No.J-11015/236/2006-IA.II(M)

Government of India

Ministry of Environment & Forests

Paryavaran Bhawan,

C.G.O.Complex, Lodi Road,

New Delhi -110003.

 

11.01.2007

To

Shri R.S.Singh,

Executive Director,

M/s Eletrosteel Castings Ltd.,

19, Camac Street,

KOLKATTA – 700017.

 

 

Sub:                Parbatpur Coal Mine Project (1.80 MTPA.) of M/s Eletrosteel Castings Ltd., located in village Talgoria, Tehsil Chandankyari, District Bokaro, Jharkand- Environmental clearance – reg.

Sir,

 

                This has reference to your letter dated 01.01.2006 enclosing the application and subsequent letter dated 05.10.2006 on the above-mentioned subject. The Ministry of Environment & Forests has considered your application. It has been noted that the project is for opening a new Parbatur Coal Mine Project for an annual production capacity of 1.8 MTPA over a total lease area of 865 ha. Of this, 484 ha is agricultural land, 205 ha is wasteland, 132 ha is grazing land, 1 ha is surface water bodies, and 43 ha is others. There area no National Parks, Wildlife Sanctuary, Biosphere Reserves found in the 10 km buffer zone. The project does not involve R&R. Site clearance was granted on 16.11.2005. River Damodar flows at a distance of 50m to 1500m from the ML boundary. It is not proposed to modify the existing drainage. Mining will be both opencast (OC) and underground (UG) by semi-mechanised/mechanised method. The project includes a Coal Washery capacity for 1 MTPA of washed coal as ancillary operations. Controlled blasting is involved. Rated capacity of the mine is 1.80 million tonnes per annum (MTPA) of coal production. Mineral transportation of 4000 TPD of coal is by road (1000 TPD) involving about 350 vehicles covering a distance of 15 km and by rail (3000 TPD).. Ultimate working depth of the mine by opencast operations is 92m below ground level (bgl) and 600m bgl by UG mining. Water table is in the range of 2.76-4.93 m bgl in the core zone and 3.20-6.30m bgl in the buffer zone. Mining will intersect water table. Peak water demand is 9415 m3/d of water which is met from mine sump/pit water (8600 m3/d) and from groundwater (100 m3/d). during construction stage only. The sump water (8600 m3/d) wil be use for mine operation (5000 m3/d), dust suppression (250 m3/d), domestic use (35 m3/d), green belt (250 3/d), coal washery (1400 m3/d) and for stowing (1400 m3/d). Further requirement of water, if any, will be from rainwater harvesting measures. An estimated 15 Mm3 of OB will be generated of which 9 Mm3 will be backfilled at the end of mine life, 5 Mm3 will be used for levelling, and 1 Mm3 for strengthening of river embankment. The balance OB will be stored in 2 external OB dumps of a max. height of 60m consisting of 6-10m terraces. Life of the mine at the rated capacity is 55 years. Public Hearing was held on 05.05.2006. NOC has been obtained on 15.07.2006. Mining Plan has been approved by the Ministry of Coal on 14.07.2006. Capital cost of the project is Rs. 350 crores.

 

2.             The Ministry of Environment & Forests has examined the application in accordance with Section 12 of the EIA Notification 2006 and under the provisions thereof, hereby accords environmental clearance for the above-mentioned Parbatpur Coal Mine Project of M/s Electrosteel Castings Ltd. over a lease area of 865 ha for production of coal at 1.8 MTPA rated capacity under the provisions of the Environmental Impact Assessment Notification, 2006 subject to the compliance of the terms and conditions mentioned below:

 

 

A.            Specific Conditions

 

(i)                  All the conditions stipulated by the SPCB in their NOC shall be effectively implemented.

 

(ii)           Mining shall be carried out as per statuette at a safe distance from the river and any water body flowing within the lease boundary. At the time of depillaring, protective bunds and garland drains shall be provided so that no water from the surface enters the subsidence area and the shaft.

 

(iii)         While extracting panels in the lower seam, all water bodies in the subsidence area shall be drained. Dewatering of the old goaves of the upper seam shall be continued as long as the lower seam is worked to prevent accumulation of large water bodies over working area.

 

(iv)                Sufficient coal pillars shall be left unextracted around the air shaft (within the subsidence influence area) to protect from any damage from subsidence, if any.

 

(v)           Solid barriers shall be left below the roads falling within the blocks to avoid any damage to the roads.

 

(vi)          No depillaring operation shall be carried out below the roads and village area found within the lease.

 

(vii)        Regular monitoring of subsidence movement on the surface over and around the working area and impact on natural drainage pattern, water bodies, vegetation, structure, roads, and surroundings should be continued till movement ceases completely. In case of observation of any high rate of subsidence movement, appropriate effective corrective measures should be taken to avoid loss of life and material. Cracks should be effectively plugged with ballast and clayey soil/suitable material.

 

(viii)           Garland drains (size, gradient and length) around the safety areas such as mine shaft and low lying areas and sump capacity should be designed keeping 50% safety margin over an above the peak sudden rainfall and maximum discharge in the area adjoining the mine sites. Sump capacity should also provided adequate retention period to allow proper settling of silt material.

 

(ix)          OB should be stacked at the two earmarked external OB dumpsite(s) within ML area and shall have a maximum height of 60m only and consist of benches of 6-10 m each. The ultimate slope of the dump shall not exceed 28o. Monitoring and management of existing reclaimed dumpsites should continue until the vegetation becomes self-sustaining. Compliance status should be submitted to the Ministry of Environment & Forests and its Regional office located at Bhubaneshwar on yearly  basis.

 

(x)           Catch drains and siltation ponds of appropriate size should be constructed to arrest silt and sediment flows from soil, OB and mineral dumps. The water so collected should be utilised for watering the mine area, roads, green belt development, etc. The drains should be regularly desilted and maintained properly.

Garland drains (size, gradient and length) and sump capacity should be designed keeping 50% safety margin over and above the peak sudden rainfall and maximum discharge in the area adjoining the mine site. Sump capacity should also provide adequate retention period to allow proper settling of silt material.

 

(xi)                Dimension of the retaining wall at the toe of the dumps and OB benches within the mine to check run-off and siltation should be based on the rainfall data.

 

(xii)                        Crushers at the CHP should be operated with high efficiency bag filters/water sprinkling system should be provided to check fugitive emissions from crushing operations, conveyor system, haulage roads, transfer points, etc.

 

(xiii)      Drills should be wet operated only.

 

(xiv)                Controlled blasting should be practiced with use of delay detonators and only during daytime. The mitigative measures for control of ground vibrations and to arrest the fly rocks and boulders should be implemented.

 

(xv)        A progressive afforestation plan covering an area of 100ha shall be implemented, which includes reclaimed external OB dump, backfilled area, along ML boundary, along roads and infrastructure, vacant land and in area in township located outside the lease by planting native species in consultation with the local DFO/Agriculture Department. The density of the trees should be around 2500 plants per ha.

 

(xvi)           The backfilled quarry area shall be reclaimed with plantation/afforestation by planting native plant species in consultation with the local DFO/Agriculture Department. The density of the trees should be around 2500 plants per ha.

 

(xvii)     The company shall obtain approval of CGWA/CGWB Regional Office for use of groundwater if any, for mining operations.

 

(xviii)    Regular monitoring of groundwater level and quality should be carried out by establishing a network of exiting wells and construction of new peizometers. The monitoring for quantity should be done four times a year in pre-monsoon (May), monsoon (August), post-monsoon (November) and winter (January) seasons and for quality in May. Data thus collected should be submitted to the Ministry of Environment & Forests and tot eh Central Pollution Control Board quarterly within one month of monitoring.

 

(xix)       The Company shall put up artificial groundwater recharge measures for augmentation of groundwater resource. Any additional water requirement for mining operation shall bemet from rainwater use only. The project authorities should meet water requirement of nearby village(s) in case the village wells go dry due to dewatering of mine.

 

(xx)             Sewage treatment plant should be installed in the colony. ETP should also be provided for treatment of effluents form workshop, CHP and coal washery. There shall be zero discharge from the coal washery.

 

(xxi)       Besides carrying out regular periodic health check up of their workers, 10% of the workers identified from workforce engaged in active mining operations shall be subjected to health check up for occupational diseases and hearing impairment, if any, through an agency such as NIOH, Ahmedabad within a period of one year and the results reported to this Ministry and to DGMS.

 

(xxii)     Digital processing of the entire lease area using remote sensing technique should be done regularly once in 3 years for monitoring land use pattern and report submitted to MOEF and its Regional office at Bhubaneshwar.

 

(xxiii)    A Final Mine Closure Plan along with details of Corpus Fund should be submitted to the Ministry of Environment & Forests within one year for approval.

 

(xxiv)     Consent to Operate shall be obtained before expanding mining operations.

 

 

 

B.                General Conditions

 

(i)                  No change in mining technology and scope of working should be made without prior approval of the Ministry of Environment and Forests.

 

(ii)                No change in the calendar plan including excavation, quantum of mineral coal and waste should be made.

 

(iii)              Four ambient air quality monitoring stations should be established in the core zone as well as in the buffer zone for SPM, RPM, SO2 and NOx monitoring.  Location of the stations should be decided based on the meteorological data, topographical features and environmentally and ecologically sensitive targets in consultation with the State Pollution Control Board.

 

(iv)               Data on ambient air quality (SPM, RPM, SO2 and NOx) should be regularly submitted to the Ministry including its Regional Office and to the State Pollution Control Board and the Central Pollution Control Board once in six months.

 

(v)                 Fugitive dust emissions from all the sources should be controlled regularly monitored and data recorded properly. Water spraying arrangement on haul roads, wagon loading, dump trucks (loading and unloading) points should be provided and properly maintained.

 

(vi)               Adequate measures should be taken for control of noise levels below 85 dBA in the work environment. Workers engaged in blasting and drilling operations, operation of HEMM, etc should be provided with ear plugs/muffs.

 

(vii)             Industrial wastewater (workshop and wastewater from the mine) should be properly collected, treated so as to conform to the standards prescribed under GSR 422 (E) dated 19th May 1993 and 31st December 1993 or as amended from time to time before discharge. Oil and grease trap should be installed before discharge of workshop effluents.

 

(viii)           Vehicular emissions should be kept under control and regularly monitored. Vehicles used for transporting the mineral should be covered with tarpaulins and optimally loaded.

 

(ix)               Environmental laboratory should be established with adequate number and type of pollution monitoring and analysis equipment in consultation with the State Pollution Control Board.

 

(x)                 Personnel working in dusty areas should wear protective respiratory devices and they should also be provided with adequate training and information on safety and health aspects.

                Occupational health surveillance programme of the workers should be undertaken periodically to observe any contractions due to exposure to dust and to take corrective measures, if needed.

 

(xi)               A separate environmental management cell with suitable qualified personnel should be set up under the control of a Senior Executive, who will report directly to the Head of the company.

 

(xii)             The funds earmarked for environmental protection measures should e kept in separate account and should not be diverted for other purpose. Year-wise expenditure should be reported to this Ministry and its Regional Office at Bhubaneshwar.

 

(xiii)           The Regional Office of this Ministry located at Bhubaneshwar shall monitor compliance of the stipulated conditions. The Project authorities shall extend full cooperation to the office(s) of the Regional Office by furnishing the requisite data/ information/monitoring reports.

 

(xiv)           A copy of the will be marked to concerned Panchayat/ local NGO, if any, from whom any suggestion/representation has been received while processing the proposal.

(xv)             State Pollution Control Board should display a copy of the clearance letter at the Regional  Office, District Industry Centre and Collector’s Office/Tehsildar’s Office for 30 days.

 

(xvi)           The Project authorities should advertise at least in two local newspapers widely circulated around the project, one of which shall be in the vernacular language of the locality concerned within seven days of the clearance letter informing that the project has been accorded environmental clearance and a copy of the clearance letter is available with the State Pollution control Board and may also be seen at the website of the ministry of Environment & Forests at http://envfor.nic.in.

 

3.            The Ministry or any other competent authority may stipulate any further condition for environmental protection.

 

4.            Failure to comply with any of the conditions mentioned above may result in withdrawal of this clearance and attract the provisions of the Environment (Protection) Act, 1986.

 

5.            The above conditions will be enforced inter-alia, under the provisions of the Water (Prevention & Control of Pollution) Act, 1974, the Air (Prevention & Control of Pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public Liability Insurance Act, 1991 along with their amendments and Rules.

 

 

 

 

Copy to:

1.       Secretary, Ministry of Coal, Shastri Bhawan, New Delhi.

2.       Secretary, Department of Environment & Forests, Government of Jharkand, Secretariat, Ranchi.

3.       Chief Conservator of Forests, Regional office (EZ), Ministry of Environment & Forests, A/3 Chandrashekarpur, Bhubaneshwar – 751023.

4.       Chairman, Jharkand State Pollution Control Board, TA Building, HEC Complex, PO Dhurwa, Ranchi.

5.       Chairman, Central Pollution Control Board, CBD-cum-Office Complex, East Arjun Nagar, New Delhi -110032.

6.       Member-Secretary, Central Ground Water Authority, Ministry of Water Resources, Curzon Road Barracks, A-2, W-3 Kasturba Gandhi Marg, New Delhi.

7.       District Collector, Bokaro, Government of Jharkand, Dhanbad.

8.       Monitoring File                       9.                       Guard File                       10.                       Record File

 

 

 

 

 

Untitled Page