 

5.

Others (specify)

 

 

 

 

            Area Under Surface Rights

S.N.

Details

Land use details (ha)

1.

Buildings

Agr. Land

Forestland

Wasteland

Settlements

Any other

(provide details)

2.

Infrastructure

 

 

 

 

 

3.

Roads

 

 

 

 

 

4.

Others (specify)

 

 

 

 

 

 

TOTAL

 

 

 

 

 

 

(vii)             Study on the existing flora and fauna in the study area carried out by an institution of relevant discipline and the list of flora and fauna duly authenticated separately for the core and buffer zone and a statement clearly specifying whether the study area forms a part of the migratory corridor of any endangered fauna. The flora and fauna details should be furnished separately for the core zone and buffer zone. The report and the list should be authenticated by the concerned institution carrying out the study and the names of the species scientific and common names) along with the classification under the Wild Life Protection Act, 1972 should be furnished.

(viii)           Details of mineral reserves, geological status of the study area and the seams to be worked, ultimate working depth and progressive stage-wise working plan/scheme until end of mine life should be reflected on the basis of the approved rated capacity and calendar plans of production from the approved Mining Plan. Geological maps should also be included.

(ix)               Impact of mining on hydrology, modification of natural drainage, diversion and channelling of the existing rivers/water courses flowing though the ML and adjoining the lease/project and the impact on the existing users and impacts of mining operations thereon.

(x)                Collection of one-season (non-monsoon) primary baseline data on environmental quality – air (PM10, PM2.5, SOx, NOx and heavy metals such as Hg, Pb, Cr, AS, etc), noise, water (surface and groundwater), soil along with one-season met data.

(xi)               Map of the study area (core and buffer zone) clearly delineating the location of various monitoring stations (air/water/soil and noise – each shown separately) superimposed with location of habitats, wind roses, other industries/mines, polluting sources. The number and location of the stations should be selected on the basis of the proposed impacts in the downwind/downstream/groundwater regime. One station should be in the upwind/upstream/non-impact non-polluting area as a control station. Wind roses to determine air pollutant dispersion and impacts thereof shall be determined. Monitoring should be as per CPCB guidelines and standards for air, water, noise notified under Environment Protection Rules. Parameters for water testing for both ground and surface water should be as per ISI standards and CPCB classification of surface water wherever applicable.

(xii)             Impact of mining and water abstraction and mine water discharge in mine on the hydrogeology and groundwater regime within the core zone and 10km buffer zone including long–term modelling studies on the impact of mining on the groundwater regime. Details of rainwater harvesting and measures for recharge of groundwater should be reflected wherever the areas are declared dark/grey from groundwater development.

(xiii)            Study on subsidence, measures for mitigation/prevention of subsidence, modelling subsidence prediction and its use during mine operation, safety issues.

(xiv)           Detailed water balance should be provided. The break up of water requirement as per different activities in the mining operations, including use of water for sand stowing should be given separately. Source of water for use in mine, sanction of the competent authority in the State Govt. and impacts vis-à-vis the competing users should be provided.

(xv)             Impact of choice of mining method, technology, selected use of machinery - and impact on air quality, mineral transportation, coal handling & storage/stockyard, etc, Impact of blasting, noise and vibrations.

(xvi)           Impacts of mineral transportation – within and outside the lease/project. The entire sequence of mineral production, transportation, handling, transfer and storage of mineral and waste, and their impacts on air quality should be shown in a flow chart with the specific points where fugitive emissions can arise and the specific pollution control/mitigative measures proposed to be put in place. Examine the adequacy of roads existing in the area and if new roads are proposed, the impact of their construction and use particularly if forestland is used.

(xvii)          Details of various facilities to be provided in terms of parking, rest areas, canteen, and effluents/pollution load from these activities.  Examine whether existing roads are adequate to take care of the additional load of mineral and their impacts.

(xviii)        Examine the number and efficiency of mobile/static water sprinkling system along the main mineral transportation road within the mine, approach roads to the mine/stockyard/siding, and also the frequency of their use in impacting air quality.

(xix)            Impacts of CHP, if any on air and water quality. A flow chart of water use and whether the unit can be made a zero-discharge unit.

(xx)             Conceptual Final Mine Closure Plan along with the fund requirement for the detailed activities proposed there under.  Impacts of change in land use for mining operations and whether the land can be restored for agricultural use post mining.

            Table 1 Stage-wise Cumulative Plantation

S.N.

YEAR*

Green Belt

External Dump

Backfilled Area

Others

(Undisturbed

Area/etc)

TOTAL

 

 

Area

(ha)

No. of trees

Area

(ha)

No. of Trees

Area

(ha)

No. of Trees

Area

(ha)

No. of

 Trees

Area

(ha)

No. of

 Trees

1.

1st year

 

 

 

 

 

 

 

 

 

 

2.

3rd year

 

 

 

 

 

 

 

 

 

 

3.

5th year

 

 

 

 

 

 

 

 

 

 

4.

10th yesr

 

 

 

 

 

 

 

 

 

 

5.

15th year

 

 

 

 

 

 

 

 

 

 

6.

20th year

 

 

 

 

 

 

 

 

 

 

7.

25th year

 

 

 

 

 

 

 

 

 

 

8.

30th year

 

 

 

 

 

 

 

 

 

 

9.

34th year (end of mine life)

 

 

 

 

 

 

 

 

 

 

10.

34-37th Year (Post-mining)

 

 

 

 

 

 

 

 

85*

2,12,500

            *As a representative example

 

(xxi)            Occupational health issues. Baseline data on the health of the population in the impact zone and measures for occupational health and safety of the personnel and manpower for the mine should be furnished.

(xxii)          Details of cost of EMP (capital and recurring) in the project cost and for final mine closure plan. The specific costs (capital and recurring) of each pollution control/mitigative measures proposed in the project until end of mine life and a statement that this is included in the project cost.

(xxiii)         Integrating in the Env. Management Plan with measures for minimising use of natural resources – water, land, energy, raw materials/mineral, etc.

(xxiv)        R&R: Detailed project specific R&R Plan with data on the existing socio-economic status (including tribals, SC/ST) of the population in the study area and broad plan for resettlement of the displaced population, site for the resettlement colony, alternate livelihood concerns/employment for the displaced people, civic and housing amenities being offered, etc and costs along with the schedule of the implementation of the R&R Plan.

(xxv)          CSR Plan along with details of villages and specific budgetary provisions (capital and recurring) for specific activities over the life of the project.

(xxvi)        Public Hearing should cover the details as specified in the EIA Notification 2006, and include notices issued in the newspaper, proceedings/minutes of public hearing, the points raised by the general public and commitments by the proponent made should be presented in a tabular form. If the Public Hearing is in the regional language, an authenticated English Translation of the same should be provided.

(xxvii)       Status of any litigations/ court cases filed/pending in any Court/Tribunal on the project should be furnished.

(xxxvi)     Submission of sample test analysis of:

(xxxvii) Characteristics of coal - this includes grade of coal and other characteristics – ash, S

            and heavy metals including levels of Hg, As, Pb, Cr etc.

(xxxviii) Copy of clearances/approvals – such as Forestry clearances, Mining Plan Approval, NOC from Flood and Irrigation Dept. (if req.), etc.

 

 

            (A) FORESTRY CLEARANCE

 

TOTAL ML/PROJECT 

AREA (ha)

TOTAL FORESTLAND (ha)

Date of FC

Extent of forestland

Balance area for which FC is yet to be obtained

Status of appl. for diversion of

forestland

 

 

If more than one, provide details of each FC

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

            (B)        MINING PLAN /PROJECT APPROVAL

                        Date of Approval of Mining Plan/Project Approval:

                        Copy of Letter of Approval of Mining Plan/Project Approval

(xxxviii) Corporate Environment Responsibility:

a)     The Company must have a well laid down Environment Policy approved by the Board of Directors.

b)     The Environment Policy must prescribe for standard operating process/procedures to bring into focus any infringements/deviation/violation of the environmental or forest norms/conditions.

c)     The hierarchical system or Administrative Order of the company to deal with environmental issues and for ensuring compliance with the environmental clearance conditions must be furnished.

d)  To have proper checks and balances, the company should have a well laid down system of reporting of non-compliances/violations of environmental norms to the Board of Directors of the company and/or shareholders or stakeholders at large.

 

TOR FOR COAL WASHERY

(i)                  A brief description of the plant, the technology used, the source of coal, the mode of transport of incoming unwashed coal and the outgoing washed coal. Specific pollution control and mitigative measures for the entire process.

(ii)                The EIA-EMP report should cover the impacts and management plan for the project of the capacity for EC is sought and the impacts of specific activities on the environment of the region, and the environmental quality – air, water, land, biotic community, etc. through collection of data and information, generation of data on impacts for the rated capacity. If the washery is captive to a coal mine/TPP/Plant the cumulative impacts on the environment and usage of water should be brought out along with the EMP.

(iii)               A Study area map of the core zone and 10km area of the buffer showing major industries/mines and other polluting sources, which shall also indicate the migratory corridors of fauna, if any and the areas where endangered fauna and plants of medicinal and economic importance are found in the area. If there are any ecologically sensitive areas found within the 15km buffer zone, the shortest distance from the National Park/WL Sanctuary Tiger Reserve, etc should be shown and the comments of the Chief Wildlife Warden of the State Government should be furnished.

(iv)              Collection of one-season (non-monsoon) primary base-line data on environmental quality – air (PM10, PM2.5, SOx and NOx), noise, water (surface and groundwater), soil. 

(v)                Detailed water balance should be provided. The break up of water requirement as per different activities in the mining operations vis-à-vis washery should be given separately. Source of water for use in mine, sanction of the competent authority in the State Govt.. and examine if the unit can be zero discharge including recycling and reuse of the wastewater for other uses such as green belt, etc.

(vi)       Impact of choice of the selected use of technology and impact on air quality and waste generation (emissions and effluents). 

(vii)      Impacts of mineral transportation - the entire sequence of mineral production, transportation, handling, transfer and storage of mineral and waste, if any, and their impacts on air quality should be shown in a flow chart with the specific points where fugitive emissions can arise and the specific pollution control/mitigative measures proposed to be put in place.

(viii)      Details of various facilities to be provided for the personnel involved in mineral transportation in terms of parking, rest areas, canteen, and effluents/pollution load from these activities.  Examine whether existing roads are adequate to take care of the additional load of mineral [and rejects] transportation, their impacts. Details of workshop, if any, and treatment of workshop effluents.

(ix)       Impacts of CHP, if any on air and water quality. A flow chart of water use and whether the unit can be made a zero-discharge unit.

(x)        Details of green belt development.

(xi)       Including cost of EMP (capital and recurring) in the project cost.

(xiv)      Public Hearing details of the coal washery to include details of notices issued in the newspaper, proceedings/minutes of public hearing, the points raised by the general public and commitments made in a tabular form. If the Public Hearing is in the regional language, an authenticated English Translation of the same should be provided.

(xv)                         Status of any litigations/ court cases filed/pending on the project.

(xvi)                       Submission of sample test analysis of:

I     Characteristics of coal to be washed- this includes grade of coal and other characteristics – ash, S and and heavy metals including levels of Hg, As, Pb, Cr etc.

II    Characteristics and quantum of washed coal.

III  Characteristics and quantum of coal waste rejects.

(xvii)     Management/disposal/Use of coal waste rejects

(xviii)    Copies of MOU/Agreement with linkages (for stand alone washery) for the capacity for which EC has been sought.

(xxxvii)    Submission of sample test analysis of:

Characteristics of coal to be washed- this includes grade of coal and other characteristics – ash, S

 

Washery Details

Washery-

(MTPA)

Expn. of Washery

(.. MTPA to .. MTPA

TOTAL

(MTPA)

Ash content (%)

Obtained from/End User

Raw Coal (ROM)

 

 

 

 

 

 

Washed Coal

 

 

 

 

 

 

Middling + Coal Fines

 

 

 

 

 

 

Coal Rejects

 

 

 

 

 

 

 

The following general points should be noted:

(i)         All documents should be properly indexed, page numbered.

(ii)        Period/date of data collection should be clearly indicated.

(iii)       Authenticated English translation of all material provided in Regional languages.

(iv)       After the preparation of the draft EIA-EMP Report as per the aforesaid TOR, the proponent shall get the Public Hearing conducted as prescribed in the EIA Notification 2006 and take necessary action for obtaining environmental clearance under the provisions of the EIA Notification 2006.

(v)                The letter/application for EC should quote the MOEF file No. and also attach a copy of the letter prescribing the TOR.

(vi)              The copy of the letter received from the Ministry on the TOR prescribed for the project should be attached as an annexure to the final EIA-EMP Report.

(vii)      The final EIA-EMP report submitted to the Ministry must incorporate the issues in TOR and that raised in Public Hearing. The index of the final EIA-EMP report, must indicate the specific chapter and page no. of the EIA-EMP Report where the specific TOR prescribed by Ministry and the issue raised in the P.H. have been incorporated. Mining Questionnaire (posted on MOEF website) with all sections duly filled in shall also be submitted at the time of applying for EC.

(viii)      General Instructions for the preparation and presentation before the EAC of TOR/EC projects of Coal Sector should be incorporated/followed.

(viii)      The aforesaid TOR has a validity of two years only.

 

The following additional points are also to be noted:

(i)                  Grant of TOR does not necessarily mean grant of EC.

(ii)                Grant of TOR/EC to the present project does not necessarily mean grant of TOR/EC to the captive/linked project.

(iii)               Grant of TOR/EC to the present project does not necessarily mean grant of approvals in other regulations such as the Forest (Conservation) Act 1980 or the Wildlife (Protection) Act, 1972.

(iv)       Grant of EC is also subject to Circulars issued under the EIA Notification 2006, which are available on the MOEF website: www.envfor.nic.in

Yours faithfully,

 

 

 

(Dr.T.Chandini)

Director

 

 

Copy to: Member-Secretary, Jharkhand State Pollution Control Board, TA Building, HEC Complex, P.O. Dhurva, Ranchi - 834002.

 

Untitled Page