No. J-11015/01/2011-IA.II(M)

Government of India

Ministry of Environment & Forests

Paryavaran Bhawan,

CGO Complex,

New Delhi-110510.

To

Dated: 16th March 2011

Director (tech.),

M/s BCCL,

Koyla Bhawan, Dhanbad.

 

Sub:     Cluster V (7 mines) of normative prod. cap. of 4.854 MTPA and 6.311 MTPA (peak) of M/s Bharat Coking Coal Ltd. located in Jharia Coalfields, dist. Dhanbad, Jharkhand - Terms of Reference  (TOR) – reg.

 

Sir,

            This is with reference to letter no. 43011/48/2010-CPAM dated 03.01.2011 regarding the aforesaid subject which was considered in the meeting of Expert Appraisal Committee (Thermal & Coal) in the meeting held on 24th -25th January 2011. In the presentation made, it was informed that the cluster V consists of 7 mines consisting of  6 OC and UG mines  and 1 UG closed mine of a combined ML area of 1957.08 ha and prod. capacity of 4.854 MTPA and 6.311 MTPA (peak) as given below:

 

S.N.

 

MINES IN CLUSTER -V

Name of Mine

Production capacity(MTY)

Lease Hold Area(HA)

Life of Mine

(years)

NORMATIVE

PEAK

1

Nichitpur OC Mines

0.6

0.78

150

10

2

Tetulmari Colliery Opencast & Underground mines

0.795

1.033

317

>30

3

Mudidih Colliery Opencast & Underground mines

1.553

2.019

378.05

>30

4.

Sendra Bansjore Colliery  Opencast & Underground mines

0.75

0.975

249.63

23

5

Kankanee Colliery Opencast &Underground mines

0.48

0.624

258.12

>30

6.

Bansdeopur Colliery (Opencast & Underground mines)

0.676

0.879

104.72

>30

7.

Loyabad UG Mines (closed for coal production)

0

0

499.56

-

 

 

Total

4.854

6.311

1957.08

-

 

 

LAND USE OF CLUSTER V

 

S.No

Type Land Use

Present Mining

Land Use(In Ha)

Proposed Mining Land Use(In Ha)

Post- Mining Land Use(In Ha)

1.

Running quarry

 

 

 

Backfilled

112.13

36.35

0.00

Not Backfilled

123.47

44.38

0.00

 

2.

Abandoned quarry

 

 

 

Backfilled

82.53

0.00

0.00

Not Backfilled

48.98

0.00

0.00

3.

External OB dump

73.07

0.00

0.00

4.

Service building/mine infrastructure

13.87

11.86

0.00

5.

Coal dump

12.15

12.15

0.00

6.

Rail & Road

124.03

113.22

113.22

7.

Homestead land

272.93

248.00

248.00

8.

Agriculture land

14.00

14.00

14.00

9.

Plantation/reclamation

150.45

979.25

1089.62

10

Water body

29.19

51.57

95.95

11.

Barren land

900.28

446.28

396.28

 

                                Total

 

1957.08

 

1957.08

 

1957.08

 

      The details of Rehabilitation for Mines in CLUSTER V

 

S.N.

Parameter

Details

1.

Total Voids

25.87 Mm3

2.

Total External OB

21.92 Mm3

3.

Total Unstable Sites

77 no.

4.

Total Affected Areas

1383420 m2

5.

No. of Houses to be rehabilitated

5835 no. as per JAP

6.

Land for Resettlement

39.76 ha (BCCL land) 72.53 ha (Non-BCCL land)

7.

Total cost of fire dealing

16465 lakhs

8.

Total  resettlement Cost

Rs 104024.9 lakhs

 

 

This cluster is bounded east by cluster VI group of mines and in the west by cluster IV mines and by cluster XI mines in the south and within Jharia Coalfields. Mine area is drained by Nagri Jore & Ekra Jore, flowing towards South and South West respectively across the cluster.

 

The Committee desired that AAQ monitoring stations should be established based on the locations of habitations, pollution generating sources and the wind direction and should be checked for impacts of measures taken on the air quality in view that Dhanbad  is a critically polluted area. The Committee desired that abandoned pits/quarries if any, of worked out mines of pre-nationalisation period should be backfilled and reclaimed with plantation properly. The Committee also desired that the details of Jharia Action Plan involving resettlement of habitation from unstable sites within the cluster should be an integrated with the EIA-EMP study for the entire cluster along with specific time targets of the schedule of implementation. The Committee desired that the R&R Plan involving 5835 homesteads living in unstable locations within the cluster requiring to be rehabilitated should be prepared.

 

The Committee desired a detailed CSR Plan for the entire cluster and Rs 5 per tonne of coal to be earmarked for activities under CSR. The Committee also desired that a dedicated multidisciplinary team of experts of all age groups including locals particularly the freshly inducted should be created to continue with the smooth implementation and completion and monitoring of the Jharia Action Plan.

 

Based on the application along with documents and presentation thereon and discussions held, the Committee prescribed the following TOR:

(i)                  An Integrated EIA-EMP Report for cluster V consisting of 7 mines consisting of  6 OC and UG mines  and 1 UG closed mine of a combined ML area of 1957.08 ha should be prepared for 4.854 MTPA (normative) with 6.311 MTPA (peak) rated capacity based on the generic structure specified in Appendix III of the EIA Notification 2006. The Integrated EIA-EMP for the cluster V  mines shall be prepared clearly bringing out the present status of 7 mines in Cluster V as above- status of env. quality and the extent of pollution load from each mine and the combined pollution load from the cluster of mines that would be reduced by taking suitable mitigative measures for the individual mines and for the cluster and the expected improvement in the environmental quality of the mines in the cluster and within the coalfield after the implementation of the measures through an Integrated Environmental Plan formulated on the aforesaid basis.  A fresh baseline data on the env. quality – air, water, land, biotic community, etc. shall be generated through collection of data and information, generation of data on impacts. Baseline data collection can be for any season except monsoon. Details of the present land use and post mining land use of the operating and abandoned mines individually and as a cluster shall be furnished as part of the EIA. A detailed Mine Closure Plan and a Mine Reclamation Plan for the abandoned mines (UG and OC)/pits/quarries found in the cluster shall be furnished as a part of EIA-EMP study. The closure of UG mines should ensure that no illegal mining is done thereafter from the mines. Details of long term benefits to environment because of cluster approach of mining shall be clearly addressed in the EIA-EMP study. In addition to the above, details of an Action Plan for project specific R&R and CSR shall also be formulated and presented in the EIA-EMP. The aforesaid Integrated Environmental Management Plan shall be dovetailed with the Jharia Action Plan and details of its implementation with specific time-lines should be provided. As Dhanbad is a Critically Polluted Area, the specific Action Plan for mitigation and improvement of env. quality should be presented.

(ii)                 An EIA-EMP Report would be prepared for 4.854 MTPA (normative) with 6.311 MTPA (peak) rated capacity cover the impacts and management plan for the project specific activities on the environment of the region, and the environmental quality – air, water, land, biotic community, etc. through collection of data and information, generation of data on impacts including prediction modelling for 4.854 MTPA (normative) with 6.311 MTPA (peak) of coal production based on approval of project/Mining Plan for 6.311 MTPA (peak). Baseline data collection can be for any season except monsoon.

(iii)                A map specifying locations of the State, District and Project location.

(iv)               A Study area map of the core zone and 10km area of the buffer zone (1: 50,000 scale) clearly delineating the major topographical features such as the land use, surface drainage of rivers/streams/nalas/canals, locations of human habitations, major constructions including railways, roads, pipelines, major industries/mines and other polluting sources. In case of ecologically sensitive areas such as Biosphere Reserves/National Parks/WL Sanctuaries/ Elephant Reserves, forests (Reserved/Protected), migratory corridors of fauna, and areas where endangered fauna and plants of medicinal and economic importance found in the 15 km area of the buffer zone should be given.

(v)                 Land use map (1: 50,000 scale) based on a recent satellite imagery of the study area may also be provided with explanatory note of the land use. Satellite imagery per se is not required.

(vi)               Map showing the core zone delineating the agricultural land (irrigated and unirrigated, uncultivable land (as defined in the revenue records), forest areas (as per records), along with other physical features such as water bodies, etc should be furnished.

(vii)              A contour map showing the area drainage of the core zone and 2-5 km of the buffer zone (where the water courses of the core zone ultimately join the major rivers/streams outside the lease/project area) should also be clearly indicated as a separate map.

(viii)            A detailed Site plan of the mine showing the various proposed break-up of the land for mining operations such as the quarry area, OB dumps, green belt, safety zone, buildings, infrastructure, CHP, ETP, Stockyard, township/colony (within and adjacent to the ML), undisturbed area and if any, in topography such as existing roads, drains/natural water bodies are to be left undisturbed along with any natural drainage adjoining the lease /project and modification of thereof in terms of construction of embankments/bunds, proposed diversion/rechannelling of the water courses, etc., approach roads, major haul roads, etc.

(ix)               In case of any proposed diversion of nallah/canal/river, the proposed route of diversion/modification of drainage and their realignment, construction of embankment etc. should also be shown on the map.

(x)                 Similarly if the project involves diversion of any road/railway line passing through the ML/project area, the proposed route of diversion and its realignment should be shown.

(xi)               Break up of lease/project area as per different land uses and their stage of acquisition.

(xii)              Break-up of lease/project area as per mining operations.

(xiii)            Impact of changes in the land use due to the start of the projects if much of the land being acquired is agricultural land/forestland/grazing land.

(xiv)            The Committee desired that AAQ monitoring stations should be established based on the locations of habitations, pollution generating sources and the wind direction and should be checked for impacts of measures taken on the air quality in view that Dhanbad  is a critically polluted area.Collection of one-season (non-monsoon) primary baseline data on environmental quality - air (PM10, PM2.5, SOx, NOx and heavy metals such as Hg, Pb, Cr, As, etc), noise, water (surface and groundwater), soil along with one-season met data.

(xv)             Map of the study area (1: 50, 000 scale)  (core and buffer zone clearly delineating the location of various stations superimposed with location of habitats, other industries/mines, polluting sources. The number and location of the stations in both core zone and buffer zone should be selected on the basis of size of lease/project area, the proposed impacts in the downwind (air)/downstream (surface water)/groundwater regime (based on flow). One station should be in the upwind/upstream/non-impact/non-polluting area as a control station. The monitoring should be as per CPCB guidelines and parameters for water testing for both ground water and surface water as per ISI  standards and CPCB classification wherever applicable.

(xvi)            Study on the existing flora and fauna in the study area (10km) carried out by an institution of relevant discipline and the list of flora and fauna duly authenticated separately for the core and buffer zone and a statement clearly specifying whether the study area forms a part of the migratory corridor of any endangered fauna. If the study area has endangered flora and fauna, or if the project falls within 15 km of an ecologically sensitive area, then a comprehensive Conservation Plan should be prepared and furnished along with comments from the CWLW of the State Govt.

(xvii)          Details of mineral reserves, geological status of the study are and the seams to be worked, ultimate working depth and progressive stage-wise working scheme until end of mine life should be reflected on the basis of the approved rated capacity and calendar plans of production from the approved Mining Plan. Geological maps and sections should be included. The progressive mine development and final mine closure plan should also be shown in figures.

(xviii)         Details of mining methods, technology, equipment to be used, etc., rationale for selection of that technology and equipment proposed to be used vis-à-vis the potential impacts.

(xix)            Study on subsidence, measures for mitigation/prevention of subsidence, modelling subsidence prediction and its use during mine operation, safety issues.

(xx)             Impact of mining on hydrology, modification of natural drainage, diversion and channelling of the existing rivers/water courses flowing though the ML and adjoining the lease/project and the impact on the existing users and impacts of mining operations thereon.

(xxi)            Detailed water balance should be provided. The break up of water requirement for the various mine operations should be given separately.

(xxii)          Source of water for use in mine, sanction of the competent authority in the State Govt. and impacts vis-à-vis the competing users.

(xxiii)         Impact of mining and water abstraction use in mine on the hydrogeology and groundwater regime within the core zone and 10 km buffer zone including long–term modelling studies on. Details of rainwater harvesting and measures for recharge of groundwater should be reflected in case there us a declining trend of groundwater availability and/or if the area falls within dark/grey zone.

(xxiv)        Impact of blasting, noise and vibrations.                       

(xxv)          Impacts of mining on the AAQ, predictive modelling using the ISCST-3 (Revised) or latest model.

(xxvi)        Impacts of mineral transportation – within and outside the lease/project along with flow-chart indicating the specific areas generating fugitive emissions. Impacts of transportation, handling, transfer of mineral and waste on air quality, generation of effluents from workshop, management plan for maintenance of HEMM, machinery, equipment. Details of various facilities to be provided in terms of parking, rest areas, canteen, and effluents/pollution load from these activities.

(xxvii)       Details of waste generation – OB, topsoil – as per the approved calendar programme, and their management shown in figures as well explanatory chapter with tables giving progressive development and mine closure plan, green belt development, backfilling programme and conceptual post mining land use. OB dump heights and terracing should based on slope stability studies with a max of 28o angle as the ultimate slope. Sections of dumps (ultimate) (both longitudinal and cross section) with relation to the adjacent area should be shown.

(xxviii)     Impact and management of wastes and issues of rehandling and backfilling and progressive mine closure and reclamation.

(xxix)        Flow chart of water balance. Treatment of effluents from workshop, township, domestic wastewater, mine water discharge, etc. Details of STP in colony and ETP in mine. Recycling of water to the max. possible extent.

(xxx)          Occupational health issues. Baseline data on the health of the population in the impact zone and measures for occupational health and safety of the personnel and manpower for the mine.

(xxxi)        Disaster Management Plan and Risk Assessment.

(xxxii)       Integrating in the Env. Management Plan with measures for minimising use of natural resources - water, land, energy, etc.

(xxxiii)     Progressive Green belt and afforestation plan (both in text, figures as well as in tables prepared by MOEF).  and selection of species (local) for the afforestation/plantation programme based on original survey/landuse.

(xxxiv)     Conceptual Final Mine Closure Plan, post mining land use and restoration of land/habitat to pre- mining. A Plan for the ecological restoration of the area post mining and for land use should be prepared with detailed cost provisions.

(xxxv)      Including cost of EMP (capital and recurring) in the project cost and for progressive and final mine closure plan.

(xxxvi)     The Committee desired that the R&R Plan involving 5835 homesteads living in unstable locations within the cluster requiring to be rehabilitated should be prepared. Details of R&R.  Detailed project specific R&R Plan with data on the existing socio-economic status of the population (including tribals, SC/ST, BPL families) found in the study area and broad plan for resettlement of the displaced population, site for the resettlement colony, alternate livelihood concerns/employment for the displaced people, civic and housing amenities being offered, etc and costs along with the schedule of the implementation of the R&R Plan.

(xxxvii)   Public Hearing should cover the details of notices issued in the newspaper, proceedings/minutes of public hearing, the points raised by the general public and commitments made by the proponent should be presented in a tabular form. If the Public Hearing is in the regional language, an authenticated English Translation of the same should be provided.

(xxxviii)  In built mechanism of self-monitoring of compliance of environmental regulations.

(xxxx)   Status of any litigations/ court cases filed/pending on the project.

(xxxxi)  Submission of sample test analysis of:

(xxxxii) Copy of clearances/approvals – such as Forestry clearances, Mining Plan Approval, NOC from

            Flood and Irrigation Dept. (if req.), etc.

 

The following general points should be noted:

(i)         All documents should be properly indexed, page numbered.

(ii)         Period/date of data collection should be clearly indicated.

(iii)        Authenticated English translation of all material provided in Regional languages.

(iv)        After the preparation of the draft EIA-EMP Report as per the aforesaid TOR, the proponent shall get the Public Hearing conducted as prescribed in the EIA Notification 2006 and take necessary action for obtaining environmental clearance under the provisions of the EIA Notification 2006.

(v)                 The letter/application for EC should quote the MOEF file No. and also attach a copy of the letter prescribing the TOR.

(vi)               The copy of the letter received from the Ministry on the TOR prescribed for the project should be attached as an annexure to the final EIA-EMP Report.

(vii)       The final EIA-EMP report submitted to the Ministry must incorporate the issues in TOR and that raised in Public Hearing. The index of the final EIA-EMP report, must indicate the specific chapter and page no. of the EIA-EMP Report where the specific TOR prescribed by Ministry and the issue raised in the P.H. have been incorporated. Mining Questionnaire (posted on MOEF website) with all sections duly filled in shall also be submitted at the time of applying for EC.

(viii)      The aforesaid TOR has a validity of two years only.

 

After the preparation of the draft EIA-EMP Report as per the aforesaid TOR, and the public Hearing conducted as prescribed in the EIA Notification 2006 and the proponent will take necessary action for obtaining environmental clearance under provisions of the EIA Notification 2006.

 

Yours faithfully,

 

 

 

(Dr.T.Chandini)

Director

 

 

Copy to: Member-Secretary, Jharkhand State Pollution Control Board, TA Building, HEC Complex, P.O. Dhurva, Ranchi - 834002.

 

Untitled Page