No.J-11015/311/2006-IA.II(M)

Government of India

Ministry of Environment & Forests

Paryavaran Bhawan,

C.G.O.Complex, Lodi Road,

New Delhi -110003.

 

Dated: 16th May 2007

To

Shri Harshad Pophali,

Manger – Mining Diviison,

M/s Jayeswals Neco Ltd.,

F-8, MIDC, Hinga Road,

NAGPUR – 440016.

 

Sub:       Moitra Coal Mining Project (1 MTPA) of M/s Jayeswals Neco Ltd., located in village Moitra, Tehsil Barkagaon, District Hazaribagh, Jharkand - environmental clearance – reg.

 

Sir,

 

                This has reference to your letter No. JNL/Moitra/ECMoEF/06/68 dated 09.10.2006 along with your application and subsequent letter dated 22.01.007 on the above-mentioned subject. The Ministry of Environment & Forests has considered your application.  It has been noted that the project is for opening a new Opencast Coal Mine Project at a rated capacity of 1 million tonnes per annum) MTPA of coal for the captive consumption of the Integrated Steel Plant which has obtained EC on 14.05.2004 and the linked 135MW Power Plant. The total lease area is 293.54 ha of which 194.83 ha is agricultural land, 90.66 ha is forestland, 5.47 ha is surface water bodies, and 2.58 ha is Govt. land. Forestry clearance has been applied for. There are no National Parks, Wildlife Sanctuary, Biosphere Reserves found in the 10 km buffer zone. However, the study area contains a number of rare and endangered/Schedule-I and II fauna such as the Indian Elephant, Bear, Leopard, Pangolin, Indian Wolf, Monitor Lizard and Vulture. The area does not form part of the migratory corridor of any protected/endangered species. River Badmahi flows along the south-west boundary of the mine lease and the Rajhar nala flows through the mining block. The project involves modification of the natural drainage by construction of embankment of a height of 3 m, and which is 3m higher than the HFL of the river flowing along the southern boundary of the lease for protection against flood/mine inundation. The Rajhar nala would also be diverted during the 10th year by 200m from its course and gain realigned with its original course during the 0th year of operation. Site clearance was obtained o 10.04.2006. Of the total lease area, area for excavation is 143.86 ha, 84.04 ha is for OB dumps, 19.01 ha is for infrastructure, 20.05 ha is for roads and for safety zone, 5.47 ha is for surface water body, and 21.11 ha is for garland drains. No township/colony is proposed. Mining will be opencast by semi-mechanised method and involves controlled blasting using delay detonators. The rated capacity of the mine is 1 MTPA of coal production. A coal washery of 1 MTPA capacity is planned at the pit head for coal beneficiation and based on zero discharge principle. Mineral transportation of 1167 TPD (0.35 MTPA) of clean coal is by road covering a distance of 45 km and thereafter by rail to Integrated Steel plant at a distance of 660 km and the remaining 2166 TPD is by dumpers to the washery located within the lease and thereafter by conveyors covering a distance of 1.5km for captive consumption of the power plant. Ultimate working depth of the mine is 215m below ground level (bgl). Water table is in the range of 2.25 -7.01 m bgl in the core zone and 2.53 – 6.20 m bgl in the buffer zone. Mining will intersect water table. Peak water requirement is 1010 m3/d, which will be met from mine pit water. Of this, 460 m3/d is for coal beneficiation in the washery and 400 m3/d is for dust suppression. There is no discharge of wastewater from the coal washery and from the CHP as they are zero-discharge units. An estimated 77.58 Mm3 of OB will be generated in the life of mine of which 36% will be backfilled and the balance stored in one external OB dump of  a max. height of 90m with 3 benches of 30m each, which will be biologically reclaimed with plantation. Clean coal would be dispatched to the Integrated Steel Plant and the midlings and rejects generated in washeries will be used in the  power plant and fines for further utilisation. Project involves R&R of two villages in the core zone – Moitra and Hahe. Life of the mine at the rated capacity of 1 MTPA is 33 years. Public Hearing was held on 03.07.2006. NOC has been obtained on 15.09.2006. The Mining Plan has been approved by Ministry of Coal on 11.11.2005. Capital cost of the project is Rs. 4620 lakhs.

 

2.             The Ministry of Environment & Forests hereby accords environmental clearance for the above-mentioned Moitra Coal Mining Project of M/s Jayeswals Neco Ltd. for production of coal at  1 MTPA rated capacity involving a total lease area of 293.54 ha under Section 12 of the Environmental Impact Assessment Notification, 2006 and subsequent amendments thereto and under Para 2.1.1 of MOEF Circular dated 13.10.2006 subject to the compliance of the terms and conditions mentioned below:

 

A.            Specific Conditions

 

(i)            No mining operations shall be undertaken in the forestland until clearance has been obtained under the provisions of FC Act, 1980.

 

(ii)           The embankment shall be designed taking into account the highest flood level, based on past data, along the quarry area at the mine boundary along the River Badmahi so as to guard against mine inundation. The slope of the embankment shall at least 2:1 towards the ML and shall be stabilised by plantation. The height of the embankment shall be at least 5 m higher than the HFL.

 

(iii)              Diversion of the Rajhar nala shall be done with approval of the competent authority. Users of the water from the nala during the period of its diversion shall be provided with alternate sources of water, if required. Detailed proposal for realignment of the nala shall be submitted to this ministry at least one year prior to start of the realignment work.

 

(iv)               Augmentation of road network for mineral transportation from the ML shall be done with approval of the competent authority of the State Govt. All approach roads and main haul roads shall be metal topped.

 

(v)           Topsoil should be stacked properly with proper slope at earmarked site(s) and should not be kept active and shall be used for reclamation and development of green belt.

 

(vi)          OB should be stacked at the earmarked external OB dumpsite within ML area and shall be a maximum height of 90m only and consist of benches of 30m each. The ultimate slope of the dump shall not exceed 28o.  Monitoring and management of the reclaimed dumpsites should continue until the vegetation becomes self-sustaining. Compliance status should be submitted to the Ministry of Environment & Forests and its Regional office located at Bhubaneshwar on yearly  basis.

 

(vii)        Catch drains and siltation ponds of appropriate size should be constructed to arrest silt and sediment flows from soil, OB and mineral dumps. The water so collected should be utilised for watering the mine area, roads, green belt development, etc. The drains should be regularly desilted and maintained properly.

Garland drains (size, gradient and length) and sump capacity should be designed keeping 50% safety margin over and above the peak sudden rainfall and maximum discharge in the area adjoining the mine site. Sump capacity should also provided adequate retention period to allow proper settling of silt material.

 

(viii)       Dimension of the retaining wall at the toe of the dumps and OB benches within the mine to check run-off and siltation should be based on the rainfall data.

 

(ix)                          Crushers at the CHP should be operated with high efficiency bag filters, water sprinkling system should be provided to check fugitive emissions from crushing operations, conveyor system, haulage roads, transfer points, etc. Conveyors to pit head shall be closed.

 

(x)          Drills should be wet operated.

 

(xi)         Controlled blasting should be practiced only during daytime with use of delay detonators. The mitigative measures for control of ground vibrations and to arrest the fly rocks and boulders should be implemented.

 

(xii)             Area brought under afforestation shall include reclaimed external OB dump, backfilled area, along ML boundary, along roads, green belt and  in undisturbed areas within the mine lease area by planting native species in consultation with the local DFO/Agriculture Department. The density of the trees should be around 2500 plants per ha.

 

(xiii)       A Progressive Closure Plan shall be implemented by reclamation of quarry area which shall be partially backfilled and afforested by planting native plant species in consultation with the local DFO/Agriculture Department. The density of the trees should be around 2500 plants per ha.

 

(xiii)           A Conservation Plan prepared for rare and endangered species found in and around the project area shall be finalised and implemented in consultation with the State Forest and Wildlife Departments. Separate funds (capital and recurring which is not less than 15% of the capital expenditure) shall be earmarked for implementation of the various activities identified there under and placed at the disposal of the Chief Wildlife Warden and the status thereof shall be regularly reported to this Ministry and the MOEF Regional Office, Bhubaneshwar

 

(xv)        No groundwater/surface water shall be used for the mining/project activities. Additional water required, if any, shall be met by recycling/reuse of the water from mining operations and from rainwater harvesting measures.

 

(xvi)       Regular monitoring of groundwater level and quality should be carried out by establishing a network of exiting wells and construction of new peizometers. The monitoring for quantity should be done four times a year in pre-monsoon (May), monsoon (August), post-monsoon (November) and winter (January) seasons and for quality in May. Data thus collected should be submitted to the Ministry of Environment & Forests and to the Central Pollution Control Board quarterly within one month of monitoring.

 

(xvii)      The Company shall put up artificial groundwater recharge measures for augmentation of groundwater resource. The project authorities should meet water requirement of nearby village(s) in case the village wells go dry due to dewatering of mine.

 

(xviii)    ETP should also be provided for workshop, coal washery and CHP wastewater. There shall be no discharge of wastewater from CHP and the coal washeries. 

 

(xix)       R&R of Moitra and Hahe villages shall not be less than the norms laid down by the State Government and shall not be inferior than that in the National R&R Policy and shall be completed within a specified time-frame.

 

(xx)         For monitoring land use pattern and for post mining land use, a time series of landuse maps (on a scale of 1 : 5000) from start of the project until end of mine life, of the core zone and buffer zone based on satellite imagery shall be done once in 3 years for any particular season which is consistent in the time series, and the report submitted to MOEF and its Regional office at Bhubaneshwar.

 

(xxi)       A Final Mine Closure Plan along with details of Corpus Fund should be submitted to the Ministry of Environment & Forests for approval 5 years in advance of final mine closure for approval.

 

(xx)             Consent to Operate shall be obtained before starting mining operations.

 

B.            General Conditions

 

(i)                  No change in mining technology and scope of working should be made without prior approval of the Ministry of Environment and Forests.

 

(ii)                No change in the calendar plan including excavation, quantum of mineral coal and waste should be made.

 

(iii)              Four ambient air quality monitoring stations should be established in the core zone as well as in the buffer zone for SPM, RPM, SO2 and NOx monitoring.  Location of the stations should be decided based on the meteorological data, topographical features and environmentally and ecologically sensitive targets in consultation with the State Pollution Control Board.

 

(iv)               Fugitive dust emissions (SPM and RPM) from all the sources should be controlled regularly monitored and data recorded properly. Water spraying arrangement on haul roads, wagon loading, dump trucks (loading and unloading) points should be provided and properly maintained.

 

(v)                 Data on ambient air quality (SPM, RPM, SO2 and NOx) should be regularly submitted to the Ministry including its Regional Office at Bhubaneshwar and to the State Pollution Control Board and to the Central Pollution Control Board once in six months.

 

(vi)               Adequate measures should be taken for control of noise levels below 85 dBA in the work environment. Workers engaged in blasting and drilling operations, operation of HEMM, etc should be provided with ear plugs/muffs.

 

(vii)             Industrial wastewater (workshop and wastewater from the mine) should be properly collected, treated so as to conform to the standards prescribed under GSR 422 (E) dated 19th May 1993 and 31st December 1993 or as amended from time to time before discharge. Oil and grease trap should be installed before discharge of workshop effluents.

 

(viii)           Vehicular emissions should be kept under control and regularly monitored. Vehicles used for transporting the mineral should be covered with tarpaulins and optimally loaded.

 

(ix)               Environmental laboratory should be established with adequate number and type of pollution monitoring and analysis equipment in consultation with the State Pollution Control Board.

 

(x)                 Personnel working in dusty areas should wear protective respiratory devices and they should also be provided with adequate training and information on safety and health aspects.

                Occupational health surveillance programme of the workers should be undertaken periodically to observe any contractions due to exposure to dust and to take corrective measures, if needed.

 

(xi)               A separate environmental management cell with suitable qualified personnel should be set up under the control of a Senior Executive, who will report directly to the Head of the company.

 

(xii)             The funds earmarked for environmental protection measures should e kept in separate account and should not be diverted for other purpose. Year-wise expenditure should be reported to this Ministry and its Regional Office at Bhubaneshwar.

 

(xiii)           The Regional Office of this Ministry located at Bhubaneshwar shall monitor compliance of the stipulated conditions. The Project authorities shall extend full cooperation to the office(s) of the Regional Office by furnishing the requisite data/ information/monitoring reports.

 

(i)                  A copy of the will be marked to concerned Panchayat/ local NGO, if any, from whom any suggestion/representation has been received while processing the proposal.

 

(ii)                State Pollution Control Board should display a copy of the clearance letter at the Regional  Office, District Industry Centre and Collector’s Office/Tehsildar’s Office for 30 days.

 

(iii)              The Project authorities should advertise at least in two local newspapers widely circulated around the project, one of which shall be in the vernacular language of the locality concerned within seven days of the clearance letter informing that the project has been accorded environmental clearance and a copy of the clearance letter is available with the State Pollution control Board and may also be seen at the website of the ministry of Environment & Forests at http://envfor.nic.in.

 

3.            The Ministry or any other competent authority may stipulate any further condition for environmental protection.

 

4.            Failure to comply with any of the conditions mentioned above may result in withdrawal of this clearance and attract the provisions of the Environment (Protection) Act, 1986.

 

5.            The above conditions will be enforced inter-alia, under the provisions of the Water (Prevention & Control of Pollution) Act, 1974, the Air (Prevention & Control of Pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public Liability Insurance Act, 1991 along with their amendments and Rules.

 

 

 

(Dr.T.Chandini)

Director

Copy to:

1.       Secretary, Ministry of Coal, Shastri Bhawan, New Delhi.

2.       Secretary, Department of Environment & Forests, Government of Jharkand, Secretariat, Ranchi.

3.       Chief Conservator of Forests, Regional office (EZ), Ministry of Environment & Forests, A/3 Chandrashekarpur, Bhubaneshwar – 751023.

4.       Chairman, Jharkand State Pollution Control Board, TA Building, HEC Complex, PO Dhurwa, Ranchi.

5.       Chairman, Central Pollution Control Board, CBD-cum-Office Complex, East Arjun Nagar, New Delhi -110032.

6.       Member-Secretary, Central Ground Water Authority, Ministry of Water Resources, Curzon Road Barracks, A-2, W-3 Kasturba Gandhi Marg, New Delhi.

7.       District Collector, Hazaribagh, Government of Jharkand.

8.       Monitoring File          9.             Guard File           10.          Record File

 

 

 

(Dr.T.Chandini)

Director

 

 

Untitled Page